RERA projects in Devrung
9 projects under 9 MahaRERA registrations, registered 2017–2026. 22% have a completion date extended beyond the one promised.
Locality
9RERA projects
9Registrations
7Completion still due2 past their completion date
25 monthsMedian extension beyond promised date22% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 2 |
| 2024 | 2 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Devrung
9 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gangotri HeightsLaxmi Construction | PR1330002601929 | 15 Sep 2026 | 30 Jun 2027 | — | Not yet due | 0 |
| Vrundavan Park JaswandiShree Vastunirman Developers | PR1330002501246 | 16 Oct 2025 | 30 Jun 2028 | — | Not yet due | 0 |
| Arunoday PlazaSankalp Builders | PM1330002500818 | 17 Sep 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai Ram HeightsSai Ram Builders And Developers | P51700076874 | 3 Jul 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Shree ResidencyShree Developers | P51700056067 | 10 May 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Varsha HeightsB K Groups | P51700050218 | 27 Mar 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Vrundavan ParkShree Vastunirman Developers | P51700049309 | 7 Feb 2023 | 31 Mar 2025 | 31 Dec 2027 | Extended 33 mo | 0 |
| Vrundavan-IShree Vastucreation Developers | P51700014675 | 20 Dec 2017 | 30 Dec 2020 | 30 Jun 2022 | Extended 18 mo | 0 |
| VrundavanShree Vasturachana Developers | P51700003306 | 5 Aug 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
Other localities in Bhiwandi
Most active promoters
By projects registered here, as named on MahaRERA.
- Shree Vastunirman Developers2 projects
- B K Groups1 project
- Laxmi Construction1 project
- Sai Ram Builders And Developers1 project
- Sankalp Builders1 project
- Shree Developers1 project
- Shree Vastucreation Developers1 project
- Shree Vasturachana Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology