Skip to content

Shree Residency

Certificate Signed

Devrung, Thane 421302 |Promoter: Shree Developers

10 May 2024Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
1Building
59Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1RK, Shop59 units in all
Address
Survey No 10/53/1/A And 10/53/2/B, Devrung, BhiwandiPIN 421302
Designated bank account
82
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
10 May 2024
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005606710 May 202431 Mar 202731 Jul 2027Shree DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Main building859

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 59 units booked (0%), as the promoter reported to MahaRERA

1BHK · 56 units1RK · 1 unitShop · 2 units
TypeCarpet areaUnitsBooked
1BHK25.7 sq m · 277 sq ft140
1BHK31.2 sq m · 336 sq ft280
1BHK33.38 sq m · 359 sq ft140
1RK24.2 sq m · 260 sq ft10
Shop8.05 sq m · 87 sq ft10
Shop8.75 sq m · 94 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 74 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD PDF.pdf · uploaded 5 Apr 2024Source

Legal

  • Declaration Form BFORM B PROMOTER.pdf · uploaded 13 Apr 2024Source
  • Legal Title reportLEGAL TITLE REPORT 150423.pdf · uploaded 15 Apr 2024Source

Migrated

  • 1 PAN CardPAN CARD PDF.pdf · uploaded 5 Apr 2024Source
  • 1 a Details of encumbrances concerned to FinanceNO ENCUMBRANCES CONCERNED TO FINANCE_0001.pdf · uploaded 5 Apr 2024Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCES CONCERNED TO FINANCE_0001.pdf · uploaded 5 Apr 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN COPY_11zon.pdf · uploaded 5 Apr 2024Source
Show all 75 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC- SHREE RES.pdf · uploaded 5 Apr 2024Source
  • 1 CERSAI detailsDECLARATION OF CERSAI.pdf · uploaded 5 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SHREE DEVELOPERS_0001_11zon.pdf · uploaded 5 Apr 2024Source
  • 1 Proforma of Agreement for saleDRAFT AGREEMENT.pdf · uploaded 5 Apr 2024Source
  • 1 Proforma of Allotment letterMODEL ALLOTMENT LETTER_11zon.pdf · uploaded 5 Apr 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK ACCOUNT.pdf · uploaded 5 Apr 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION WITH RESPECT ALLOTMENT LATTER_0001.pdf · uploaded 5 Apr 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION FROM AGREEMENT.pdf · uploaded 5 Apr 2024Source
  • 1 Declaration about Commencement CertificateDECLARATION OF COMMENCEMNET CERTIFIACTE.pdf · uploaded 13 Apr 2024Source
  • 1 Declaration in FORM BFORM B PROMOTER.pdf · uploaded 13 Apr 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST SURESH K KENE.pdf · uploaded 13 Apr 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST SANJAY S FULAWARE.pdf · uploaded 13 Apr 2024Source
  • 3 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest - ravindra patil.pdf · uploaded 13 Apr 2024Source
  • 1 Other – TechnicalCC COMMENT.pdf · uploaded 13 Apr 2024Source
  • 2 Other – Technicalone plot one project.pdf · uploaded 13 Apr 2024Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT 150423.pdf · uploaded 15 Apr 2024Source
  • 1 Copy of Layout Approval (in case of layout)SHREE LAYOUT.pdf · uploaded 15 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SIGN.pdf · uploaded 15 Apr 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SIGN.pdf · uploaded 15 Apr 2024Source
  • 2 a Details of encumbrances concerned to FinanceLEGAL LITIGATION ENCUMBRANCES CERTIFICATE.pdf · uploaded 29 Apr 2024Source
  • 2 b Details of encumbrances concerned to LegalLEGAL LITIGATION ENCUMBRANCES CERTIFICATE.pdf · uploaded 29 Apr 2024Source
  • 3 Other – TechnicalCC COMMENT 1.pdf · uploaded 29 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - JUN 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - SEPT 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - JUN 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - SEPT 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - JUN 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - SEPT 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • 1 Other – TechnicalSHOW CAUSE NOTICE REPLY.pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- DEC 2024 SHREE DEV.pdf · uploaded 17 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - DEC 2024 SHREE DEV_11zon.pdf · uploaded 17 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 dec 2024- shree developers.pdf · uploaded 17 Mar 2025Source
  • Form 1FORM 1 - SHREE DEVLP - MAR 2025.pdf · uploaded 6 Aug 2025Source
  • Form 3FORM 3 - SHREE DEVELOPERS - MAR 25.pdf · uploaded 6 Aug 2025Source
  • Form 2FORM 2 - SHREE DEVL - MAR 25- SIGN.pdf · uploaded 6 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDISCL FOR SOLD UNSOLD - SHREE DEVELP - MAR 2025- SIGNED.pdf · uploaded 6 Aug 2025Source
  • Self-declaration of Quarterly ProgressSELF DECL - SHREE DEVELOPERS - MAR 25.pdf · uploaded 6 Aug 2025Source
  • Form 1FORM 1 - SHREE DEVELP - JUNE 2025.pdf · uploaded 22 Aug 2025Source
  • Form 2FORM 2 - SHREE DEVELP - JUN 2025.pdf · uploaded 22 Aug 2025Source
  • Form 3FORM 3 - SHREE DEVELP - JUN 2025- SIGNED.pdf · uploaded 22 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDISCL FOR SOLD UNSOLD - SHREE DEVELP - JUN 2025.pdf · uploaded 22 Aug 2025Source
  • Form 1FORM 1 - SHREE DEVLP - DEC 25.pdf · uploaded 13 Mar 2026Source
  • Form 2FORM 2 - SHREE DEVLP - DEC 25.pdf · uploaded 13 Mar 2026Source
  • Form 3FORM 3 - SHREE DEVLP - DEC 25.pdf · uploaded 13 Mar 2026Source
  • Disclosure of Sold and Booked InventoryFORM 3 - SHREE DEVLP - DEC 25.pdf · uploaded 13 Mar 2026Source
  • Form 1FORM 1 - SHREE DEVLP - SEPT 25.pdf · uploaded 13 Mar 2026Source
  • Form 2FORM 2 - SHREE DEVLP - SEPT 25.pdf · uploaded 13 Mar 2026Source
  • Form 3FORM 3 - SHREE DEVLP - SEPT 25.pdf · uploaded 13 Mar 2026Source
  • Disclosure of Sold and Booked InventoryFORM 3 - SHREE DEVLP - SEPT 25.pdf · uploaded 13 Mar 2026Source
  • Form 1FORM 1 - SHREE DEVELOPERS - MARCH 26 .pdf · uploaded 22 Jun 2026Source
  • Form 2FORM 2- SHREE DEVELOPERS - MARCH 26 - SIGNED.pdf · uploaded 22 Jun 2026Source
  • Form 3FORM 3 - SHREE DEVELOPERS - MARCH 26 - SIGNED.pdf · uploaded 22 Jun 2026Source
  • Disclosure of Sold and Booked InventoryFORM 3 - SHREE DEVELOPERS - MARCH 26 - SIGNED.pdf · uploaded 22 Jun 2026Source

Technical

  • DocumentPLAN COPY_11zon.pdf · uploaded 5 Apr 2024Source
  • Other – TechnicalCC COMMENT.pdf · uploaded 13 Apr 2024Source
  • Other – Technicalone plot one project.pdf · uploaded 13 Apr 2024Source
  • DocumentSHREE LAYOUT.pdf · uploaded 15 Apr 2024Source
  • Other – TechnicalCC COMMENT 1.pdf · uploaded 29 Apr 2024Source
  • Other – TechnicalSHOW CAUSE NOTICE REPLY.pdf · uploaded 12 Dec 2024Source

Technical (Architect)

  • DocumentFORM 1 SIGN.pdf · uploaded 15 Apr 2024Source
  • DocumentFORM 1 - JUN 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • DocumentFORM 1 - SEPT 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • DocumentFORM 1- DEC 2024 SHREE DEV.pdf · uploaded 17 Mar 2025Source

Technical (Engineer)

  • DocumentFORM 2 SIGN.pdf · uploaded 15 Apr 2024Source
  • DocumentFORM 2 - JUN 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • DocumentFORM 2 - SEPT 24 SHREE DEVELOPERS_11zon.pdf · uploaded 12 Dec 2024Source
  • Documentform 2 dec 2024- shree developers.pdf · uploaded 17 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Devrung, Bhiwandi taluka

Survey, CTS, gat or plot numbers

10/53/2/BSURVEY NO 10/53/1/A

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSyenergydessign—
Chartered accountantNiitn B Dhavan & Co—
EngineerA. S. Garyal & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology