Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 14% of its units are booked.

Devrung, Thane 421302 · by Sankalp Builders

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales14% booked4 of 28 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 17 Sep 2025, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002500818
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133000250081817 Sep 202531 Dec 202630 Apr 2027Sankalp BuildersProject page
Documents27

1 document held by Deedo, 26 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card Sankalp Builders.pdf · uploaded 22 May 2025Source
  • OthersDeclaration regarding Not Selling Units.pdf · uploaded 21 Aug 2025Source

Legal

  • Declaration Form BForm B Rs 500.pdf · uploaded 8 Jul 2025Source
  • OthersDeclaration AL.pdf · uploaded 14 Aug 2025Source
  • OthersDeclaration AFS.pdf · uploaded 14 Aug 2025Source
  • OthersAnnexure A.pdf · uploaded 14 Aug 2025Source
  • Declaration Form BLegal title report (5).pdf · uploaded 21 Aug 2025Source
Show all 27 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1Form 1 (30-09-2025).pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 2FORM - 2 .pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 3SIGNED- FORM 3.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 1Form 1 (31-12-2025).pdf · uploaded 17 Jun 2026Source
  • Withdrawal Update Form 231-12-2025 SANKALP BUILDERS .pdf · uploaded 17 Jun 2026Source
  • Withdrawal Update Form 3SIGNED FORM 3.pdf · uploaded 17 Jun 2026Source
  • Withdrawal Update Form 1FORM -1.pdf · uploaded 20 Jun 2026Source
  • Withdrawal Update Form 231-03-2026 SANKALP BUILDERS .pdf · uploaded 20 Jun 2026Source
  • Withdrawal Update Form 3FORM -3.pdf · uploaded 20 Jun 2026Source

Technical

  • DocumentAnnexure 'A' - Declaration cum Undertaking.pdf · uploaded 2 Jun 2025Source
  • OthersNo Encumbrances Legal.pdf · uploaded 2 Jun 2025Source
  • OthersCersai Declaration.pdf · uploaded 2 Jun 2025Source
  • Documentscan0964.pdf · uploaded 8 Jul 2025Source
  • OthersCC Verification.pdf · uploaded 14 Aug 2025Source
  • OthersForm 1 Architects Certificate (1).pdf · uploaded 14 Aug 2025Source
  • OthersForm 2 Engineer's Certificate.pdf · uploaded 18 Aug 2025Source
  • OthersPartnership Deed.pdf · uploaded 16 Sep 2025Source

Technical (Architect)

  • DocumentFORM -1.pdf · uploaded 20 Jun 2026Source

Technical (Engineer)

  • Document31-03-2026 SANKALP BUILDERS .pdf · uploaded 18 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Survey 77 Hissa No 24

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—28 units in all
Address
Survey No 77 Hissa No 24, DevrungPIN 421302
Village
Devrung, Bhiwandi taluka
Land area for this project
800 sq m (8,611 sq ft)
Permissible built-up area
1,473 sq m (15,854 sq ft)
Sanctioned built-up area
1,472 sq m (15,844 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
200
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey 77 Hissa No 24

Land as published on MahaRERA's project page

Survey 77 Hissa No 24

Boundaries

North
Open Plot
South
Open Plot
East
Open Plot
West
Open Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking28 units

28 units registered

— · 28 units
TypeCarpet areaUnits
——28

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhiraj Bharat Patil—
Chartered accountantDeepak Himaji Purohit—
Chartered accountantSantosh Kumar Padhi—
EngineerAditya Rajan Deshmukh—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Devrung

All 9 projects in Devrung · Compare Arunoday Plaza with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology