Vrundavan Park
Deedo IDDP-THN-HQS9Completion was pushed back 2 years and 9 months, to Dec 2027; no MahaRERA orders on record; 63% of its units are booked.
Devrung, Thane 421302 · Promoter: Shree Vastunirman Developers
Completion was pushed back 2 years and 9 months, to Dec 2027
- This projectRegistered 7 Feb 2023, completion promised 31 Mar 2025, revised to 31 Dec 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Jai - Bldg No 1 Wing A Wing B8 floors · 70 units63% booked
- Jui - Bldg No 2 Wing A Wing B Wing C8 floors
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700049309
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700049309 | 7 Feb 2023 | 31 Mar 2025 | 31 Dec 2027 | Shree Vastunirman Developers | Project page |
Documents145
2 documents held by Deedo, 143 filings listed on MahaRERA's project page
Finance
- PAN CardPAN - SHREE VASTUNIRMAN DEVELOPERS.pdf · uploaded 16 Dec 2022Source
Legal
Migrated
- 1 PAN CardPAN - SHREE VASTUNIRMAN DEVELOPERS.pdf · uploaded 16 Dec 2022Source
Show all 145 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)SHEET NO 1_compressed.pdf · uploaded 29 Dec 2022Source
- 1 a Details of encumbrances concerned to FinanceDeclaration Form B - Jai.pdf · uploaded 2 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalDeclaration Form B - Jai.pdf · uploaded 2 Jan 2023Source
- 1 Declaration in FORM BFORM B - JAI.pdf · uploaded 2 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect - UPDATED.pdf · uploaded 3 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200256609900_For_Asset_Based_Search_03_01_2023_12_16_29_759 (1).pdf · uploaded 3 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Certificate of Engineer - Vrundavan Park Jai.pdf · uploaded 5 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN 2-3 REDUCED.pdf · uploaded 10 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC Vrundavan Park resize.pdf · uploaded 10 Jan 2023Source
- 1 Copy of the legal title reportrera.pdf · uploaded 12 Jan 2023Source
- 1 Declaration about Commencement CertificateCOMMENCEMENT DECLARATION.pdf · uploaded 12 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE REDUCED.pdf · uploaded 12 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsOTHER FIRM RERA DISCLOSURE SEEMA NIKAM.pdf · uploaded 12 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsOTHER FIRM RERA DISCLOSURE.pdf · uploaded 12 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterNO DEVIATION SALE DRAFT.pdf · uploaded 12 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION SALE DRAFT.pdf · uploaded 12 Jan 2023Source
- 2 a Details of encumbrances concerned to FinanceDeclaration encumbrances - Jai.pdf · uploaded 27 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalDeclaration encumbrances - Jai.pdf · uploaded 27 Jan 2023Source
- 1 Proforma of Agreement for saleFINAL Agreement for Sale _ Draft Vrundavan Park Jai AS PER RERA.pdf · uploaded 27 Jan 2023Source
- 1 Proforma of Allotment letterFINAL RERA Allotment Letter (1) - JAI.pdf · uploaded 27 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of seperate bank account.pdf · uploaded 27 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- MARCH 2023.pdf · uploaded 4 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- JUNE 2023.pdf · uploaded 4 Dec 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- SEP 2023.pdf · uploaded 4 Dec 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on 31-03-2023.pdf · uploaded 8 Dec 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on June 2023.pdf · uploaded 8 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Sept 2023.pdf · uploaded 8 Dec 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 31-03-2023.pdf · uploaded 8 Dec 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 30-06-2023.pdf · uploaded 8 Dec 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 30-09-2023.pdf · uploaded 8 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_ Vrundavan for FY 22-23.pdf · uploaded 8 Dec 2023Source
- 1 Disclosure of sold/ booked inventoryCircular 29 - Jai Vastunirman.pdf · uploaded 23 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VRUNDAVAN PARK JAI as on DEC 2023.pdf · uploaded 8 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Dec 2023.pdf · uploaded 13 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Vrundavan Park Jai as on Dec 2023.pdf · uploaded 13 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 3 Apr 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 VRUNDAVAN PARK JAI as on March 2024.pdf · uploaded 19 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on March 2024.pdf · uploaded 20 Apr 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 31-03-2024.pdf · uploaded 20 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Vrundavan Park Jai as on June 2024.pdf · uploaded 26 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on June 2024.pdf · uploaded 3 Aug 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Vrundavan Park Jai as on June 2024.pdf · uploaded 3 Aug 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 VRUNDAVAN PARK JAI Sep 2024 (1).pdf · uploaded 14 Oct 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 30-09-2024.pdf · uploaded 20 Oct 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Sep 2024.pdf · uploaded 20 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Vrundavan Park Jai as on December 2024.pdf · uploaded 8 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2022-23.pdf · uploaded 13 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-23.pdf · uploaded 13 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 13 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Vrundavan Park Jai as on 31-12-2024.pdf · uploaded 15 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Dec 2024.pdf · uploaded 15 Jan 2025Source
- 2 Declaration in FORM BFORM B (1).pdf · uploaded 16 Jan 2025Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 16 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 jai.pdf · uploaded 16 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 16 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2024.pdf · uploaded 28 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_ Vrundavan Park Jai for FY 23-24.pdf · uploaded 28 Jan 2025Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 FY 2023-24.pdf · uploaded 28 Jan 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2024.pdf · uploaded 8 Feb 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2024.pdf · uploaded 8 Feb 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 2024.pdf · uploaded 8 Feb 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 2024.pdf · uploaded 8 Feb 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2023 Form 1.pdf · uploaded 8 Feb 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - September 2023.pdf · uploaded 8 Feb 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 2023.pdf · uploaded 8 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2023.pdf · uploaded 8 Feb 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - June 2024.pdf · uploaded 8 Feb 2025Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2024.pdf · uploaded 8 Feb 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Sept 2024.pdf · uploaded 8 Feb 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - March 2024.pdf · uploaded 8 Feb 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Sept 2023.pdf · uploaded 8 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - June 2023.pdf · uploaded 8 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - March 2023.pdf · uploaded 8 Feb 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 2023.pdf · uploaded 8 Feb 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on March 2024.pdf · uploaded 8 Feb 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 2024.pdf · uploaded 8 Feb 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 2024.pdf · uploaded 8 Feb 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Sep 2024.pdf · uploaded 8 Feb 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on June 2024.pdf · uploaded 8 Feb 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Dec 2023.pdf · uploaded 8 Feb 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on Sept 2023.pdf · uploaded 8 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on June 2023.pdf · uploaded 8 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Vrundavan Park Jai as on March 2023.pdf · uploaded 8 Feb 2025Source
- Form 1Form 1 - Vrundavan Park Jai as on June 2025.pdf · uploaded 12 Aug 2025Source
- Form 2Form 2 - Vrundavan Park Jai as on June 2025.pdf · uploaded 12 Aug 2025Source
- Form 3Form 3 - Vrundavan Park Jai as on June 2025.pdf · uploaded 12 Aug 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park Jai as on June 2025.pdf · uploaded 12 Aug 2025Source
- Form 1Form 1 - Vrundavan Park Jai as on March 2025.pdf · uploaded 9 Sep 2025Source
- Form 2Form 2 - Vrundavan Park Jai as on March 2025.pdf · uploaded 9 Sep 2025Source
- Form 3Form 3 - Vrundavan Park Jai as on March 2025.pdf · uploaded 9 Sep 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park Jai as on March 2025.pdf · uploaded 9 Sep 2025Source
- Form 1Form 1 - Vrundavan Park Jai as on Sept 2025.pdf · uploaded 19 Oct 2025Source
- Form 2Form 2 - Vrundavan Park Jai as on Sept 2025.pdf · uploaded 19 Oct 2025Source
- Form 3Form 3 - Vrundavan Park Jai as on Sept 2025.pdf · uploaded 19 Oct 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park Jai as on Sept 2025.pdf · uploaded 19 Oct 2025Source
- Form 1Form 1 - Vrundavan Park Jai as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Form 2Form 2 - Vrundavan Park Jai as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Form 3Form 3 - Vrundavan Park Jai as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park Jai as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Form 1Form 1 - Vrundavan Park as on March 2026.pdf · uploaded 14 May 2026Source
- Form 2Form 2 - Vrundavan Park as on March 2026.pdf · uploaded 14 May 2026Source
- Form 3Form 3 - Vrundavan Park as on March 2026.pdf · uploaded 14 May 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park as on march 2026.pdf · uploaded 14 May 2026Source
- Form 1Form -1 Vrundavan Park as on june 2026.pdf · uploaded 15 Jul 2026Source
- Form 2Form 2 - Vrundavan Park as on June 2026.pdf · uploaded 15 Jul 2026Source
- Form 3Form 3 - Vrundavan Park as on June 2026.pdf · uploaded 15 Jul 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Vrundavan Park as on june 2026.pdf · uploaded 15 Jul 2026Source
Technical
Technical (Architect)
- DocumentForm 1 - Vrundavan Park Jai as on June 2024.pdf · uploaded 26 Jul 2024Source
- DocumentFORM -1 VRUNDAVAN PARK JAI Sep 2024 (1).pdf · uploaded 14 Oct 2024Source
- DocumentForm 1 - Vrundavan Park Jai as on December 2024.pdf · uploaded 8 Jan 2025Source
- DocumentFORM 1 jai.pdf · uploaded 16 Jan 2025Source
- DocumentForm 1 - Dec 2024.pdf · uploaded 28 Jan 2025Source
- DocumentForm 1 - March 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - June 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - September 2023.pdf · uploaded 8 Feb 2025Source
- DocumentDec 2023 Form 1.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - March 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - June 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - Sept 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 1 - Dec 2024.pdf · uploaded 8 Feb 2025Source
Technical (Engineer)
- DocumentForm 2 - Vrundavan Park Jai as on June 2024.pdf · uploaded 3 Aug 2024Source
- DocumentForm 2 - Vrundavan Park Jai as on Sep 2024.pdf · uploaded 20 Oct 2024Source
- DocumentForm 2 - Vrundavan Park Jai as on Dec 2024.pdf · uploaded 15 Jan 2025Source
- DocumentForm 2.pdf · uploaded 16 Jan 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on March 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on June 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on Sept 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on Dec 2023.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on March 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on June 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Vrundavan Park Jai as on Sep 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Dec 2024.pdf · uploaded 8 Feb 2025Source
- DocumentForm 2 - Dec 2024.pdf · uploaded 8 Feb 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals94/19, 94/23
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK70 units in all
- Address
- 94/19, 94/23, 94/25, Mdr To Devrung Village Road, DevrungPIN 421302
- Village
- Devrung, Bhiwandi taluka
- Location
- 19.22586, 73.13280
- Designated bank account
- 82
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- 5
- South
- 94-25
- East
- 94-20
- West
- 94-18
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking70 units
44 of 70 units booked (63%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Jai - Bldg No 1 Wing A Wing B | 1BHK | 30.16 sq m · 325 sq ft | 42 | 28 |
| Jai - Bldg No 1 Wing A Wing B | 2BHK | 46.85 sq m · 504 sq ft | 28 | 16 |
| Jui - Bldg No 2 Wing A Wing B Wing C | 1BHK | — | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.