RERA projects in Kon (Ct)
34 projects under 34 MahaRERA registrations, registered 2017–2025. 9% have a completion date extended beyond the one promised.
Locality
34RERA projects
34Registrations
21Completion still due13 past their completion date
45 monthsMedian extension beyond promised date9% of registrations extended
1Regulatory caseson 1 project
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 2 |
| 2019 | 3 |
| 2020 | 3 |
| 2021 | 1 |
| 2022 | 7 |
| 2023 | 8 |
| 2024 | 3 |
| 2025 | 5 |
Projects in Kon (Ct)
34 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aai Mauli Park Building BHendar Laxman Mhatre | P51700081073 | 26 Dec 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai Darshan D WingTrimurti Enterprises | PR1330002501864 | 24 Dec 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Millat ArcadeR K Buildcon | P51700080861 | 23 Jul 2025 | 30 Jun 2026 | — | Promised date passed | 0 |
| Kalyan EliteKalyan Buildcon | P51700080574 | 16 Jun 2025 | 31 Oct 2027 | — | Not yet due | 0 |
| Kalyan VatikaKalyan Avenue | P51700079636 | 17 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Magus City Tower 2 LunarMagus Infra Tech Private Limited | P51700077802 | 7 Nov 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| The LivinSupreme Realty | P51700055755 | 16 Apr 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Tahoora ComplexShree Harekrishna Realtor | P51700055023 | 26 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai Nida ApartmentPrashant Wagaji Gawande | P51700054040 | 27 Dec 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Namo MaximaViren Kishor Jain | P51700053313 | 27 Oct 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Kalyan SurabhiKalyan Buildcon | P51700050410 | 12 Apr 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Shree Laxman ApartmentShri Gajanan Enterprises | P51700050282 | 1 Apr 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Amruta ParkCheroba Homes | P51700049842 | 6 Mar 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Aai Mauli ParkHendar Laxman Mhatre | P51700049466 | 14 Feb 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Kalyan AashiyanaAl Bruj Developers | P51700049257 | 3 Feb 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Kalyan SquareKagvin Ventures | P51700048508 | 3 Jan 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Laxman ResidencyCrystal Krishraj | P51700048029 | 7 Dec 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Magus City Tower 1 SeleneMagus Infratech Private Limited | P51700045444 | 18 May 2022 | 30 Apr 2027 | — | Not yet due | 0 |
| Shree Sai Saburi Apartment-Building BShree Saishraddha Enterprises | P51700034808 | 28 Apr 2022 | 30 Mar 2026 | — | Promised date passed | 0 |
| AtlanticRiddhi Siddhi Enterprises | P51700034411 | 5 Apr 2022 | 31 Mar 2027 | — | Not yet due | 0 |
| Kalyan ResidencySm Life Space Private Limited | P51700034384 | 5 Apr 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Kalyan ViharHonest Developers | P51700033988 | 14 Mar 2022 | 31 Dec 2029 | — | Not yet due | 0 |
| Sai Krupa ApartmentVinit Subhash Mukadam | P51700033770 | 8 Mar 2022 | 22 Nov 2024 | — | Promised date passed | 0 |
| Sai DarshanTrimurti Enterprises | P51700029507 | 4 Jun 2021 | 30 Apr 2027 | — | Not yet due | 0 |
| Prince AvenueShakti Developers | P51700025661 | 1 Jul 2020 | 30 Jun 2027 | — | Not yet due | 0 |
Other localities in Bhiwandi
Most active promoters
By projects registered here, as named on MahaRERA.
- Hendar Laxman Mhatre2 projects
- Honest Developers2 projects
- Kalyan Buildcon2 projects
- Magus Infratech Private Limited2 projects
- Shree Saishraddha Enterprises2 projects
- Trimurti Enterprises2 projects
- Al Bruj Developers1 project
- Asmeeta Infratech Limited1 project
- Cheroba Homes1 project
- Continental Sidhant Reality1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology