Badlapur (M Cl), Thane

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects715
Registrations752some projects hold several
Completion still due218534 past their date
Median extension4 months35% of registrations extended
Regulatory cases44on 9 projects
Badlapur (M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

752 MahaRERA registrations in Badlapur (M Cl)

13 completed53 not yet due165 extended, not yet due521 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Badlapur (M Cl)

715 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gokul HeightsSairaj DevelopersPR133000260188411 Sep 202631 Dec 202931 Dec 2029Not yet due0
Chandrama S ChslS R InfraaPM133000260135529 Jul 202631 Mar 202931 Jul 2029Extended 4 mo0
Mery Villa ChslDilip Tukaram SurvalP5170008112411 May 202631 Dec 202730 Apr 2028Extended 4 mo0
Gurukrupa Builders And DevelopersGurukrupa Builders And DevelopersPM13300026003365 May 202631 Dec 203030 Apr 2031Extended 4 mo0
Shrey SwapnaShree Sai Builders And DevelopersPM13300025026376 Mar 202631 Oct 202729 Feb 2028Extended 4 mo0
Gouri Aangan CHSU S ConstructionsPM133000250237316 Feb 202631 Mar 202731 Jul 2027Extended 4 mo0
Swanand Niwas Co Op Housing Society LtdKasturi Life SpacePM133000250208316 Jan 202631 Dec 202930 Apr 2030Extended 4 mo0
Shivam NirvaanaM K RealtyPM133000250207413 Jan 202631 Dec 203030 Apr 2031Extended 4 mo0
Saurabh SankulS K DevelopersP517000810802 Jan 202631 Dec 202831 Dec 2028Not yet due0
Saurabh ChslShree Gurumanya ConstructionsPM133000250194830 Dec 202531 May 202830 Sep 2028Extended 4 mo0
Ranimaa Devi ChsThakur ConstructionPR133000250181217 Dec 202531 Dec 202730 Apr 2028Extended 4 mo0
Adiyogi MajestyAdiyogi InfraPR133000250152421 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Sai Chhaya Co.op. Housing SocietyPrakash Jagannath ManePM13300025014097 Nov 202531 Dec 202631 Dec 2026Not yet due0
Shiv-KutirKoutilya EnterprisesPR13300025014147 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Jyoti Jagannath HeritageMayur GroupPM13300025013843 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Prime HeightsPrime EnterprisesP5170008103024 Oct 202528 Feb 202928 Jun 2029Extended 4 mo0
Sai MatoshreeUnnadhra Lifespaces LLPPM133000250129820 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Grand Unity ResidencesYash EnterprisesPM133000250121513 Oct 202531 May 202831 May 2028Not yet due0
James Residency Phase 3Sudhir Damodar GhatnekarP5170008100910 Oct 202530 Jun 202730 Jun 2027Not yet due0
Shree Sadguru KrupaShree Sai Aashray DevelopersPR133000250117710 Oct 202531 Dec 202630 Apr 2027Extended 4 mo0
Om Ambika Darshan Chs LtdSharvi EnterprisesPR13300025010913 Oct 202531 Dec 202831 Dec 2028Not yet due0
Om Shiv DarshanVinayak Enterprises DevelopersP517000810033 Oct 202531 Jul 202631 Jul 2026Promised date passed0
Aishwarya Sadan Co-Op Housing Society Ltd.Nitant Narendra DesaiPR133000250084419 Sep 202531 Dec 202830 Apr 2029Extended 4 mo0
Vishnu KrupaPatil Reality GroupPM133000250081116 Sep 202531 Dec 202730 Apr 2028Extended 4 mo0
Patil Highlands Phase II Wing BSas InfraP5170008093522 Aug 202531 Dec 202830 Apr 2029Extended 4 mo0

Most active promoters

  1. Mohan Hardasmal Tharwani7 projects
  2. Raj Group6 projects
  3. Ashish Waman Gole5 projects
  4. M K Patil Developers5 projects
  5. Mohan Lifespaces LLP5 projects
  6. Panvelkar Infrastructures Private Limited5 projects
  7. Sai Shradha Developers5 projects
  8. Bhavani Enterprises4 projects
  9. Bhushan Nandkishor Patkar4 projects
  10. Sairaj Developers4 projects
Data through23 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology