RERA projects in Sonavale
8 projects under 8 MahaRERA registrations, registered 2017–2024. 38% have a completion date extended beyond the one promised.
Locality
8RERA projects
8Registrations
2Completion still due6 past their completion date
4 monthsMedian extension beyond promised date38% of registrations extended
0Regulatory casesnone on MahaRERA's lists
20Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 2 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 1 |
Projects in Sonavale
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Atmiya CrownAtmiya Realty | P51700056458 | 5 Jun 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Atmiya BlissAkshar Group | P51700031540 | 25 Oct 2021 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Atmiya ResidencyAkshar Infra | P51700024195 | 24 Jan 2020 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Trishul Golden VedaA Plus Life Space | P51700020374 | 9 Apr 2019 | 15 Apr 2023 | 31 Aug 2023 | Extended 4 mo | 0 |
| Trishul Golden VilleA Plus Life Space | P51700015246 | 8 Feb 2018 | 26 Dec 2022 | 26 Dec 2022 | Promised date passed | 0 |
| Atmiya HeightsAkshar Group | P51700015091 | 24 Jan 2018 | 30 Dec 2025 | 30 Dec 2025 | Promised date passed | 0 |
| Atmiya LuxuriaAkshar Builders And Developer | P51700009857 | 22 Aug 2017 | 16 Oct 2021 | 16 Oct 2021 | Promised date passed | 0 |
| Golden ValleyA Plus Realty | P51700002661 | 2 Aug 2017 | 3 Feb 2023 | 3 Feb 2023 | Promised date passed | 0 |
Other localities in Ambarnath
Most active promoters
By projects registered here, as named on MahaRERA.
- Akshar Group2 projects
- A Plus Life Space2 projects
- Akshar Builders And Developer1 project
- Akshar Infra1 project
- A Plus Realty1 project
- Atmiya Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology