RERA projects in Kulgaon
11 projects under 11 MahaRERA registrations, registered 2024–2026. 91% have a completion date extended beyond the one promised.
Locality
11RERA projects
11Registrations
11Completion still due0 past their completion date
4 monthsMedian extension beyond promised date91% of registrations extended
0Regulatory casesnone on MahaRERA's lists
22Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2024 | 1 |
| 2025 | 0 |
| 2026 | 10 |
Projects in Kulgaon
11 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Jay Vijayshri Co. Op. Hsc. SocK S Builders & Developers | PM1330002602323 | 15 Oct 2026 | 31 Mar 2030 | — | Not yet due | 0 |
| Sudarshan ViharEeshwar Construction | PR1330002601354 | 29 Jul 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Vishnu Krupa Co operative Housing SocietyKrishna Buildcon | PM1330002601125 | 9 Jul 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| AaryakrushnaSkyline Developers | PR1330002600385 | 11 May 2026 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Shree Shivsai Co. Op. Hsg. Soc.Shiv Sai Developers | PR1330002503029 | 24 Mar 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Om Sagar ParkTown Icon | PR1330002503014 | 23 Mar 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Shilpa Adarsh Co Op Housing Society LimitedShree Rameshwaram Builders & Developers | PM1330002502834 | 16 Mar 2026 | 30 Sep 2029 | 30 Jan 2030 | Extended 4 mo | 0 |
| Sharmila SadanShree Vedant Krupa | PR1330002502539 | 2 Mar 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Babaji CHSRelation Developers | PR1330002502525 | 27 Feb 2026 | 20 Mar 2028 | 20 Jul 2028 | Extended 4 mo | 0 |
| Laxmivihar Co-Operative Housing Society LimitedShree Saraswati Developers | PM1330002502361 | 16 Feb 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| S P ArcadeShree Dattakrupa Associates | P51700078378 | 10 Dec 2024 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
Other localities in Ambarnath
Most active promoters
By projects registered here, as named on MahaRERA.
- Eeshwar Construction1 project
- Krishna Buildcon1 project
- K S Builders & Developers1 project
- Relation Developers1 project
- Shiv Sai Developers1 project
- Shree Dattakrupa Associates1 project
- Shree Rameshwaram Builders & Developers1 project
- Shree Saraswati Developers1 project
- Shree Vedant Krupa1 project
- Skyline Developers1 project
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology