RERA projects in Nandivli Tarfe Panchnand

10 projects under 10 MahaRERA registrations, registered 2019–2026. 50% have a completion date extended beyond the one promised.

Locality
10RERA projects
10Registrations
8Completion still due2 past their completion date
9 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
16Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191
20201
20213
20220
20231
20241
20252
20261

Projects in Nandivli Tarfe Panchnand

10 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vinayak CrownVinayak ConstructionPM133000250271111 Mar 202630 Jun 202830 Jun 2028Not yet due0
Nivasa Green City Phase 1Nivasa DevelopersP5170008007022 Apr 202531 Dec 203030 Apr 2031Extended 4 mo0
SwamiSwapn Vastu Builders And DevelopersP5170007954211 Mar 202530 Jan 202930 Jan 2029Not yet due0
Yesu Anand ResidencyVijay Ananta PatilP5170005627922 May 202431 Dec 2026—Not yet due0
Shree Anandi ImperialJai Malhar Builders & DevelopersP5170004858510 Jan 202331 Dec 202630 Apr 2027Extended 4 mo0
Suman ArcadeShreekrupa ConstructionP5170003134523 Oct 202131 Dec 202431 Dec 2026Extended 24 mo0
Shlok ApartmentChetan Abhimanyu PatilP5170003009931 Jul 202131 Dec 202431 Dec 2025Extended 12 mo0
Mokshit MajestaAshapura Builders And DevelopersP5170002943429 May 202131 Mar 202431 Dec 2024Extended 9 mo0
Yesu Anand HeightsYesu Anand EnterprisesP517000247582 Mar 202018 Nov 202618 Nov 2026Not yet due0
Mahalaxmi Heights Phase 2Mahalaxmi Builders & DevelopersP5170002086915 May 201931 Dec 202631 Dec 2026Not yet due0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ashapura Builders And Developers1 project
  2. Chetan Abhimanyu Patil1 project
  3. Jai Malhar Builders & Developers1 project
  4. Mahalaxmi Builders & Developers1 project
  5. Nivasa Developers1 project
  6. Shreekrupa Construction1 project
  7. Swapn Vastu Builders And Developers1 project
  8. Vijay Ananta Patil1 project
  9. Vinayak Construction1 project
  10. Yesu Anand Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology