RERA projects in Badlapur
3 projects under 3 MahaRERA registrations, registered 2026–2026. 33% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
3Completion still due0 past their completion date
4 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
14Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2026 | 3 |
Projects in Badlapur
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| KalpataruSuraj Builders | PR1330002602159 | 6 Oct 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| City Pride NxAbhishek Buildcon | PM1330002601687 | 27 Aug 2026 | 31 Mar 2030 | 31 Mar 2030 | Not yet due | 0 |
| Sai UniversePinnacle Corporation | PR1330002601334 | 28 Jul 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
Other localities in Ambarnath
Most active promoters
By projects registered here, as named on MahaRERA.
- Abhishek Buildcon1 project
- Pinnacle Corporation1 project
- Suraj Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology