Delayed projects in Thane
1,161 MahaRERA projects in Thane are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 7 of 24.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Aadinath ResidencyShree Mahavir Enterpises | Anjur | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Anthony AnnexMagnum Enterprises | Thane (M Corp.) | Dec 2022 | Aug 2024 | 3 yrs 11 mo late |
| Arya SapphireVaastudeal Developers Pvt. Ltd. | Asade | Dec 2022 | Jun 2024 | 3 yrs 11 mo late |
| Atrinandan HeightsHeramb Construction | Kalyan | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Banjara Hills Sector 7Seema Developers | Kharade | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Bhakti ParkMilan Jayantilal Salot | Bhayandar | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Blue BellRavi Developments | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Deep HeightsSai Developers | Dombivli | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Deepali ResidencyParekh Infraprojects | Badlapur (M Cl) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Evergreen Residency Wing A, B, D, EBalaji Construction | Badlapur (M Cl) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Gaurav SaffronRavi Developments | Mirabhayandar (M Corp.) | Dec 2022 | Jun 2026 | 3 yrs 11 mo late |
| Gulmohar Apartment Building B Upper Three FloorsChaitanya Enterprises | Thane | Dec 2022 | Jun 2023 | 3 yrs 11 mo late |
| HerbeliaAcme Housing India Private Limited | Thane (M Corp.) | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Intelligentia Business Park Vashi by Haware PropertiesHaware Finance Pvt. Ltd. | Navi Mumbai (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Jai Guruji TowerOm Sai Construction And Developers | Gauripada | Dec 2022 | Jun 2023 | 3 yrs 11 mo late |
| Jsk ParkShiv Sai Developers | Washind (Ct) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Jyoti DarshanKanso Realty | Mira Bhayandar (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Lake ViewSai Mahima Infradevelopers LLP | Navi Mumbai (M Corp.) | Dec 2022 | Dec 2024 | 3 yrs 11 mo late |
| Lalbaug DarshanVishal R Group & Enterprises | Kon (Ct) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Leela ApartmentShubham Builders And Developers | Bhayandar | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Lifestyle City Kalyan PlatanoNirmal Lifestyle (Kalyan) Private Limited | Vadavali Kh. | Dec 2022 | May 2024 | 3 yrs 11 mo late |
| MaansarovarMeridian Buildpro Private Limited | Panchpakhadi | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Madhu VillaShree Krishna Enterprises | Chikanghar | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Mata Ramai PalaceSanidhya Enterprises | Belavli | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Medtiya RavirajS.n. Builders | Mira Bhayandar (M Corp.) | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| MoonstoneS K Enterprise | Thane | Dec 2022 | Mar 2025 | 3 yrs 11 mo late |
| N G Valencia Phase IRNA Builders (NG) | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Om Sai Residency NxOm Sai Residency | Manda | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Panvelkar SrushtiKashikar Infrastructures Private Limited | Shahapur | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Pooja AnganSairaj Projects | Ghansoli | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Pushpanjali Residency Phase IIIShriraam Pioneer Developers Private Limited | Owale | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Panvelkar Estate - GreenfordPanvelkar Infrastructures Private Limited | Badlapur | Dec 2022 | Dec 2024 | 3 yrs 11 mo late |
| Raj EnclaveRatna Priya Builders | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Sai DarshanShree Sai Enterprises | Badlapur (M Cl) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Sai GloryKd Vision Developers | Washind (Ct) | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Satyam EleganzaPanorama Realty | Ambarnath(M Cl) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Shabri ResidencyShree Ayyappa Constructions | Ambarnath | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Shakti AuraShakti Developers | Ghansoli | Dec 2022 | Jun 2023 | 3 yrs 11 mo late |
| Shree Gaurang | Naupada | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Shree Mandar ChslV. V. Enterprises | Dombivli | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Shree Nandan Park B WingLaxmi Construction | Titwala | Dec 2022 | Dec 2024 | 3 yrs 11 mo late |
| Shree VallabhSalasar Property Developers | Thane | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Shubham HeightsShyamsunder Radhyshyam Agrawal | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Swastik RiverviewLucky Homes | Kalambhe | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Sahyadri Residency Phase INirman Developers | Murbad | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Sai Heights Phase II A And B WingSai Siddhi Developers | Kalyandombivali (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Shreedham ExcellencyShreedham Construction Private Limited | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Silver SpringAnudan Properties Private Limited | Thane (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Tirupati HeightsShri Tirupati Realty | Mirabhayandar (M Corp.) | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| VaibhavGavdevi Shelter | Badlapur (M Cl) | Dec 2022 | Jun 2025 | 3 yrs 11 mo late |
Delayed projects by district
All MaharashtraPune · 2,219Thane · 1,161Raigarh · 1,042Mumbai Suburban · 996Nashik · 482Palghar · 364Nagpur · 323Aurangabad · 243Mumbai City · 243Satara · 228Ratnagiri · 193Sangli · 176Solapur · 156Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology