Deedo IDDP-THN-TKEMCompletion was pushed back 6 months to Jun 2023, and that date has passed too; no MahaRERA orders on record; 41% of its units are booked.
Ghansoli, Thane 400701 · by Shakti Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 6 months to Jun 2023, and that date has passed too
- This projectRegistered 20 Feb 2019, completion promised 30 Dec 2022, revised to 30 Jun 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700019646
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700019646 | 20 Feb 2019 | 30 Dec 2022 | 30 Jun 2023 | Shakti Developers | Project page |
Documents321
2 documents held by Deedo, 319 filings listed on MahaRERA's project page
Finance
- PAN Cardshakti developers pan card.pdf · uploaded 31 Jan 2019Source
Legal
Show all 321 documentsShow fewer documents
Migrated
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 Engineer Certificate final.pdf · uploaded 11 Jan 2019Source
- 1 Certificates of CA (Form 3)Form 3 CA Certificate.pdf · uploaded 11 Jan 2019Source
- 1 Proforma of Allotment letterallotment.pdf · uploaded 11 Jan 2019Source
- 1 Otherplot agreement_reduced size.pdf · uploaded 11 Jan 2019Source
- 1 PAN Cardshakti developers pan card.pdf · uploaded 31 Jan 2019Source
- 1 Details of encumbrancesDeclaraion No Encumbrances.pdf · uploaded 31 Jan 2019Source
- 1 Copy of the legal title reporttitle.pdf · uploaded 13 Feb 2019Source
- 1 Copy of Layout Approval (in case of layout)pdf 1.pdf · uploaded 13 Feb 2019Source
- 2 Copy of Layout Approval (in case of layout)pdf 2.pdf · uploaded 13 Feb 2019Source
- 3 Copy of Layout Approval (in case of layout)pdf 3.pdf · uploaded 13 Feb 2019Source
- 4 Copy of Layout Approval (in case of layout)pdf 4.pdf · uploaded 13 Feb 2019Source
- 5 Copy of Layout Approval (in case of layout)pdf 5.pdf · uploaded 13 Feb 2019Source
- 6 Copy of Layout Approval (in case of layout)pdf 6.pdf · uploaded 13 Feb 2019Source
- 7 Copy of Layout Approval (in case of layout)pdf 7.pdf · uploaded 13 Feb 2019Source
- 8 Copy of Layout Approval (in case of layout)pdf 8.pdf · uploaded 13 Feb 2019Source
- 9 Copy of Layout Approval (in case of layout)pdf 9.pdf · uploaded 13 Feb 2019Source
- 10 Copy of Layout Approval (in case of layout)pdf 9.pdf · uploaded 13 Feb 2019Source
- 11 Copy of Layout Approval (in case of layout)pdf 11.pdf · uploaded 13 Feb 2019Source
- 12 Copy of Layout Approval (in case of layout)pdf 12.pdf · uploaded 13 Feb 2019Source
- 13 Copy of Layout Approval (in case of layout)pdf 13.pdf · uploaded 13 Feb 2019Source
- 1 Building Plan Approval (IOD)pdf 1.pdf · uploaded 13 Feb 2019Source
- 2 Building Plan Approval (IOD)pdf 2.pdf · uploaded 13 Feb 2019Source
- 3 Building Plan Approval (IOD)pdf 3.pdf · uploaded 13 Feb 2019Source
- 4 Building Plan Approval (IOD)pdf 4.pdf · uploaded 13 Feb 2019Source
- 5 Building Plan Approval (IOD)pdf 5.pdf · uploaded 13 Feb 2019Source
- 6 Building Plan Approval (IOD)pdf 6.pdf · uploaded 13 Feb 2019Source
- 7 Building Plan Approval (IOD)pdf 7.pdf · uploaded 13 Feb 2019Source
- 8 Building Plan Approval (IOD)pdf 8.pdf · uploaded 13 Feb 2019Source
- 9 Building Plan Approval (IOD)pdf 9.pdf · uploaded 13 Feb 2019Source
- 10 Building Plan Approval (IOD)pdf 10.pdf · uploaded 13 Feb 2019Source
- 11 Building Plan Approval (IOD)pdf 11.pdf · uploaded 13 Feb 2019Source
- 12 Building Plan Approval (IOD)pdf 12.pdf · uploaded 13 Feb 2019Source
- 13 Building Plan Approval (IOD)pdf 13.pdf · uploaded 13 Feb 2019Source
- 1 Declaration in FORM Bform b - shakti aura.pdf · uploaded 13 Feb 2019Source
- 1 Form 2ARERA-ARCHITECT CERTIFICATE-compressed.pdf · uploaded 12 Jun 2019Source
- 2 Commencement Certificates / NA Order for plotted development20220506050545.pdf · uploaded 19 May 2022Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects certificate form1.pdf · uploaded 19 May 2022Source
- 14 Copy of Layout Approval (in case of layout)HPSCANNER0726_compressed.pdf · uploaded 24 May 2022Source
- 15 Copy of Layout Approval (in case of layout)HPSCANNER0727_compressed.pdf · uploaded 24 May 2022Source
- 16 Copy of Layout Approval (in case of layout)HPSCANNER0728_compressed.pdf · uploaded 24 May 2022Source
- 17 Copy of Layout Approval (in case of layout)HPSCANNER0729_compressed.pdf · uploaded 24 May 2022Source
- 18 Copy of Layout Approval (in case of layout)HPSCANNER0730_compressed.pdf · uploaded 24 May 2022Source
- 19 Copy of Layout Approval (in case of layout)HPSCANNER0731_compressed.pdf · uploaded 24 May 2022Source
- 20 Copy of Layout Approval (in case of layout)HPSCANNER0732_compressed.pdf · uploaded 24 May 2022Source
- 21 Copy of Layout Approval (in case of layout)HPSCANNER0733_compressed.pdf · uploaded 24 May 2022Source
- 22 Copy of Layout Approval (in case of layout)HPSCANNER0734_compressed.pdf · uploaded 24 May 2022Source
- 23 Copy of Layout Approval (in case of layout)HPSCANNER0735_compressed.pdf · uploaded 24 May 2022Source
- 24 Copy of Layout Approval (in case of layout)HPSCANNER0736_compressed.pdf · uploaded 24 May 2022Source
- 25 Copy of Layout Approval (in case of layout)HPSCANNER0737_compressed.pdf · uploaded 24 May 2022Source
- 26 Copy of Layout Approval (in case of layout)HPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- 27 Copy of Layout Approval (in case of layout)HPSCANNER0739_compressed.pdf · uploaded 24 May 2022Source
- 14 Building Plan Approval (IOD)HPSCANNER0726_compressed.pdf · uploaded 24 May 2022Source
- 15 Building Plan Approval (IOD)HPSCANNER0727_compressed.pdf · uploaded 24 May 2022Source
- 16 Building Plan Approval (IOD)HPSCANNER0728_compressed.pdf · uploaded 24 May 2022Source
- 17 Building Plan Approval (IOD)HPSCANNER0729_compressed.pdf · uploaded 24 May 2022Source
- 18 Building Plan Approval (IOD)HPSCANNER0730_compressed.pdf · uploaded 24 May 2022Source
- 19 Building Plan Approval (IOD)HPSCANNER0731_compressed.pdf · uploaded 24 May 2022Source
- 20 Building Plan Approval (IOD)HPSCANNER0732_compressed.pdf · uploaded 24 May 2022Source
- 21 Building Plan Approval (IOD)HPSCANNER0733_compressed.pdf · uploaded 24 May 2022Source
- 22 Building Plan Approval (IOD)HPSCANNER0734_compressed.pdf · uploaded 24 May 2022Source
- 23 Building Plan Approval (IOD)HPSCANNER0735_compressed.pdf · uploaded 24 May 2022Source
- 24 Building Plan Approval (IOD)HPSCANNER0736_compressed.pdf · uploaded 24 May 2022Source
- 25 Building Plan Approval (IOD)HPSCANNER0737_compressed.pdf · uploaded 24 May 2022Source
- 26 Building Plan Approval (IOD)HPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- 27 Building Plan Approval (IOD)HPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- 28 Building Plan Approval (IOD)HPSCANNER0739_compressed.pdf · uploaded 24 May 2022Source
- 1 Declaration about Commencement Certificateformat d shakti aura.pdf · uploaded 11 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certificate Shakti Aura (1).pdf · uploaded 11 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form no 5 RERA 2019-20.pdf · uploaded 11 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form no 5 RERA 2020-21.pdf · uploaded 11 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form-5.pdf · uploaded 16 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5.pdf · uploaded 25 Apr 2024Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 2019.pdf · uploaded 23 May 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2019.pdf · uploaded 23 May 2025Source
- 20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2019.pdf · uploaded 23 May 2025Source
- 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 2019.pdf · uploaded 23 May 2025Source
- 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 2019.pdf · uploaded 23 May 2025Source
- 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2020.pdf · uploaded 23 May 2025Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2023.pdf · uploaded 23 May 2025Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 2023.pdf · uploaded 23 May 2025Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2023.pdf · uploaded 23 May 2025Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 2022.pdf · uploaded 23 May 2025Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 2022.pdf · uploaded 23 May 2025Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2022.pdf · uploaded 23 May 2025Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 2021.pdf · uploaded 23 May 2025Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 2021.pdf · uploaded 23 May 2025Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 2021.pdf · uploaded 23 May 2025Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 MAR 2021.pdf · uploaded 23 May 2025Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 2020.pdf · uploaded 23 May 2025Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 2020.pdf · uploaded 23 May 2025Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 2020.pdf · uploaded 23 May 2025Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 2022.pdf · uploaded 23 May 2025Source
- 10 Certificates of CA (Form 3)FORM 3 JUNE 2021.pdf · uploaded 23 May 2025Source
- 11 Certificates of CA (Form 3)FORM 3 SEPT 2021.pdf · uploaded 23 May 2025Source
- 12 Certificates of CA (Form 3)FORM 3 DEC 2021.pdf · uploaded 23 May 2025Source
- 13 Certificates of CA (Form 3)FORM 3 MAR 2022.pdf · uploaded 23 May 2025Source
- 14 Certificates of CA (Form 3)FORM 3 JUNE 2022.pdf · uploaded 23 May 2025Source
- 15 Certificates of CA (Form 3)FORM 3 SEPT 2022.pdf · uploaded 23 May 2025Source
- 16 Certificates of CA (Form 3)FORM 3 DEC 2022.pdf · uploaded 23 May 2025Source
- 17 Certificates of CA (Form 3)FORM 3 MAR 2023.pdf · uploaded 23 May 2025Source
- 18 Certificates of CA (Form 3)FORM 3 JUNE 2023.pdf · uploaded 23 May 2025Source
- 8 Certificates of CA (Form 3)FORM 3 DEC 2020.pdf · uploaded 23 May 2025Source
- 9 Certificates of CA (Form 3)FORM 3 MAR 2021.pdf · uploaded 23 May 2025Source
- 1 Certificates of CA (Form 3)FORM 3 MAR 2019.pdf · uploaded 23 May 2025Source
- 2 Certificates of CA (Form 3)FORM 3 JUNE 2019.pdf · uploaded 23 May 2025Source
- 3 Certificates of CA (Form 3)FORM 3 SEPT 2019.pdf · uploaded 23 May 2025Source
- 4 Certificates of CA (Form 3)FORM 3 DEC 2019.pdf · uploaded 23 May 2025Source
- 5 Certificates of CA (Form 3)FORM 3 MAR 2020.pdf · uploaded 23 May 2025Source
- 6 Certificates of CA (Form 3)FORM 3 JUNE 2020.pdf · uploaded 23 May 2025Source
- 7 Certificates of CA (Form 3)FORM 3 SEPT 2020.pdf · uploaded 23 May 2025Source
- 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 2023.pdf · uploaded 23 May 2025Source
- 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 MAR 2023.pdf · uploaded 23 May 2025Source
- 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 2022.pdf · uploaded 23 May 2025Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 SEPT 2022.pdf · uploaded 23 May 2025Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 2022.pdf · uploaded 23 May 2025Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 MAR 2022.pdf · uploaded 23 May 2025Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 2021.pdf · uploaded 23 May 2025Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 SEPT 2021.pdf · uploaded 23 May 2025Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 MAR 2021.pdf · uploaded 23 May 2025Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 2021.pdf · uploaded 23 May 2025Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 2020.pdf · uploaded 23 May 2025Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 SEPT 2020.pdf · uploaded 23 May 2025Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 2020.pdf · uploaded 23 May 2025Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 MAR 2020.pdf · uploaded 23 May 2025Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 2019.pdf · uploaded 23 May 2025Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 SEPT 2019.pdf · uploaded 23 May 2025Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 2019.pdf · uploaded 23 May 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 1 MAR 2020.pdf · uploaded 23 May 2025Source
- 1 Form 2AFORM 2A MAR'19.pdf · uploaded 23 May 2025Source
- 2 Form 2AFORM 2A MAR'20.pdf · uploaded 23 May 2025Source
- 3 Form 2AFORM 2A MAR'21.pdf · uploaded 23 May 2025Source
- 4 Form 2AFORM 2A MAR'22.pdf · uploaded 23 May 2025Source
- 5 Form 2AFORM 2A MAR'23.pdf · uploaded 23 May 2025Source
- 1 Disclosure of sold/ booked inventorySold and Unsold Inventory 30th JUn 2023.pdf · uploaded 23 May 2025Source
- Form 11 FORM 1 MAR 2019.pdf · uploaded 1 Jul 2025Source
- Form 12 FORM 1 JUNE 2019.pdf · uploaded 1 Jul 2025Source
- Form 12 FORM 1 SEPT 2019.pdf · uploaded 1 Jul 2025Source
- Form 13 FORM 1 DEC 2019.pdf · uploaded 1 Jul 2025Source
- Form 14 FORM 1 MAR 2020.pdf · uploaded 1 Jul 2025Source
- Form 15 FORM 1 JUNE 2020.pdf · uploaded 1 Jul 2025Source
- Form 16 FORM 1 SEPT 2020.pdf · uploaded 1 Jul 2025Source
- Form 17 FORM 1 DEC 2020.pdf · uploaded 1 Jul 2025Source
- Form 18 FORM 1 MAR 2021.pdf · uploaded 1 Jul 2025Source
- Form 19 FORM 1 JUNE 2021.pdf · uploaded 1 Jul 2025Source
- Form 110 FORM 1 SEPT 2021.pdf · uploaded 1 Jul 2025Source
- Form 111 FORM 1 DEC 2021.pdf · uploaded 1 Jul 2025Source
- Form 111 FORM 1 MAR 2022.pdf · uploaded 1 Jul 2025Source
- Form 112 FORM 1 JUNE 2022.pdf · uploaded 1 Jul 2025Source
- Form 112 FORM 1 SEPT 2022.pdf · uploaded 1 Jul 2025Source
- Form 114 FORM 1 DEC 2022.pdf · uploaded 1 Jul 2025Source
- Form 115 FORM 1 MAR 2023.pdf · uploaded 1 Jul 2025Source
- Form 116 FORM 1 JUNE 2023.pdf · uploaded 1 Jul 2025Source
- Form 21 FORM 2 MAR 2019.pdf · uploaded 1 Jul 2025Source
- Form 22 FORM 2 JUNE 2019.pdf · uploaded 1 Jul 2025Source
- Form 22 FORM 2 SEPT 2019.pdf · uploaded 1 Jul 2025Source
- Form 23 FORM 2 DEC 2019.pdf · uploaded 1 Jul 2025Source
- Form 24 FORM 2 MAR 2020.pdf · uploaded 1 Jul 2025Source
- Form 25 FORM 2 JUNE 2020.pdf · uploaded 1 Jul 2025Source
- Form 26 FORM 2 SEPT 2020.pdf · uploaded 1 Jul 2025Source
- Form 27 FORM 2 DEC 2020.pdf · uploaded 1 Jul 2025Source
- Form 28 FORM 2 MAR 2021.pdf · uploaded 1 Jul 2025Source
- Form 29 FORM 2 JUNE 2021.pdf · uploaded 1 Jul 2025Source
- Form 210 FORM 2 SEPT 2021.pdf · uploaded 1 Jul 2025Source
- Form 211 FORM 2 DEC 2021.pdf · uploaded 1 Jul 2025Source
- Form 212 FORM 2 MAR 2022.pdf · uploaded 1 Jul 2025Source
- Form 213 FORM 2 JUNE 2022.pdf · uploaded 1 Jul 2025Source
- Form 214 FORM 2 SEPT 2022.pdf · uploaded 1 Jul 2025Source
- Form 215 FORM 2 DEC 2022.pdf · uploaded 1 Jul 2025Source
- Form 216 FORM 2 MAR 2023.pdf · uploaded 1 Jul 2025Source
- Form 217 FORM 2 JUNE 2023.pdf · uploaded 1 Jul 2025Source
- Form 31 FORM 3 MAR 2019.pdf · uploaded 1 Jul 2025Source
- Form 32 FORM 3 JUNE 2019.pdf · uploaded 1 Jul 2025Source
- Form 33 FORM 3 SEPT 2019.pdf · uploaded 1 Jul 2025Source
- Form 34 FORM 3 DEC 2019.pdf · uploaded 1 Jul 2025Source
- Form 35 FORM 3 MAR 2020.pdf · uploaded 1 Jul 2025Source
- Form 36 FORM 3 JUNE 2020.pdf · uploaded 1 Jul 2025Source
- Form 37 FORM 3 SEPT 2020.pdf · uploaded 1 Jul 2025Source
- Form 38 FORM 3 DEC 2020.pdf · uploaded 1 Jul 2025Source
- Form 39 FORM 3 MAR 2021.pdf · uploaded 1 Jul 2025Source
- Form 310 FORM 3 JUNE 2021.pdf · uploaded 1 Jul 2025Source
- Form 311 FORM 3 SEPT 2021.pdf · uploaded 1 Jul 2025Source
- Form 312 FORM 3 DEC 2021.pdf · uploaded 1 Jul 2025Source
- Form 313 FORM 3 MAR 2022.pdf · uploaded 1 Jul 2025Source
- Form 314 FORM 3 JUNE 2022.pdf · uploaded 1 Jul 2025Source
- Form 315 FORM 3 SEPT 2022.pdf · uploaded 1 Jul 2025Source
- Form 316 FORM 3 DEC 2022.pdf · uploaded 1 Jul 2025Source
- Form 317 FORM 3 MAR 2023.pdf · uploaded 1 Jul 2025Source
- Form 318 FORM 3 JUNE 2023.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory1 Disclosure of Sold_ Booked Inventory 31-March 2019.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory2 Disclosure of Sold_ Booked Inventory 30-June 2019.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of Sold_ Booked Inventory 30-Sep 2019.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory4 Disclosure of Sold_ Booked Inventory 31-Dec 2019.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory5 Disclosure of Sold_ Booked Inventory 31-March 2020.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory6 Disclosure of Sold_ Booked Inventory 30-June 2020.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory7 Disclosure of Sold_ Booked Inventory 30-Sep 2020.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory8 Disclosure of Sold_ Booked Inventory 31-Dec 2020.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory9 Disclosure of Sold_ Booked Inventory 31-March 2021.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory10 Disclosure of Sold_ Booked Inventory 30-June 2021.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory11 Disclosure of Sold_ Booked Inventory 30-Sep 2021.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory12 Disclosure of Sold_ Booked Inventory 31-Dec 2021.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory13 Disclosure of Sold_ Booked Inventory 31-March 2022.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory14 Disclosure of Sold_ Booked Inventory 30-June 2022.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory15 Disclosure of Sold_ Booked Inventory 30-Sep 2022.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory16 Disclosure of Sold_ Booked Inventory 31-Dec 2022.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory17 Disclosure of Sold_ Booked Inventory 31-March 2023.pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventory18 Disclosure of Sold_ Booked Inventory 30-June 2023.pdf · uploaded 1 Jul 2025Source
- Form 5 (FY 2021-2022)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 6 Mar 2026Source
- Form 2A (FY 2018-2019)Shakti Developer (Aura)- Form-2A 2019_11zon.pdf · uploaded 2 Apr 2026Source
- Form 2A (FY 2019-2020)Shakti Developer (Aura)- Form-2A 2019-20_11zon.pdf · uploaded 2 Apr 2026Source
- Form 2A (FY 2020-2021)Shakti Developer (Aura)- Form-2A 2020-21_11zon.pdf · uploaded 2 Apr 2026Source
- Form 2A (FY 2021-2022)Shakti Developer (Aura)- Form-2A 2021-22_11zon.pdf · uploaded 2 Apr 2026Source
- Form 2A (FY 2022-2023)Shakti Developer (Aura)- Form-2A 2022-23_11zon (1).pdf · uploaded 2 Apr 2026Source
- Form 5 (FY 2018-2019)Shakti Aura Form-5 (20-02-2019-31-03-2019)Signed_11zon.pdf · uploaded 2 Apr 2026Source
- Form 5 (FY 2019-2020)Shakti Aura Form 5 (2019-20)Signed_11zon.pdf · uploaded 2 Apr 2026Source
- Form 5 (FY 2020-2021)Shakti Aura Form5 March 21 Final signed_11zon.pdf · uploaded 14 Apr 2026Source
- Form 5 (FY 2022-2023)1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf · uploaded 14 Apr 2026Source
- Form 2A (FY 2023-2024)Shakti Developer Aura Form 2A 2023 24 .pdf · uploaded 9 Jun 2026Source
- Form 5 (FY 2023-2024)Shakti Aura Form 5 FY 2023 24.pdf · uploaded 9 Jun 2026Source
Technical
- Documentpdf 1.pdf · uploaded 13 Feb 2019Source
- Documentpdf 2.pdf · uploaded 13 Feb 2019Source
- Documentpdf 3.pdf · uploaded 13 Feb 2019Source
- Documentpdf 4.pdf · uploaded 13 Feb 2019Source
- Documentpdf 5.pdf · uploaded 13 Feb 2019Source
- Documentpdf 6.pdf · uploaded 13 Feb 2019Source
- Documentpdf 7.pdf · uploaded 13 Feb 2019Source
- Documentpdf 8.pdf · uploaded 13 Feb 2019Source
- Documentpdf 9.pdf · uploaded 13 Feb 2019Source
- Documentpdf 9.pdf · uploaded 13 Feb 2019Source
- Documentpdf 11.pdf · uploaded 13 Feb 2019Source
- Documentpdf 12.pdf · uploaded 13 Feb 2019Source
- Documentpdf 13.pdf · uploaded 13 Feb 2019Source
- Documentpdf 1.pdf · uploaded 13 Feb 2019Source
- Documentpdf 2.pdf · uploaded 13 Feb 2019Source
- Documentpdf 3.pdf · uploaded 13 Feb 2019Source
- Documentpdf 4.pdf · uploaded 13 Feb 2019Source
- Documentpdf 5.pdf · uploaded 13 Feb 2019Source
- Documentpdf 6.pdf · uploaded 13 Feb 2019Source
- Documentpdf 7.pdf · uploaded 13 Feb 2019Source
- Documentpdf 8.pdf · uploaded 13 Feb 2019Source
- Documentpdf 9.pdf · uploaded 13 Feb 2019Source
- Documentpdf 10.pdf · uploaded 13 Feb 2019Source
- Documentpdf 11.pdf · uploaded 13 Feb 2019Source
- Documentpdf 12.pdf · uploaded 13 Feb 2019Source
- Documentpdf 13.pdf · uploaded 13 Feb 2019Source
- DocumentHPSCANNER0726_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0727_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0728_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0729_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0730_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0731_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0732_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0733_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0734_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0735_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0736_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0737_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0739_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0726_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0727_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0728_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0729_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0730_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0731_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0732_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0733_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0734_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0735_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0736_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0737_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0738_compressed.pdf · uploaded 24 May 2022Source
- DocumentHPSCANNER0739_compressed.pdf · uploaded 24 May 2022Source
Technical (Architect)
- DocumentArchitects certificate form1.pdf · uploaded 19 May 2022Source
- DocumentFORM 1 MAR 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 JUNE 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 JUNE 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 SEPT 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 DEC 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 JUNE 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 SEPT 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 DEC 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 JUNE 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 SEPT 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 DEC 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2023.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 JUNE 2023.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2023.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 SEPT 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 DEC 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 1 MAR 2019.pdf · uploaded 23 May 2025Source
Technical (Engineer)
- Documentform 2 Engineer Certificate final.pdf · uploaded 11 Jan 2019Source
- DocumentFORM 1 MAR 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 JUNE 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 SEPT 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 DEC 2019.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 MAR 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 JUNE 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 SEPT 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 DEC 2020.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 MAR 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 JUNE 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 SEPT 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 DEC 2021.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 MAR 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 JUNE 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 SEPT 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 DEC 2022.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 MAR 2023.pdf · uploaded 23 May 2025Source
- DocumentFORM 2 JUNE 2023.pdf · uploaded 23 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 12
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop127 units in all
- Address
- Plot No 12, Ghansoli Station Road, GhansoliPIN 400701
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Land area for this project
- 2,400 sq m (25,833 sq ft)
- Permissible built-up area
- 3,599 sq m (38,739 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 305 sq m (3,283 sq ft)
- Designated bank account
- 154
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 12
Boundaries
- North
- Plot No 10
- South
- Plot No 13 And Plot No 14
- East
- Railway Boundry
- West
- 30m Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking127 units
52 of 127 units booked (41%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.59 sq m · 372 sq ft | 30 | 18 |
| 1BHK | 34.77 sq m · 374 sq ft | 46 | 8 |
| 2BHK | 49.74 sq m · 535 sq ft | 4 | 2 |
| 2BHK | 49.75 sq m · 536 sq ft | 29 | 22 |
| Office space | 37.35 sq m · 402 sq ft | 1 | 0 |
| Office space | 37.36 sq m · 402 sq ft | 7 | 0 |
| Office space | 42.18 sq m · 454 sq ft | 1 | 0 |
| Shop | 36.66 sq m · 395 sq ft | 1 | 0 |
| Shop | 37.67 sq m · 405 sq ft | 7 | 2 |
| Shop | 42.53 sq m · 458 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Soyuz Talib Architects | — |
| Chartered accountant | Satish Kavitake | — |
| Chartered accountant | Shalu Anand | — |
| Engineer | Piyush Chopda | — |
| Engineer | Raajesh Ladhad | — |
| Engineer | Structural Concept Designs Private Limited | — |