RERA projects in Gauripada
4 projects under 4 MahaRERA registrations, registered 2023–2026. 75% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
4Completion still due0 past their completion date
4 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Gauripada
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Dwarka DivineG D Home Creators | PR1330002602019 | 23 Sep 2026 | 31 Mar 2028 | 31 Mar 2028 | Not yet due | 0 |
| Junomoneta - Lovis Lake ViewPalika Infratech LLP | P51700080416 | 2 Jun 2025 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Siyara HeightsShakti Realty | P51700077145 | 23 Jul 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Sai Dwarka ResidencyHari Om Construction | P51700053053 | 12 Oct 2023 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
Other localities in Kalyan
Most active promoters
By projects registered here, as named on MahaRERA.
- G D Home Creators1 project
- Hari Om Construction1 project
- Palika Infratech LLP1 project
- Shakti Realty1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology