RERA projects in Gauripada

4 projects under 4 MahaRERA registrations, registered 2023–2026. 75% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
4Completion still due0 past their completion date
4 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20231
20241
20251
20261

Projects in Gauripada

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dwarka DivineG D Home CreatorsPR133000260201923 Sep 202631 Mar 202831 Mar 2028Not yet due0
Junomoneta - Lovis Lake ViewPalika Infratech LLPP517000804162 Jun 202531 Dec 203130 Apr 2032Extended 4 mo0
Siyara HeightsShakti RealtyP5170007714523 Jul 202431 Mar 202931 Jul 2029Extended 4 mo0
Sai Dwarka ResidencyHari Om ConstructionP5170005305312 Oct 202330 Jun 202830 Oct 2028Extended 4 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. G D Home Creators1 project
  2. Hari Om Construction1 project
  3. Palika Infratech LLP1 project
  4. Shakti Realty1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology