Others · 13 buildings · 537 unitsRERA P51700008949

Pushpanjali Residency Phase III

Deedo IDDP-THN-23BQ

Completion was pushed back 3 years to Dec 2025, and that date has passed too; 1 listing or order with MahaRERA on record; 99% of its units are booked.

Owale, Thane 400615 · by Shriraam Pioneer Developers Private Limited

Delivery3 yrs 11 mo latePromised Dec 2022 · revised Dec 2025 · that date has passed tooRegulatory1 listing or orderLatest: Regulatory order, 2024Sales99% booked529 of 537 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 years to Dec 2025, and that date has passed too

  • This projectRegistered 19 Aug 2017, completion promised 30 Dec 2022, revised to 31 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

13 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory record1

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order21 Jun 2024Matched by RERA number

    Regulatory order: PROJECT NAME:PUSHPANJALI RESIDENCY PHASE III (Regulatory Case No. 233 OF 2024) dated 21 June 2024.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700008949
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000894919 Aug 201730 Dec 202231 Dec 2025Shriraam Pioneer Developers Private LimitedProject page
Documents245

95 documents held by Deedo, 150 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other (93)

Show all 245 documentsShow fewer documents

Other (93)

Finance

  • PAN CardPan.pdf · uploaded 31 Jul 2017Source
  • PAN CardPancardSPDPL.pdf · uploaded 13 Mar 2024Source

Legal

  • Declaration Form BScan - from B (2).pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTitle_1.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTitle_2.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTitle_3.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTitle_4.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTitle_5.pdf · uploaded 31 Jul 2017Source
  • OtherCC to upload.pdf · uploaded 16 Oct 2017Source
  • Legal Title report1.pdf · uploaded 16 Oct 2017Source
  • Legal Title report2.pdf · uploaded 16 Oct 2017Source
  • Legal Title report3.pdf · uploaded 16 Oct 2017Source
  • Legal Title report4.pdf · uploaded 16 Oct 2017Source
  • Legal Title report5.pdf · uploaded 16 Oct 2017Source
  • Legal Title report6.pdf · uploaded 16 Oct 2017Source
  • Legal Title report7.pdf · uploaded 16 Oct 2017Source
  • Legal Title report8.pdf · uploaded 16 Oct 2017Source
  • Legal Title report1 to 6.pdf · uploaded 8 Nov 2017Source
  • Legal Title report7 to 12.pdf · uploaded 8 Nov 2017Source
  • Legal Title report13 to 18.pdf · uploaded 8 Nov 2017Source
  • Legal Title report19 to 24.pdf · uploaded 8 Nov 2017Source
  • Legal Title report25 to 30.pdf · uploaded 8 Nov 2017Source
  • Legal Title report31 to 36.pdf · uploaded 8 Nov 2017Source
  • Legal Title report37 to 42.pdf · uploaded 8 Nov 2017Source
  • Legal Title report43 to 44.pdf · uploaded 8 Nov 2017Source
  • Legal Title reportTitle Certificate_NEW_07_04_2021_new.pdf · uploaded 30 Mar 2022Source
  • Declaration Form BFORM_B.pdf · uploaded 1 Apr 2024Source
  • Declaration Form BForm B.pdf · uploaded 28 Mar 2025Source

Migrated

  • 1 PAN CardPan.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of the legal title reportTitle_1.pdf · uploaded 31 Jul 2017Source
  • 2 Copy of the legal title reportTitle_2.pdf · uploaded 31 Jul 2017Source
  • 3 Copy of the legal title reportTitle_3.pdf · uploaded 31 Jul 2017Source
  • 4 Copy of the legal title reportTitle_4.pdf · uploaded 31 Jul 2017Source
  • 5 Copy of the legal title reportTitle_5.pdf · uploaded 31 Jul 2017Source
  • 1 Details of encumbrancesScan_no___encumbran_Certificate (1).pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)New Doc 2017-07-31 (1) (1).pdf · uploaded 31 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentIOD_2.pdf · uploaded 31 Jul 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentIOD.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BScan - from B (2).pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architec Certificates_1.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architec Certificates_2.pdf · uploaded 31 Jul 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architec Certificates_3.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng 1.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng 2.pdf · uploaded 31 Jul 2017Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng 3.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Certificates_1-.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of CA (Form 3)CA Certificates_2-.pdf · uploaded 31 Jul 2017Source
  • 3 Certificates of CA (Form 3)CA Certificates_3-.pdf · uploaded 31 Jul 2017Source
  • 4 Certificates of CA (Form 3)CA Certificates_4-.pdf · uploaded 31 Jul 2017Source
  • 5 Certificates of CA (Form 3)CA Certificates_5-.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterAllotment letter Pushpanjali.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterRERA Pushpanjali final.pdf · uploaded 31 Jul 2017Source
  • 6 Copy of the legal title report1.pdf · uploaded 16 Oct 2017Source
  • 7 Copy of the legal title report2.pdf · uploaded 16 Oct 2017Source
  • 8 Copy of the legal title report3.pdf · uploaded 16 Oct 2017Source
  • 9 Copy of the legal title report4.pdf · uploaded 16 Oct 2017Source
  • 10 Copy of the legal title report5.pdf · uploaded 16 Oct 2017Source
  • 11 Copy of the legal title report6.pdf · uploaded 16 Oct 2017Source
  • 12 Copy of the legal title report7.pdf · uploaded 16 Oct 2017Source
  • 13 Copy of the legal title report8.pdf · uploaded 16 Oct 2017Source
  • 2 Details of encumbrancesencumbrance.pdf · uploaded 16 Oct 2017Source
  • 3 Details of encumbrancesencumbrance.pdf · uploaded 16 Oct 2017Source
  • 3 Proforma of Allotment letterRERA agreeement final draft.pdf · uploaded 16 Oct 2017Source
  • 1 OtherCC to upload.pdf · uploaded 16 Oct 2017Source
  • 14 Copy of the legal title report1 to 6.pdf · uploaded 8 Nov 2017Source
  • 15 Copy of the legal title report7 to 12.pdf · uploaded 8 Nov 2017Source
  • 16 Copy of the legal title report13 to 18.pdf · uploaded 8 Nov 2017Source
  • 17 Copy of the legal title report19 to 24.pdf · uploaded 8 Nov 2017Source
  • 18 Copy of the legal title report25 to 30.pdf · uploaded 8 Nov 2017Source
  • 19 Copy of the legal title report31 to 36.pdf · uploaded 8 Nov 2017Source
  • 20 Copy of the legal title report37 to 42.pdf · uploaded 8 Nov 2017Source
  • 21 Copy of the legal title report43 to 44.pdf · uploaded 8 Nov 2017Source
  • 1 Certificates of CA (Form 5)FORM5_Certificate_CA.pdf · uploaded 30 Jul 2019Source
  • 22 Copy of the legal title reportTitle Certificate_NEW_07_04_2021_new.pdf · uploaded 30 Mar 2022Source
  • 2 Copy of Layout Approval (in case of layout)Lay_Out_Plan_2021_NEW.pdf · uploaded 30 Mar 2022Source
  • 2 Building Plan Approval (IOD)Commencement Certificate_2021_NEW.pdf · uploaded 30 Mar 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_2021_NEW.pdf · uploaded 30 Mar 2022Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineering Certificate_FORM_2_S1___S2.pdf · uploaded 30 Mar 2022Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineering Certificate_FORM_2_S3___S4.pdf · uploaded 30 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5_CA Certificate_compressed.pdf · uploaded 25 May 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A_FY_2019_2020 (1).pdf · uploaded 28 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A_FY_2020_2021.pdf · uploaded 28 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A_FY_2020_2021.pdf · uploaded 28 Nov 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A_FY_2021_2022.pdf · uploaded 28 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5_FY_2018_2019.pdf · uploaded 28 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5_FY_2019_2020.pdf · uploaded 28 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5_FY_2021_2022.pdf · uploaded 28 Nov 2022Source
  • 1 Declaration about Commencement CertificateDeclaration_for_Extension_Compressed.pdf · uploaded 7 Jan 2023Source
  • 1 Disclosure of sold/ booked inventorySold_Inventory__compressed1_11zon.pdf · uploaded 7 Jan 2023Source
  • 2 Disclosure of sold/ booked inventoryUnsold_Inventory__Compressed.pdf · uploaded 7 Jan 2023Source
  • 4 Details of encumbrancesEncumbrance_Certificate_RD_.pdf · uploaded 27 Jun 2023Source
  • 3 Copy of Layout Approval (in case of layout)1_Layout Plan.pdf · uploaded 13 Jul 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificate dated_4_7_2023_1.pdf · uploaded 13 Jul 2023Source
  • 5 a Details of encumbrances concerned to Finance4 Details of encumbrances_S1S2S3S4.pdf · uploaded 27 Oct 2023Source
  • 1 b Details of encumbrances concerned to Legal4 Details of encumbrances_S1S2S3S4.pdf · uploaded 27 Oct 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM1.pdf · uploaded 5 Feb 2024Source
  • 2 PAN CardPancardSPDPL.pdf · uploaded 13 Mar 2024Source
  • 2 Declaration in FORM BFORM_B.pdf · uploaded 1 Apr 2024Source
  • 6 Certificates of CA (Form 3)FORM_3_compressed.pdf · uploaded 1 Apr 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM_2_311223.pdf · uploaded 9 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Self_Declaration_for_FORM_2A.pdf · uploaded 9 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Self_Declaration_for_FORM_2A.pdf · uploaded 9 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM_5_20222_2023_2.pdf · uploaded 9 May 2024Source
  • 6 a Details of encumbrances concerned to FinanceAnnexure_F-Non-Encumbrance_Concerned_to_Finance.pdf · uploaded 15 May 2024Source
  • 2 b Details of encumbrances concerned to LegalAnnexure_F-Non-Encumbrance_Concerned_to_Finance.pdf · uploaded 15 May 2024Source
  • 1 CERSAI detailsAnnexure_D-Asset_Based_Declaration_.pdf · uploaded 15 May 2024Source
  • 2 CERSAI detailsAnnexure_E-_Debtor_Based_Declaration.pdf · uploaded 15 May 2024Source
  • 3 Disclosure of sold/ booked inventoryAnnexure_B-Disclosure_of_Sold_or_Unsold_Inventory_compressed.pdf · uploaded 15 May 2024Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 2 Aug 2024Source
  • 2 Certificates of CA (Form 3)Form 3_As on 30924.pdf · uploaded 30 Oct 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM1.pdf · uploaded 13 Nov 2024Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM1.pdf · uploaded 13 Nov 2024Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM1.pdf · uploaded 13 Nov 2024Source
  • 3 Certificates of CA (Form 3)Form 3_As on 30924_Edited as per query.pdf · uploaded 13 Nov 2024Source
  • 4 Certificates of CA (Form 3)Form 3_As on 30924_Edited as per query.pdf · uploaded 13 Nov 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 13 Nov 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 13 Nov 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 13 Nov 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 13 Nov 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 13 Nov 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM1.pdf · uploaded 31 Jan 2025Source
  • 1 Certificates of CA (Form 3)Form3.pdf · uploaded 31 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 31 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5.pdf · uploaded 31 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5.pdf · uploaded 31 Jan 2025Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 28 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 28 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 28 Mar 2025Source
  • 1 Other – TechnicalCPM RAM.pdf · uploaded 30 Mar 2025Source
  • 1 Other – TechnicalPart OC_11zon.pdf · uploaded 25 Apr 2025Source

Technical

  • DocumentLayout Plan.pdf · uploaded 31 Jul 2017Source
  • DocumentNew Doc 2017-07-31 (1) (1).pdf · uploaded 31 Jul 2017Source
  • DocumentLay_Out_Plan_2021_NEW.pdf · uploaded 30 Mar 2022Source
  • DocumentCommencement Certificate_2021_NEW.pdf · uploaded 30 Mar 2022Source
  • Document1_Layout Plan.pdf · uploaded 13 Jul 2023Source
  • Other – TechnicalCPM RAM.pdf · uploaded 30 Mar 2025Source
  • Other – TechnicalPart OC_11zon.pdf · uploaded 25 Apr 2025Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 18 Sep 2024Source
  • DocumentFORM1.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM1.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM1.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM1.pdf · uploaded 31 Jan 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 18 Sep 2024Source
  • DocumentFORM2.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM2.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM2.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM2.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM2.pdf · uploaded 13 Nov 2024Source
  • DocumentFORM2.pdf · uploaded 31 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 101/3, 58/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
B1, B2, B3, B4, B5, B6, B7, B8, B9, 1 BHK TYPE 1, 1 BHK TYPE 2, 2 BHK TYPE 1, 2 BHK TYPE 2, 2 BHK TYPE 3, 1 BHK TYPE 3, 1 BHK TYPE 4, 1 BHK TYPE 5, —537 units in all
Address
99/2, 99/4B, 101/3, 97/1, 58/1, 98/1A, 98/1B, 99/6 59/1A 99/4A, 59/2, 97/3/3, 99/3, 58/5A, Ghodbunder Road, OwalePIN 400615
Village
Thane (M Corp.), Thane taluka
Land area for this project
27,738 sq m (2,98,574 sq ft)
Permissible built-up area
32,130 sq m (3,45,846 sq ft)
Sanctioned built-up area
26,936 sq m (2,89,940 sq ft)
Recreational open space
7,121 sq m (76,654 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

101/358/158/5A59/297/197/3/398/1A98/1B99/299/399/4B99/6 59/1A 99/4A

Land as published on MahaRERA's project page

99/2, 99/4B, 101/3, 97/1, 58/1, 98/1A, 98/1B, 99/6 59/1A 99/4A, 59/2, 97/3/3, 99/3, 58/5A

Boundaries

North
Plot With Survey No 64-1 And 61-1-A
South
Plot With Survey No 67-3-1 And 67-3-2
East
Plot With Survey No 63-1 67-2 68-1 68-2-1
West
Plot With Survey No 66-2 131-2 And 30 Mt Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking537 units

529 of 537 units booked (99%), as the promoter reported to MahaRERA

B1 · 1 unitB2 · 1 unitB3 · 1 unitB4 · 1 unitB5 · 1 unitB6 · 1 unitB7 · 1 unitB8 · 1 unitB9 · 1 unit1 BHK TYPE 1 · 169 units1 BHK TYPE 2 · 50 units2 BHK TYPE 1 · 66 units2 BHK TYPE 2 · 69 units2 BHK TYPE 3 · 79 units1 BHK TYPE 3 · 44 units1 BHK TYPE 4 · 23 units1 BHK TYPE 5 · 28 units— · 0 units
BuildingTypeCarpet areaUnitsBooked
Bungalow 41B183.73 sq m · 901 sq ft11
Bungalow 42B2102.16 sq m · 1,100 sq ft11
Bungalow 43B3102.15 sq m · 1,100 sq ft11
Bungalow 44B485.13 sq m · 916 sq ft11
Bungalow 45B5116.65 sq m · 1,256 sq ft11
Bungalow 46B6209.25 sq m · 2,252 sq ft11
Bungalow 47B7209.25 sq m · 2,252 sq ft11
Bungalow 48B8209.25 sq m · 2,252 sq ft11
Show all 73 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Bungalow 49B9209.25 sq m · 2,252 sq ft11
S11 BHK TYPE 136.7 sq m · 395 sq ft3029
S11 BHK TYPE 235.58 sq m · 383 sq ft88
S12 BHK TYPE 145.43 sq m · 489 sq ft3030
S12 BHK TYPE 259.27 sq m · 638 sq ft3030
S12 BHK TYPE 349.52 sq m · 533 sq ft3030
S21 BHK TYPE 137.72 sq m · 406 sq ft2828
S21 BHK TYPE 237.81 sq m · 407 sq ft2323
S21 BHK TYPE 339.02 sq m · 420 sq ft2525
S21 BHK TYPE 434.56 sq m · 372 sq ft2322
S21 BHK TYPE 536.05 sq m · 388 sq ft2826
S31 BHK TYPE 137.53 sq m · 404 sq ft5151
S31 BHK TYPE 236.79 sq m · 396 sq ft1010
S31 BHK TYPE 338.46 sq m · 414 sq ft1010
S32 BHK TYPE 148.77 sq m · 525 sq ft1716
S32 BHK TYPE 250.54 sq m · 544 sq ft1919
S32 BHK TYPE 356.48 sq m · 608 sq ft2424
S41 BHK TYPE 137.53 sq m · 404 sq ft6059
S41 BHK TYPE 236.79 sq m · 396 sq ft98
S41 BHK TYPE 338.46 sq m · 414 sq ft99
S42 BHK TYPE 148.77 sq m · 525 sq ft1919
S42 BHK TYPE 250.54 sq m · 544 sq ft2020
S42 BHK TYPE 356.48 sq m · 608 sq ft2524
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00
———00

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.