Shriraam Pioneer Developers Private Limited
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+36 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pushpanjali Residency Phase IIIP51700008949 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Dec 2022 | 31 Dec 2025 | +36 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 36 months, for Pushpanjali Residency Phase III (P51700008949).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:PUSHPANJALI RESIDENCY PHASE III (Regulatory Case No. 233 OF 2024) dated 21 June 2024. · Pushpanjali Residency Phase III · P51700008949 · 21 Jun 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology