RERA projects in Ambivali Tarf Chon
9 projects under 10 MahaRERA registrations, registered 2017–2025. 50% have a completion date extended beyond the one promised.
Locality
9RERA projects
10Registrationssome projects hold several
3Completion still due7 past their completion date
18 monthsMedian extension beyond promised date50% of registrations extended
5Regulatory caseson 3 projects
11Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 1 |
| 2019 | 2 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Ambivali Tarf Chon
9 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Garden Estate Phase -IIShree Balaji Developers | P51700052971 | 6 Oct 2023 | 31 Mar 2025 | 30 Sep 2025 | Extended 6 mo | 0 |
| Shree PlazaVishal Laxman Patil | P51700026644 | 21 Oct 2020 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| Sai IconSai Shraddha Developers | P51700020449, PR1331012500948 | 11 Apr 2019 | 28 Jun 2030 | 28 Jun 2030 | Not yet due | 0 |
| Sai FloraSai Raj Developers | P51700020382 | 9 Apr 2019 | 30 Dec 2023 | 28 Jun 2028 | Extended 54 mo | 0 |
| Mayur HeightsReal Value Builders And Developers | P51700015724 | 19 Mar 2018 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| PineshireAanya Residences | P51700014064 | 7 Nov 2017 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 2 |
| WoodshireShree Ji Enterprises | P51700012252 | 1 Sep 2017 | 31 Dec 2019 | 31 Dec 2025 | Extended 72 mo | 5 |
| Falco PearlshireAanya Residences | P51700011065 | 31 Aug 2017 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 2 |
| Vishnu PlazaVishnu Developers | P51700005866 | 14 Aug 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
Other localities in Kalyan
Most active promoters
By projects registered here, as named on MahaRERA.
- Aanya Residences2 projects
- Real Value Builders And Developers1 project
- Sai Raj Developers1 project
- Sai Shraddha Developers1 project
- Shree Balaji Developers1 project
- Shree Ji Enterprises1 project
- Vishal Laxman Patil1 project
- Vishnu Developers1 project
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology