RERA projects in Pali

6 projects under 7 MahaRERA registrations, registered 2017–2025. 29% have a completion date extended beyond the one promised.

Locality
6RERA projects
7Registrationssome projects hold several
5Completion still due2 past their completion date
21 monthsMedian extension beyond promised date29% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20190
20201
20210
20220
20230
20242
20252

Projects in Pali

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Lakshmi HeightsM/S. Mahalaxmi SheltersPM13310125010251 Oct 202515 Dec 2028—Not yet due0
Dipti Business CenterDipti Builders Universal Pvt LtdP5170008092520 Aug 202531 Dec 2029—Not yet due0
Precious EmpireRkr RealityP51700056016, P517000778496 May 202415 Mar 2027—Not yet due0
Shree PrastM/S Shree PrastP5170002639017 Sep 202028 Feb 202228 Feb 2023Extended 12 mo0
Jp GalaxyJp Corp LLPP5170001387130 Oct 201731 Dec 2026—Not yet due0
shree siddhivinayak residencySunil Bhagchand TalrejaP517000134677 Oct 201731 May 201830 Nov 2020Extended 30 mo0

Other localities in Ambarnath

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Dipti Builders Universal Pvt Ltd1 project
  2. Jp Corp LLP1 project
  3. M/S. Mahalaxmi Shelters1 project
  4. M/S Shree Prast1 project
  5. Rkr Reality1 project
  6. Sunil Bhagchand Talreja1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology