10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations8some projects hold several
Completion still due62 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

8 MahaRERA registrations in Muthaval

6 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Muthaval

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Haware Palms KalyanHaware Properties LLPDue Apr 2029, extended 4 mo——
Haware Paramount KalyanHaware Properties LLPDue Apr 2029, extended 4 mo——
Haware ParadiseSuresh Kashinath Haware4 yrs 8 mo late—71%
Haware PinnacleSuresh Kashinath HawareCompleted—84%
Muthaval market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Haware Properties Llp2 projects
  2. Suresh Kashinath Haware2 projects

Muthaval, in questions

How many projects in Muthaval run late?

10 in 10 MahaRERA registrations (8 of 8): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Muthaval by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology