Others · 2 buildings · 103 unitsRERA P51700016173

Krishna Darshan

Deedo IDDP-THN-Z8ZB

Completion was pushed back 1 year to Mar 2023, and that date has passed too; no MahaRERA orders on record; 96% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Shri Krishna Realtors

Delivery4 yrs 8 mo latePromised Mar 2022 · revised Mar 2023 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales96% booked99 of 103 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Mar 2023, and that date has passed too

  • This projectRegistered 20 Apr 2018, completion promised 30 Mar 2022, revised to 30 Mar 2023, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700016173
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001617320 Apr 201830 Mar 202230 Mar 2023Shri Krishna RealtorsProject page
Documents56

2 documents held by Deedo, 54 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardpan card shrii krishana realtors.pdf · uploaded 18 Apr 2018Source

Legal

  • Declaration Form BAffidavit cum Decleration.pdf · uploaded 18 Apr 2018Source
  • Legal Title reportTitle Certificate.pdf · uploaded 18 Apr 2018Source

Migrated

  • 1 PAN Cardpan card shrii krishana realtors.pdf · uploaded 18 Apr 2018Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 18 Apr 2018Source
  • 1 Details of encumbrancesDecleration of encumbrances.pdf · uploaded 18 Apr 2018Source
Show all 56 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20180413_0005 Layout.PDF · uploaded 18 Apr 2018Source
  • 1 Building Plan Approval (IOD)MYSCAN_20180413_0004.PDF · uploaded 18 Apr 2018Source
  • 2 Building Plan Approval (IOD)MYSCAN_20180413_0006.PDF · uploaded 18 Apr 2018Source
  • 3 Building Plan Approval (IOD)MYSCAN_20180413_0007.PDF · uploaded 18 Apr 2018Source
  • 4 Building Plan Approval (IOD)MYSCAN_20180413_0008.PDF · uploaded 18 Apr 2018Source
  • 5 Building Plan Approval (IOD)MYSCAN_20180413_0009-min.pdf · uploaded 18 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 18 Apr 2018Source
  • 1 Declaration in FORM BAffidavit cum Decleration.pdf · uploaded 18 Apr 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects certificate.pdf · uploaded 18 Apr 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eneineering Certificate.pdf · uploaded 18 Apr 2018Source
  • 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 18 Apr 2018Source
  • 1 Proforma of Allotment letterPROVISIONAL__ALLOTMENT__LETTER (1) (1).pdf · uploaded 18 Apr 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 (UT).pdf · uploaded 30 Dec 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Certificate.pdf · uploaded 7 Oct 2023Source
  • 6 Building Plan Approval (IOD)HPSCANNER9791.pdf · uploaded 8 Oct 2023Source
  • 7 Building Plan Approval (IOD)HPSCANNER9792.pdf · uploaded 8 Oct 2023Source
  • 8 Building Plan Approval (IOD)HPSCANNER9793.pdf · uploaded 8 Oct 2023Source
  • 9 Building Plan Approval (IOD)HPSCANNER9794.pdf · uploaded 8 Oct 2023Source
  • 10 Building Plan Approval (IOD)HPSCANNER9795.pdf · uploaded 8 Oct 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC (certificate).pdf · uploaded 8 Oct 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 31-3-19.pdf · uploaded 25 Oct 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 31-3-20.pdf · uploaded 25 Oct 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 31-3-21.pdf · uploaded 25 Oct 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 31-3-22.pdf · uploaded 25 Oct 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31-03-2019.pdf · uploaded 25 Oct 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31-03-2020.pdf · uploaded 25 Oct 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31-03-21.pdf · uploaded 25 Oct 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31-03-22.pdf · uploaded 25 Oct 2023Source
  • 2 Certificates of CA (Form 3)CA Certificate March 2019.pdf · uploaded 27 Oct 2023Source
  • 3 Certificates of CA (Form 3)Form 3 31-03-2020 SKR.pdf · uploaded 29 Oct 2023Source
  • 4 Certificates of CA (Form 3)Form 3 31-3-21 SKR.pdf · uploaded 29 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-20 SKR.pdf · uploaded 29 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2020-21 SKR.pdf · uploaded 29 Oct 2023Source
  • 5 Certificates of CA (Form 3)Form 3 31-03-2022.pdf · uploaded 1 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2021-22 SKR .pdf · uploaded 1 Nov 2023Source

Technical

  • DocumentMYSCAN_20180413_0005 Layout.PDF · uploaded 18 Apr 2018Source
  • DocumentMYSCAN_20180413_0004.PDF · uploaded 18 Apr 2018Source
  • DocumentMYSCAN_20180413_0006.PDF · uploaded 18 Apr 2018Source
  • DocumentMYSCAN_20180413_0007.PDF · uploaded 18 Apr 2018Source
  • DocumentMYSCAN_20180413_0008.PDF · uploaded 18 Apr 2018Source
  • DocumentMYSCAN_20180413_0009-min.pdf · uploaded 18 Apr 2018Source
  • DocumentHPSCANNER9791.pdf · uploaded 8 Oct 2023Source
  • DocumentHPSCANNER9792.pdf · uploaded 8 Oct 2023Source
  • DocumentHPSCANNER9793.pdf · uploaded 8 Oct 2023Source
  • DocumentHPSCANNER9794.pdf · uploaded 8 Oct 2023Source
  • DocumentHPSCANNER9795.pdf · uploaded 8 Oct 2023Source

Technical (Architect)

  • DocumentArchitect Certificate 31-3-22.pdf · uploaded 25 Oct 2023Source

Technical (Engineer)

  • DocumentForm 2 - 31-03-22.pdf · uploaded 25 Oct 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 82 HISSA NO 5

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1BHK, 2 BHK, 2BHK, Commercial, Office, Shop103 units in all
Address
Survey No 82 Hissa No 5, Badlapur Gaon Road, Kulgaon BadlapurPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
4,275 sq m (46,020 sq ft)
Permissible built-up area
5,225 sq m (56,246 sq ft)
Sanctioned built-up area
4,275 sq m (46,020 sq ft)
Designated bank account
66
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO 82 HISSA NO 5

Land as published on MahaRERA's project page

SURVEY NO 82 HISSA NO 5

Boundaries

North
Survey No 82 4 18 Mt Wide Dp Road
South
Survey No 82 5
East
Survey No 82 5
West
Survey No 82 7

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking103 units

99 of 103 units booked (96%), as the promoter reported to MahaRERA

1 BHK · 37 units1BHK · 7 units2 BHK · 43 units2BHK · 8 unitsCommercial · 2 unitsOffice · 2 unitsShop · 4 units
BuildingTypeCarpet areaUnitsBooked
A Wing1 BHK30.94 sq m · 333 sq ft99
A Wing1 BHK31.14 sq m · 335 sq ft99
A Wing1 BHK31.25 sq m · 336 sq ft99
A Wing1 BHK31.54 sq m · 339 sq ft1010
A Wing1BHK32.72 sq m · 352 sq ft22
A Wing1BHK33.5 sq m · 361 sq ft22
A Wing1BHK33.68 sq m · 363 sq ft11
A Wing1BHK33.87 sq m · 365 sq ft22
Show all 29 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Wing2 BHK36.12 sq m · 389 sq ft99
A Wing2 BHK36.13 sq m · 389 sq ft99
A Wing2 BHK36.14 sq m · 389 sq ft11
A Wing2 BHK36.31 sq m · 391 sq ft11
A Wing2 BHK39.05 sq m · 420 sq ft99
A Wing2 BHK39.3 sq m · 423 sq ft1010
A Wing2BHK47.42 sq m · 510 sq ft11
A Wing2BHK47.56 sq m · 512 sq ft22
A Wing2BHK47.59 sq m · 512 sq ft22
A Wing2BHK48.15 sq m · 518 sq ft22
A Wing2BHK81.42 sq m · 876 sq ft11
A WingCommercial135.75 sq m · 1,461 sq ft10
A WingOffice135.63 sq m · 1,460 sq ft10
A WingShop14.3 sq m · 154 sq ft11
A WingShop23.94 sq m · 258 sq ft11
A WingShop25.24 sq m · 272 sq ft10
A WingShop26.09 sq m · 281 sq ft10
B Wing2 BHK47.33 sq m · 509 sq ft22
B Wing2 BHK49.78 sq m · 536 sq ft22
B WingCommercial167.31 sq m · 1,801 sq ft11
B WingOffice268.94 sq m · 2,895 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSatish Oak—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology