Skip to content
Extended 12 mo16 floorsRERA P51700016173

A Wing, Krishna Darshan

Deedo IDDP-THN-Z8ZB-A

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked96%93 of 97 · MahaRERA
Completion30 Mar 202330 Mar 2022 · revised
Units & parking in A Wing
TypeCarpet areaUnitsBooked
1 BHK30.9 m² (333 sq.ft)99
1 BHK31.1 m² (335 sq.ft)99
1 BHK31.3 m² (336 sq.ft)99
1 BHK31.5 m² (339 sq.ft)1010
1BHK32.7 m² (352 sq.ft)22
1BHK33.5 m² (361 sq.ft)22
1BHK33.7 m² (363 sq.ft)11
1BHK33.9 m² (365 sq.ft)22
2 BHK36.1 m² (389 sq.ft)99
2 BHK36.1 m² (389 sq.ft)99
2 BHK36.1 m² (389 sq.ft)11
2 BHK36.3 m² (391 sq.ft)11
2 BHK39.1 m² (420 sq.ft)99
2 BHK39.3 m² (423 sq.ft)1010
2BHK47.4 m² (510 sq.ft)11
2BHK47.6 m² (512 sq.ft)22
2BHK47.6 m² (512 sq.ft)22
2BHK48.2 m² (518 sq.ft)22
2BHK81.4 m² (876 sq.ft)11
COMMERCIAL135.8 m² (1,461 sq.ft)10
OFFICE135.6 m² (1,460 sq.ft)10
SHOP14.3 m² (154 sq.ft)11
SHOP23.9 m² (258 sq.ft)11
SHOP25.2 m² (272 sq.ft)10
SHOP26.1 m² (281 sq.ft)10
As registered with MahaRERA
RERA registration
P51700016173 · registered 20 Apr 2018
Promised completion
30 Mar 2022
Revised completion
30 Mar 2023
Sanctioned habitable floors
16
Sanctioned floors (incl. basement, stilt, podium)
16
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
Deedo IDDP-THN-Z8ZB-A
Questions about A Wing

When is A Wing due for completion?

The MahaRERA registration promises 30 Mar 2022, revised to 30 Mar 2023.

How many floors does A Wing have?

16 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology