RERA projects in Dawale
3 projects under 3 MahaRERA registrations, registered 2026–2026. 100% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
3Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2026 | 3 |
Projects in Dawale
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shiv Shriditya HeightsShree Narayan Enterprises | PM1330002601057 | 6 Jul 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Narayan ResidencyM/S Kanak Realtors | PR1330002600661 | 4 Jun 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Laxmi Aangan - KaveriKanji Murji Mange | PR1330002600204 | 18 Apr 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
Other localities in Thane
Most active promoters
By projects registered here, as named on MahaRERA.
- Kanji Murji Mange1 project
- M/S Kanak Realtors1 project
- Shree Narayan Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology