New Era C
Deedo IDDP-THN-T84CIts promised completion date, Dec 2021, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Kalyan, Maharashtra 421201 · by Yogi Developers Corporation
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed
- This projectRegistered 27 Nov 2017, completion promised 30 Dec 2021, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700014365
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700014365 | 27 Nov 2017 | 30 Dec 2021 | 30 Dec 2021 | M/s. YOGI DEVELOPERS CORPORATION | Project page |
Documents42
1 document held by Deedo, 41 filings listed on MahaRERA's project page
Finance
- PAN Cardyogi developers corp PAN card.pdf · uploaded 20 Nov 2017Source
Legal
- OtherPartnership Deed.pdf · uploaded 20 Nov 2017Source
- Declaration Form BForm B.pdf · uploaded 20 Nov 2017Source
- Legal Title reportTitle Certificate red.pdf · uploaded 20 Nov 2017Source
- Legal Title reportTitle Certificate Deepak R Shah.pdf · uploaded 20 Nov 2017Source
- OtherOC Newera.pdf · uploaded 9 Apr 2019Source
Migrated
- 1 PAN Cardyogi developers corp PAN card.pdf · uploaded 20 Nov 2017Source
Show all 42 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTitle Certificate red.pdf · uploaded 20 Nov 2017Source
- 2 Copy of the legal title reportTitle Certificate Deepak R Shah.pdf · uploaded 20 Nov 2017Source
- 1 Details of encumbrancesDeatils of Encumbrance.pdf · uploaded 20 Nov 2017Source
- 1 Copy of Layout Approval (in case of layout)Elevation plan.pdf · uploaded 20 Nov 2017Source
- 2 Copy of Layout Approval (in case of layout)Elevation plan.pdf · uploaded 20 Nov 2017Source
- 3 Copy of Layout Approval (in case of layout)Layout plan.pdf · uploaded 20 Nov 2017Source
- 4 Copy of Layout Approval (in case of layout)Podium plan.pdf · uploaded 20 Nov 2017Source
- 5 Copy of Layout Approval (in case of layout)stilt and floor plan.pdf · uploaded 20 Nov 2017Source
- 6 Copy of Layout Approval (in case of layout)first floor plan.pdf · uploaded 20 Nov 2017Source
- 7 Copy of Layout Approval (in case of layout)Ground floor plan.pdf · uploaded 20 Nov 2017Source
- 1 Building Plan Approval (IOD)Building Permission - CC red.pdf · uploaded 20 Nov 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permission - CC red.pdf · uploaded 20 Nov 2017Source
- 1 Declaration in FORM BForm B.pdf · uploaded 20 Nov 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 20 Nov 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 20 Nov 2017Source
- 1 Certificates of CA (Form 3)Chartered Accountant Certificate.pdf · uploaded 20 Nov 2017Source
- 1 Proforma of Allotment letterProforma of Allotment letter cum Undertaking.pdf · uploaded 20 Nov 2017Source
- 1 OtherPartnership Deed.pdf · uploaded 20 Nov 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised CC New Era C.pdf · uploaded 6 Dec 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Quarterly Updated Architect Certificate New Era C Feb 2018.pdf · uploaded 10 Mar 2018Source
- 2 Certificates of CA (Form 3)Quarterly Update CA Certificate New Era C Feb 2018.pdf · uploaded 10 Mar 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Quarterly Updated Engineer's Certificate New Era C.pdf · uploaded 12 Mar 2018Source
- 3 Commencement Certificates / NA Order for plotted developmentRevised CC New Era C.pdf · uploaded 20 Mar 2018Source
- 2 OtherOC Newera.pdf · uploaded 9 Apr 2019Source
Technical
- DocumentElevation plan.pdf · uploaded 20 Nov 2017Source
- DocumentElevation plan.pdf · uploaded 20 Nov 2017Source
- DocumentLayout plan.pdf · uploaded 20 Nov 2017Source
- DocumentPodium plan.pdf · uploaded 20 Nov 2017Source
- Documentstilt and floor plan.pdf · uploaded 20 Nov 2017Source
- Documentfirst floor plan.pdf · uploaded 20 Nov 2017Source
- DocumentGround floor plan.pdf · uploaded 20 Nov 2017Source
- DocumentBuilding Permission - CC red.pdf · uploaded 20 Nov 2017Source
Technical (Architect)
- DocumentQuarterly Updated Architect Certificate New Era C Feb 2018.pdf · uploaded 10 Mar 2018Source
Technical (Engineer)
- DocumentQuarterly Updated Engineer's Certificate New Era C.pdf · uploaded 12 Mar 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 2 BHK, Shop No. 13, Shop no. 14, Shop No. 15, Shop No. 16, Shop No. 17, Shop No. 18, Shop No. 19, Shop No. 20, Shop No. 21, Shop No. 22, Shop No. 23, Shop No. 24, Shop No. 25, Shop No. 26, Shop No. 27, Shop No. 28, Shop No. 29, Shop No. 30144 units in all
- Address
- 22, 1/8, 1/1, 2, 3, 24, 2pt, 2pt, 2pt, 2pt, 2pt, 2pt, 2pt, 2pt, 2pt, 25 H no 1, 2, 3, 4pt, 4pt, 5, 6, 7, 26PIN 421201
- Village
- Kalyan-Dombivali (M Corp.), Kalyan taluka
- Location
- 19.24742, 73.15289
- Land area for this project
- 66,322 sq m (7,13,885 sq ft)
- Permissible built-up area
- 6,821 sq m (73,420 sq ft)
- Sanctioned built-up area
- 6,821 sq m (73,420 sq ft)
- Recreational open space
- 10,178 sq m (1,09,559 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Land as published on MahaRERA's project page
22,1/8,1/1,2,3, 24,2pt,2pt,2pt,2pt,2pt,2pt,2pt,2pt,2pt, 25 H no 1,2,3,4pt,4pt,5,6,7, 26
Boundaries
- North
- 12 meters D P Road
- South
- 18 meters D P Road
- East
- Survey No 22part
- West
- 12 meters D P Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking144 units
144 of 144 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 38.7 sq m · 417 sq ft | 42 | 42 |
| 1 BHK | 42.3 sq m · 455 sq ft | 42 | 42 |
| 2 BHK | 57.25 sq m · 616 sq ft | 42 | 42 |
| Shop No. 13 | 24.15 sq m · 260 sq ft | 1 | 1 |
| Shop no. 14 | 24 sq m · 258 sq ft | 1 | 1 |
| Shop No. 15 | 21.25 sq m · 229 sq ft | 1 | 1 |
| Shop No. 16 | 21.1 sq m · 227 sq ft | 1 | 1 |
| Shop No. 17 | 62.95 sq m · 678 sq ft | 1 | 1 |
Show all 21 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop No. 18 | 51.8 sq m · 558 sq ft | 1 | 1 |
| Shop No. 19 | 51.3 sq m · 552 sq ft | 1 | 1 |
| Shop No. 20 | 53.65 sq m · 577 sq ft | 1 | 1 |
| Shop No. 21 | 35 sq m · 377 sq ft | 1 | 1 |
| Shop No. 22 | 19.6 sq m · 211 sq ft | 1 | 1 |
| Shop No. 23 | 36.3 sq m · 391 sq ft | 1 | 1 |
| Shop No. 24 | 35.5 sq m · 382 sq ft | 1 | 1 |
| Shop No. 25 | 35.5 sq m · 382 sq ft | 1 | 1 |
| Shop No. 26 | 20.5 sq m · 221 sq ft | 1 | 1 |
| Shop No. 27 | 18.25 sq m · 196 sq ft | 1 | 1 |
| Shop No. 28 | 65.2 sq m · 702 sq ft | 1 | 1 |
| Shop No. 29 | 35.4 sq m · 381 sq ft | 1 | 1 |
| Shop No. 30 | 35.4 sq m · 381 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals29
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ms MQA | — |
| Architect | Ms Rachana Shilp | — |
| Chartered accountant | Parthiv & Co | — |
| Engineer | Ms J W Consultant | — |
| Other | Ms Buildcon Enterprises | — |
| Other | Ms Jyoti Enterprises | — |
| Other | Ms KGN interior Decorators | — |
| Other | Ms K P Construction | — |
Show all 29 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Other | Ms Maa Shards Electricals | — |
| Other | Ms Malak Glazing Systems | — |
| Other | Ms Om Plumbing Works | — |
| Other | Ms Parisparsh | — |
| Other | Ms Ramesh Sharma | — |
| Other | Ms Sadanand Ghadge | — |
| Other | Ms Sharda Aluminium | — |
| Other | Ms Shraddha Plumbing System Pvt Ltd | — |
| Other | Ms Spectrum Paints | — |
| Other | Ms Yasin MM Mallabadi | — |
| Registered real estate agent | Deepu J Shetty | — |
| Registered real estate agent | Elara Marketing Services Private Limited | — |
| Registered real estate agent | HDFC Realty Limited | — |
| Registered real estate agent | ICICI Home Finance Company Limited | — |
| Registered real estate agent | Manisha Nair | — |
| Registered real estate agent | Manish Chetwani | — |
| Registered real estate agent | Mumbai Property Exchange Pvt Ltd | — |
| Registered real estate agent | New Project Deals | — |
| Registered real estate agent | Prashant Harishchandra Ambade | — |
| Registered real estate agent | Ravindra Agrawal | — |
| Registered real estate agent | Shailendra Shivnandan Shukla | — |
Source: MahaRERA project page. Contact details are not shown.