Delayed projects in Thane
1,161 MahaRERA projects in Thane are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 4 of 24.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Sai IshwarMohan Kedarnath Krishnavanshi | Vehlonde | Dec 2020 | Jun 2023 | 5 yrs 11 mo late |
| Tharwanis Meghna Montana Phase - 2Tharwani Constructions Pvt Ltd | Ambarnath | Dec 2020 | Aug 2024 | 5 yrs 11 mo late |
| Vrundavan-IShree Vastucreation Developers | Devrung | Dec 2020 | Jun 2022 | 5 yrs 11 mo late |
| vardhaman vatikarashilifestyle | Sarmal | Dec 2020 | Jun 2022 | 5 yrs 11 mo late |
| Deeplaxmi HeightDeep Laxmi Developers | Kalher (Ct) | Dec 2020 | Dec 2022 | 5 yrs 11 mo late |
| Shree Mahaganpati TowerMahesh Shyamsundar Goyal | Titwala | Dec 2020 | Feb 2023 | 5 yrs 11 mo late |
| Triveni SangamSaptshrungi Construction Co | Ambarnath (R) | Jan 2021 | Oct 2022 | 5 yrs 10 mo late |
| Lifestyle City Kalyan AmazonNirmal Lifestyle (Kalyan) Private Limited | Vadavali Kh. | Jan 2021 | Dec 2023 | 5 yrs 10 mo late |
| PrabhatSamay Homes | Thane (M Corp.) | Jan 2021 | Dec 2021 | 5 yrs 10 mo late |
| Satis ChsPacific Impression | Dombivli | Jan 2021 | Mar 2023 | 5 yrs 10 mo late |
| Hari Om ArcadeIdeal Enterprises | Thane (M Corp.) | Feb 2021 | Feb 2021 | 5 yrs 9 mo late |
| Nalanda ChsYash Infra | Thane (M Corp.) | Feb 2021 | Feb 2021 | 5 yrs 9 mo late |
| Raj NirvanaRaj Homes & Infracon | Ambarnath (R) | Mar 2021 | Jun 2022 | 5 yrs 8 mo late |
| The One PearlVibha Realtors | Kalyan | May 2021 | May 2024 | 5 yrs 6 mo late |
| M K Thakur Complex Phase 2Vraj Ratan Buildcon Pvt Ltd | Nighu | Jun 2021 | Jun 2022 | 5 yrs 5 mo late |
| Anuraj HeightsShiva Bhopi Developers LLP | Dombivli | Jun 2021 | Jun 2023 | 5 yrs 5 mo late |
| AtlantisAshwamedh Builders & Developers | Panchpakhadi | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| CrossvillaShreeya Enterprises | Thane (M Corp.) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Green Willows Phase IIGreen Lifespaces | Shendrun Bk. | Jun 2021 | Jun 2021 | 5 yrs 5 mo late |
| Horizon FloraK M Enterprises | Thane (M Corp.) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Kavya GrandeurJupiter Landscapes Pvt. Ltd. | Thane (M Corp.) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Laxmi NarayanGavdevi Infra | Badlapur (M Cl) | Jun 2021 | Dec 2024 | 5 yrs 5 mo late |
| Lok Mangal SrushtiBalaram Gopal Gawli | Kalyan | Jun 2021 | Jun 2022 | 5 yrs 5 mo late |
| Pride TowerShree Gajanan Builders & Developers | Shahapur | Jun 2021 | Dec 2023 | 5 yrs 5 mo late |
| Rajeshwari ResidencyShree Siddhi Construction | Manda | Jun 2021 | Jun 2022 | 5 yrs 5 mo late |
| Sai Gangat ApartmentMnr Developers | Thane (M Corp.) | Jun 2021 | Jun 2025 | 5 yrs 5 mo late |
| Sai Siddhi Residency A WingSai Siddhi Developers | Titwala | Jun 2021 | — | 5 yrs 5 mo late |
| Sai SolitaireShraddha Sai Shelters | Ulhasnagar (M Corp.) | Jun 2021 | Aug 2022 | 5 yrs 5 mo late |
| Sajan Shantaram HeightTirupati Developers | Dombivli | Jun 2021 | Jun 2023 | 5 yrs 5 mo late |
| Sarvoday ShwetaRachana Enterprises | Dombivli | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Siddhi Yashwant ComplexSiddharth Narayan Tangdi | Bhiwandi | Jun 2021 | Dec 2024 | 5 yrs 5 mo late |
| Siddhivinayak SapphireShrikant Dhondu Hindalkar | Navi Mumbai (M Corp.) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Suraj Rama HeightsShree Rama Shree Construction Pvt Ltd | Panchpakhadi | Jun 2021 | Dec 2025 | 5 yrs 5 mo late |
| Sai Orchid Phase 1gupta builders and developers | Dawadi | Jun 2021 | Jun 2024 | 5 yrs 5 mo late |
| Vedant VatikaSiddhivinayak Developers | Manda | Jun 2021 | Jun 2021 | 5 yrs 5 mo late |
| Zp Hill Wing D G HRohan Construction | Ambarnath(M Cl) | Jun 2021 | Sep 2022 | 5 yrs 5 mo late |
| Nayan ApartmentNanda Santosh Bhoir | Adharwadi | Jul 2021 | Jan 2023 | 5 yrs 4 mo late |
| Ramchandra ResidencyJagjeet Builder | Thane (M Corp.) | Aug 2021 | Aug 2024 | 5 yrs 3 mo late |
| Cosmos Habitate A WingConcorde Associates | Majiwade | Sep 2021 | Jun 2024 | 5 yrs 2 mo late |
| Prithvi Pride Phase-IPrithvi Land Developers | Mirabhayandar (M Corp.) | Sep 2021 | Oct 2022 | 5 yrs 2 mo late |
| The Woods Phase IIILaxmi Buildcon LLP | Ambarnath (R) | Oct 2021 | Oct 2021 | 5 yrs 1 mo late |
| Planet ShelterShaikh Azim Ibrahim | Navi Mumbai (M Corp.) | Nov 2021 | Dec 2024 | 5 yrs late |
| Our Town - Majestic ApartmentsKaiyomerz Cowas Palia | Dalkhan | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Ira PearlRonak Builders & Developers | Nerul | Dec 2021 | Jan 2026 | 4 yrs 11 mo late |
| Ramleela Co-operative Housing Society LimitedYash Infra | Thane (M Corp.) | Dec 2021 | Mar 2026 | 4 yrs 11 mo late |
| Abdullah ArcadeShahnawaz Farooque Ahmed Momin | Bhiwandi (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Building No 4 Phase I Part Of Vardhaman Vatika Phase 2Grow More Infracon | Sarmal | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Bunch BerrySeema Land Developers | Sakurli | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Chahu ApartmentMul Aakar Developers | Dombivli | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Chaitanya HeightsJai Sai Enterprises | Bhiwandi (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
Delayed projects by district
All MaharashtraPune · 2,218Thane · 1,161Raigarh · 1,042Mumbai Suburban · 996Nashik · 481Palghar · 364Nagpur · 323Aurangabad · 243Mumbai City · 243Satara · 228Ratnagiri · 193Sangli · 176Solapur · 156Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 11Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology