Sarmal, Thane

8 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4
Registrations4
Completion still due22 past their date
Median extension18 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

Projects in Sarmal

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vardhaman Vatika Phase 3 Building No 4Vardhaman VentureP517000513328 Jun 202330 Jun 202830 Jun 2028Not yet due0
Building No 5 Vardhaman Vatika Pahse IIVardhaman InfrastructureP517000222225 Sep 201930 Dec 202331 Dec 2027Extended 48 mo0
VARDHAMAN VATIKA PHASE iii BUILD NO 3Vardhaman VentureP517000215418 Jul 201930 Dec 202230 Jun 2023Extended 6 mo0
vardhaman vatikarashilifestyleP517000128027 Sep 201730 Dec 202030 Jun 2022Extended 18 mo0

Most active promoters

  1. Vardhaman Venture2 projects
  2. rashilifestyle1 project
  3. Vardhaman Infrastructure1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology