Sarmal, Thane
8 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects4
Registrations4
Completion still due22 past their date
Median extension18 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Sarmal
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vardhaman Vatika Phase 3 Building No 4Vardhaman Venture | P51700051332 | 8 Jun 2023 | 30 Jun 2028 | 30 Jun 2028 | Not yet due | 0 |
| Building No 5 Vardhaman Vatika Pahse IIVardhaman Infrastructure | P51700022222 | 5 Sep 2019 | 30 Dec 2023 | 31 Dec 2027 | Extended 48 mo | 0 |
| VARDHAMAN VATIKA PHASE iii BUILD NO 3Vardhaman Venture | P51700021541 | 8 Jul 2019 | 30 Dec 2022 | 30 Jun 2023 | Extended 6 mo | 0 |
| vardhaman vatikarashilifestyle | P51700012802 | 7 Sep 2017 | 30 Dec 2020 | 30 Jun 2022 | Extended 18 mo | 0 |
Nearby: other localities in Shahapur
Most active promoters
- Vardhaman Venture2 projects
- rashilifestyle1 project
- Vardhaman Infrastructure1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology