RERA projects in Shahapur (Ct)

35 projects under 35 MahaRERA registrations, registered 2017–2026. 40% have a completion date extended beyond the one promised.

Locality
35RERA projects
35Registrations
17Completion still due18 past their completion date, 1 marked completed
4 monthsMedian extension beyond promised date40% of registrations extended
9Regulatory caseson 1 project
68Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20174
20183
20191
20202
20213
20227
20237
20246
20250
20262

Projects in Shahapur (Ct)

35 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Chintamani Habitat (Fortuna Bungalow)Jashnani Constructions Private LimitedPR133000260153713 Aug 202631 Dec 202931 Dec 2029Not yet due0
Shree Nirmala HeightsRui DevelopersPR13300026011109 Jul 202631 Dec 202830 Apr 2029Extended 4 mo0
Lotus PridePankaj Pandharinath JageP5170007744916 Aug 202431 Dec 202730 Apr 2028Extended 4 mo0
Rivera HomesKhushi DevelopersP5170005607310 May 202431 Dec 202830 Apr 2029Extended 4 mo0
Bhagwati HeightsPerfect RealityP517000556828 Apr 202431 Dec 202730 Apr 2028Extended 4 mo0
Maheshvara AvenueKalyani Shivaji GoraleP517000556465 Apr 202430 Jun 2029—Not yet due0
Arya ApartmentSeema Ramesh KadavP5170005539322 Mar 202431 Dec 202830 Apr 2029Extended 4 mo0
Sawant HeightsAkash Ashok SawantP5170005458631 Jan 202431 Dec 202630 Apr 2027Extended 4 mo0
VisavaM/s Rudrik DevelopersP5170005411727 Dec 202331 Dec 202730 Apr 2028Extended 4 mo0
Awasare HeightsRajkumar Tuljaram AswaniP5170005394211 Dec 202330 Sep 202630 Jan 2027Extended 4 mo0
Krishna CrownShree Krishna RealityP5170005156727 Jun 202331 Oct 202631 Oct 2026Not yet due0
Silver Oak ApartmentAshokkumar Topanlal DewaniP517000512101 Jun 202331 Mar 202531 Mar 2025Promised date passed0
Silver ParkMahalaxmi DevelopersP517000512031 Jun 202331 Dec 202531 Dec 2025Promised date passed0
Santosh ApartmentGajanan Kathod ShelavaleP517000492473 Feb 202331 Dec 202730 Apr 2028Extended 4 mo0
Shri Hari Vitthal ViharAj HomesP5170004879617 Jan 202331 Aug 202731 Dec 2027Extended 4 mo0
Krishna DhamRoyal GroupP5170004820715 Dec 202231 Dec 202431 Dec 2025Extended 12 mo0
Laxmi ArcadeSatish Kashinath GujarathiP5170004773221 Nov 202231 Dec 202431 Dec 2024Promised date passed0
Ramanath ApartmentSarvesh ConstructionP517000467321 Sep 202231 Dec 202531 Dec 2025Promised date passed0
Ganesh Darshan ApartmentTirupati ConstructionP5170004598715 Jun 202230 Nov 202330 Nov 2023Promised date passed0
Chintamani Habitat Jasmine Type A-B-JJashnani Construction Private LimitedP5170003489128 Apr 202231 Dec 202531 Dec 2025Promised date passed0
Model TownQavi Construction Pvt. Ltd.P517000338338 Mar 202231 Dec 202631 Dec 2026Not yet due0
Sai PalaceVardhaman DevelopersP517000330013 Feb 202231 Oct 202631 Oct 2026Not yet due0
SarojiniJay Service And ConsultantP517000310475 Oct 202131 Dec 202531 Dec 2025Promised date passed0
Baradia EkdantBaradia RealtyP5170003036517 Aug 202122 Jul 202622 Nov 2026Extended 4 mo0
Vishwam SahanivasRajesh Sitaram DhumalP5170002834718 Feb 202130 Jun 202330 Jun 2023Promised date passed0

Other localities in Shahapur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Jashnani Construction Private Limited5 projects
  2. Jay Service And Consultant2 projects
  3. Qavi Construction Pvt. Ltd.2 projects
  4. Aj Homes1 project
  5. Akash Ashok Sawant1 project
  6. Ashokkumar Topanlal Dewani1 project
  7. Baradia Realty1 project
  8. Gajanan Kathod Shelavale1 project
  9. Gajanan Katod Shelavale1 project
  10. Jashnani Constructions Private Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology