RERA projects in Khardi (Ct)
3 projects under 4 MahaRERA registrations, registered 2017–2023. 50% have a completion date extended beyond the one promised.
Locality
3RERA projects
4Registrationssome projects hold several
2Completion still due2 past their completion date
26 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
12Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 2 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
Projects in Khardi (Ct)
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Icon ApartmentIcon Construction Builders & Developers | P51700050313 | 1 Apr 2023 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Parshava ParkVardhaman Enterprises | P51700021734, P51700021828 | 22 Jul 2019 | 30 Dec 2031 | 30 Dec 2031 | Not yet due | 0 |
| Uma Residency, Phase IAdarsh Infra Developers | P51700011302 | 31 Aug 2017 | 31 Aug 2026 | 31 Aug 2026 | Promised date passed | 0 |
Other localities in Shahapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Adarsh Infra Developers1 project
- Icon Construction Builders & Developers1 project
- Vardhaman Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology