Residential / Group Housing · 5 buildings · 120 unitsRERA P51700011302

Uma Residency, Phase I

Deedo IDDP-THN-ZM76

Its promised completion date, Aug 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 22% of its units are booked.

Khardi (Ct), Thane 421601 · by Adarsh Infra Developers

Delivery3 mo past duePromised Aug 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales22% booked26 of 120 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Aug 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 31 Aug 2017, completion promised 31 Aug 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700011302
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001130231 Aug 201731 Aug 202631 Aug 2026Adarsh Infra DevelopersProject page
Documents162

1 document held by Deedo, 161 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportTitle Report.pdf · uploaded 20 Aug 2017Source
  • Declaration Form BForm B promoter-ilovepdf-compressed.pdf · uploaded 20 Aug 2017Source
  • Declaration Form BForm B_organized.pdf · uploaded 19 Mar 2024Source

Migrated

  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 20 Aug 2017Source
  • 1 Details of encumbrancesCERTIFICATE of Encumbrances.pdf · uploaded 20 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 20 Aug 2017Source
  • 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 20 Aug 2017Source
Show all 162 documentsShow fewer documents

Migrated

  • 3 Copy of Layout Approval (in case of layout)3.pdf · uploaded 20 Aug 2017Source
  • 4 Copy of Layout Approval (in case of layout)4.pdf · uploaded 20 Aug 2017Source
  • 5 Copy of Layout Approval (in case of layout)5.pdf · uploaded 20 Aug 2017Source
  • 6 Copy of Layout Approval (in case of layout)6.pdf · uploaded 20 Aug 2017Source
  • 7 Copy of Layout Approval (in case of layout)7.pdf · uploaded 20 Aug 2017Source
  • 8 Copy of Layout Approval (in case of layout)8.pdf · uploaded 20 Aug 2017Source
  • 9 Copy of Layout Approval (in case of layout)9.pdf · uploaded 20 Aug 2017Source
  • 1 Building Plan Approval (IOD)1.pdf · uploaded 20 Aug 2017Source
  • 2 Building Plan Approval (IOD)2.pdf · uploaded 20 Aug 2017Source
  • 3 Building Plan Approval (IOD)3.pdf · uploaded 20 Aug 2017Source
  • 4 Building Plan Approval (IOD)4.pdf · uploaded 20 Aug 2017Source
  • 5 Building Plan Approval (IOD)5.pdf · uploaded 20 Aug 2017Source
  • 6 Building Plan Approval (IOD)6.pdf · uploaded 20 Aug 2017Source
  • 7 Building Plan Approval (IOD)7.pdf · uploaded 20 Aug 2017Source
  • 8 Building Plan Approval (IOD)8.pdf · uploaded 20 Aug 2017Source
  • 9 Building Plan Approval (IOD)9.pdf · uploaded 20 Aug 2017Source
  • 1 Declaration in FORM BForm B promoter-ilovepdf-compressed.pdf · uploaded 20 Aug 2017Source
  • 1 Certificates of CA (Form 3)ADARSH_INFRA.pdf · uploaded 20 Aug 2017Source
  • 1 Proforma of Allotment letterRera Agreement.pdf · uploaded 20 Aug 2017Source
  • 2 Proforma of Allotment letterAllotment Letter Format.pdf · uploaded 20 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1-Final-ilovepdf-compressed (1).pdf · uploaded 10 May 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1-Final-ilovepdf-compressed (1).pdf · uploaded 10 May 2018Source
  • 2 Certificates of CA (Form 3)FORM 3.pdf · uploaded 10 May 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 11 May 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2-Final - Reduced.pdf · uploaded 11 May 2018Source
  • 1 Certificates of CA (Form 5)form 5 Adarsh-ilovepdf-compressed.pdf · uploaded 15 Oct 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Adarsh.pdf · uploaded 3 Apr 2021Source
  • 3 Certificates of CA (Form 3)Form 3 - Adarsh_compressed (1).pdf · uploaded 4 Jun 2021Source
  • 1 Declaration about Commencement CertificateForm D - Adarsh.pdf · uploaded 24 Jul 2021Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1_compressed.pdf · uploaded 24 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - Adarsh.pdf · uploaded 24 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryFlat Details- Adarsh_compressed.pdf · uploaded 24 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 24 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 - Uma Residency Phase I.pdf · uploaded 3 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 6 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 6 Feb 2024Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 June 21.pdf · uploaded 15 Feb 2024Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 Sep 21.pdf · uploaded 15 Feb 2024Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 31 Dec 21.pdf · uploaded 15 Feb 2024Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 31 Mar 22.pdf · uploaded 15 Feb 2024Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 June 22.pdf · uploaded 15 Feb 2024Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 Sep 22.pdf · uploaded 15 Feb 2024Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 31 Dec 22.pdf · uploaded 15 Feb 2024Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 31 Mar 23.pdf · uploaded 15 Feb 2024Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 June 23.pdf · uploaded 15 Feb 2024Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 30 Sep 23.pdf · uploaded 15 Feb 2024Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 31 Dec 23.pdf · uploaded 15 Feb 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)1 Form 2 till 30 06 21.pdf · uploaded 27 Feb 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2 Form 2 till 30 09 21.pdf · uploaded 27 Feb 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)3 Form 2 till 31 12 21.pdf · uploaded 27 Feb 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)4 Form 2 till 31 03 22.pdf · uploaded 27 Feb 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)5 Form 2 till 30 06 22.pdf · uploaded 27 Feb 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)6 Form 2 till 30 09 22.pdf · uploaded 27 Feb 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)7 Form 2 till 31 12 22.pdf · uploaded 27 Feb 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)8 Form 2 till 31 03 23.pdf · uploaded 27 Feb 2024Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)9 Form 2 till 30 06 23.pdf · uploaded 27 Feb 2024Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)10 Form 2 till 30 09 23.pdf · uploaded 27 Feb 2024Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11 Form 2 till 31 12 23.pdf · uploaded 27 Feb 2024Source
  • 4 Certificates of CA (Form 3)1 31 03 2021.pdf · uploaded 7 Mar 2024Source
  • 5 Certificates of CA (Form 3)2 30 06 2021.pdf · uploaded 7 Mar 2024Source
  • 6 Certificates of CA (Form 3)3 30 09 2021.pdf · uploaded 7 Mar 2024Source
  • 7 Certificates of CA (Form 3)4 31 12 2021.pdf · uploaded 7 Mar 2024Source
  • 8 Certificates of CA (Form 3)5 31 03 2022.pdf · uploaded 7 Mar 2024Source
  • 9 Certificates of CA (Form 3)6 30 06 2022.pdf · uploaded 7 Mar 2024Source
  • 10 Certificates of CA (Form 3)7 30 09 2022.pdf · uploaded 7 Mar 2024Source
  • 11 Certificates of CA (Form 3)8 31 12 2022.pdf · uploaded 7 Mar 2024Source
  • 12 Certificates of CA (Form 3)9 31 03 2023.pdf · uploaded 7 Mar 2024Source
  • 13 Certificates of CA (Form 3)10 30 06 2023.pdf · uploaded 7 Mar 2024Source
  • 14 Certificates of CA (Form 3)11 30 09 2023.pdf · uploaded 7 Mar 2024Source
  • 15 Certificates of CA (Form 3)12 31 12 2023.pdf · uploaded 7 Mar 2024Source
  • 2 Declaration in FORM BForm B_organized.pdf · uploaded 19 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A mar 20.pdf · uploaded 19 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A mar 22.pdf · uploaded 19 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A mar 23.pdf · uploaded 19 Mar 2024Source
  • 2 Disclosure of sold/ booked inventoryFlat details signed.pdf · uploaded 21 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Signed.pdf · uploaded 29 Nov 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 310324.pdf · uploaded 28 Jan 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 300624.pdf · uploaded 28 Jan 2025Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 300924.pdf · uploaded 28 Jan 2025Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 311224.pdf · uploaded 28 Jan 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 311224.pdf · uploaded 28 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 1 310324.pdf · uploaded 28 Jan 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 1 310324.pdf · uploaded 28 Jan 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 till 310324.pdf · uploaded 28 Jan 2025Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 till 300624.pdf · uploaded 28 Jan 2025Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 till 300924.pdf · uploaded 28 Jan 2025Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 till 311224.pdf · uploaded 28 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A- 23-24 Adarsh Infra Developers.pdf · uploaded 3 Feb 2025Source
  • 4 Certificates of CA (Form 3)Adarsh Infra Q3.pdf · uploaded 7 Feb 2025Source
  • 3 Certificates of CA (Form 3)Adarsh Infra Q2.pdf · uploaded 7 Feb 2025Source
  • 2 Certificates of CA (Form 3)Adarsh Infra Q1.pdf · uploaded 7 Feb 2025Source
  • 1 Certificates of CA (Form 3)Adarsh Infra 23-24 Q4.pdf · uploaded 7 Feb 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Mar 25.pdf · uploaded 1 May 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 May 2025Source
  • 1 Certificates of CA (Form 3)Form 3_compressed.pdf · uploaded 2 May 2025Source
  • Form 1Form 1.pdf · uploaded 26 Jul 2025Source
  • Form 2Form 2.pdf · uploaded 26 Jul 2025Source
  • Form 3Form 3.pdf · uploaded 26 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDiscloser Sold Unsold Inventory.pdf · uploaded 26 Jul 2025Source
  • Withdrawal Update Form 1Form 1 - Mar 25.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - Adarsh Infra Developers.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 3Form 3 June 25.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 19 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Feb 2026Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 25 Mar 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 21 May 2026Source

Technical

  • Document1.pdf · uploaded 20 Aug 2017Source
  • Document2.pdf · uploaded 20 Aug 2017Source
  • Document3.pdf · uploaded 20 Aug 2017Source
  • Document4.pdf · uploaded 20 Aug 2017Source
  • Document5.pdf · uploaded 20 Aug 2017Source
  • Document6.pdf · uploaded 20 Aug 2017Source
  • Document7.pdf · uploaded 20 Aug 2017Source
  • Document8.pdf · uploaded 20 Aug 2017Source
  • Document9.pdf · uploaded 20 Aug 2017Source
  • Document1.pdf · uploaded 20 Aug 2017Source
  • Document2.pdf · uploaded 20 Aug 2017Source
  • Document3.pdf · uploaded 20 Aug 2017Source
  • Document4.pdf · uploaded 20 Aug 2017Source
  • Document5.pdf · uploaded 20 Aug 2017Source
  • Document6.pdf · uploaded 20 Aug 2017Source
  • Document7.pdf · uploaded 20 Aug 2017Source
  • Document8.pdf · uploaded 20 Aug 2017Source
  • Document9.pdf · uploaded 20 Aug 2017Source

Technical (Architect)

  • DocumentForm 1 311224.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 310324.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 300624.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 300924.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 311224.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 - Mar 25.pdf · uploaded 1 May 2025Source
  • DocumentForm 1.pdf · uploaded 21 May 2026Source

Technical (Engineer)

  • DocumentForm 1 310324.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1 310324.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2 till 310324.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2 till 300624.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2 till 300924.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2 till 311224.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 1 May 2025Source
  • DocumentForm 2.pdf · uploaded 21 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 6, Hissa No 2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK FLAT, 1 RK FLAT, 1BHK120 units in all
Address
Survey No. 22, Hissa No 2 and 6PIN 421601
Village
Khardi (CT), Shahapur taluka
Land area for this project
4,470 sq m (48,115 sq ft)
Permissible built-up area
3,930 sq m (42,298 sq ft)
Sanctioned built-up area
3,930 sq m (42,298 sq ft)
Recreational open space
672 sq m (7,233 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

6Hissa No 2Survey No. 22

Land as published on MahaRERA's project page

Survey No. 22 , Hissa No 2 and 6

Boundaries

North
Survey No 231
South
Survey No 20
East
Survey No 22 and part
West
Survey no 232 and part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking120 units

26 of 120 units booked (22%), as the promoter reported to MahaRERA

1 BHK FLAT · 65 units1 RK FLAT · 35 units1BHK · 20 units
BuildingTypeCarpet areaUnitsBooked
Building E41 BHK FLAT29.45 sq m · 317 sq ft10
Building E41 BHK FLAT30.6 sq m · 329 sq ft43
Building E41 BHK FLAT31.15 sq m · 335 sq ft40
Building E41 BHK FLAT32 sq m · 344 sq ft169
Building E41 RK FLAT20.7 sq m · 223 sq ft30
Building E41 RK FLAT21.8 sq m · 235 sq ft121
Building F31 BHK FLAT29.3 sq m · 315 sq ft40
Building F31 BHK FLAT30.51 sq m · 328 sq ft160
Show all 14 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building F41BHK29.3 sq m · 315 sq ft40
Building F41BHK30.51 sq m · 328 sq ft1613
Building G11 BHK FLAT29.3 sq m · 315 sq ft100
Building G11 RK FLAT20.65 sq m · 222 sq ft100
Building G21 BHK FLAT29.3 sq m · 315 sq ft100
Building G21 RK FLAT20.65 sq m · 222 sq ft100

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSuyog Sanjay Pande Prop of Parth Consultant & Town Planners—
Chartered accountantGanpath Jain—
EngineerK B Consultants (Partner K K Patel)—
OtherLaxman Poojari—
OtherSanjay Sharma—

Source: MahaRERA project page. Contact details are not shown.