RERA projects in Atgaon
7 projects under 7 MahaRERA registrations, registered 2017–2019. 29% have a completion date extended beyond the one promised.
7RERA projects
7Registrations
3Completion still due4 past their completion date
63 monthsMedian extension beyond promised date29% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 1 |
| 2019 | 1 |
Projects in Atgaon
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Prem Narayan ResidencyAadinath Builders And Developers | P51700022796 | 30 Oct 2019 | 30 Dec 2026 | — | Not yet due | 0 |
| Jerry ApartmentRiel Infrastructure Pvt Ltd | P51700017219 | 23 Jul 2018 | 1 Jul 2027 | — | Not yet due | 0 |
| Aghav ResidenyAghav Developers | P51700012349 | 1 Sep 2017 | 1 Jul 2023 | 30 Jul 2027 | Extended 48 mo | 0 |
| Atulya Shubh VastuAtulya Township Buildcom Pvt Ltd | P51700011737 | 31 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Sanghvi Parsssva CitySanghvi Premises Private Limited | P51700009886 | 22 Aug 2017 | 7 Mar 2025 | — | Promised date passed | 0 |
| Sanghvis Shri Parrsssva City 15-16Sanghvi Premises Private Limited | P51700007140 | 17 Aug 2017 | 31 Dec 2019 | 30 Jun 2026 | Extended 78 mo | 1 |
| Prem Narayan ResidencyAadinath builders & developers | P51700005002 | 9 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
Other localities in Shahapur
- Shahapur (Ct)35 projects
- Washind (Ct)31 projects
- Asangaon (Ct)19 projects
- Cherpoli16 projects
- Kalambhe10 projects
- Khativali10 projects
- Gotheghar (Ct)4 projects
- Sarmal4 projects
- Dalkhan3 projects
- Khardi (Ct)3 projects
- Borsheti Bk2 projects
- Kalamgaon2 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Sanghvi Premises Private Limited2 projects
- Aadinath Builders And Developers1 project
- Aadinath builders & developers1 project
- Aghav Developers1 project
- Atulya Township Buildcom Pvt Ltd1 project
- Riel Infrastructure Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology