Sanghvi Parsssva City

Certificate Signed

Atgaon, Thane 421601 |Promoter: Sanghvi Premises Private Limited

22 Aug 2017Registered with MahaRERA
7 Mar 2025Promised completion
2Buildings
166Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
—166 units in all
Address
23/1A 23/1B 23/2 23/3 24, maharashtra, AtgaonPIN 421601
Designated bank account
85
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.50843, 73.32757
Sanghvi Parsssva City is at latitude 19.50843, longitude 73.32757.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 7 Mar 2025

The latest completion date on record passed 1 year and 7 months ago.

Registered
22 Aug 2017
Promised
7 Mar 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000988622 Aug 20177 Mar 20257 Mar 2025Sanghvi Premises Private LimitedProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building 138102
Building 14864

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

166 units registered

— · 166 units
BuildingTypeCarpet areaUnits
Building 13——102
Building 14——64

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 60 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan.pdf · uploaded 29 Jul 2017Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BFORM B.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BForm - B.pdf · uploaded 9 May 2025Source

Migrated

  • 1 PAN Cardpan.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 29 Jul 2017Source
  • 1 Details of encumbrancesIndex-II.pdf · uploaded 29 Jul 2017Source
Show all 61 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)NA Order (IOD).pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)Sanghvi Golden City Plan.pdf · uploaded 29 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 29 Jul 2017Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1 Architect Certificate.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 Engineer.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)Form-3 SPB 13-14.pdf · uploaded 29 Jul 2017Source
  • 1 Proforma of Allotment letterALLOTMENT AND AGREEMENT FOR SALE-SANGHVI'S SHRI PARRSSSVA -PDF.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 5)golden city form 5- Bldg 13-14.pdf · uploaded 24 May 2019Source
  • 1 Disclosure of sold/ booked inventorySanghvi Parsssva City (Sold -Unsold Inventory)13-14 (1).pdf · uploaded 18 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Bldg 13, 14 Form 2A FY2019.pdf · uploaded 20 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Bldg 13, 14 Form 2A FY2020.pdf · uploaded 20 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Bldg 13, 14 Form 2A FY2021.pdf · uploaded 20 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Bldg 13, 14 Form 2A FY2022.pdf · uploaded 20 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Bldg 13,14 Form 5 2019.pdf · uploaded 24 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Bldg 13,14 Form 5 2020.pdf · uploaded 24 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Bldg 13,14 Form 5 2021.pdf · uploaded 24 Apr 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Bldg 13,14 Form 5 2022.pdf · uploaded 24 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration of Legal Encumberance.pdf · uploaded 5 May 2023Source
  • 1 b Details of encumbrances concerned to LegalDeclaration of Legal Encumberance.pdf · uploaded 5 May 2023Source
  • 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 5 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of Bank Account.pdf · uploaded 5 May 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Certificate ( New ).pdf · uploaded 5 Jun 2023Source
  • 1 Certificates of CA (Form 3)form 3.pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsSanghvi Parsssva City (Sold -Unsold Inventory)13-14.pdf · uploaded 19 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Bldg 13, 14 Form 2A FY2023.pdf · uploaded 19 Oct 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1.pdf · uploaded 4 Feb 2025Source
  • 1 Proforma of Agreement for saleAgreement for Sale Sanghvi Parsssva City.pdf · uploaded 20 Mar 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 8 May 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Copy and Architect Certificate.pdf · uploaded 8 May 2025Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation report for allotment letter.pdf · uploaded 8 May 2025Source
  • 1 Deviation Report with respect to model copy of AgreementNo deviation report for agreement for Sale.pdf · uploaded 8 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Bldg 13 14 Form 2A.pdf · uploaded 8 May 2025Source
  • 1 Declaration in FORM BForm - B.pdf · uploaded 9 May 2025Source
  • Occupational CertificateBUILDING NO 13 OC.pdf · uploaded 17 Sep 2025Source
  • Occupational CertificateBUILDING NO 14 OC.pdf · uploaded 17 Sep 2025Source
  • Occupational CertificateBUILDING NO 14 OC PLAN (1 of 5).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 14 OC PLAN (2 of 5).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 14 OC PLAN (3 of 5).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 14 OC PLAN (4 of 5).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 14 OC PLAN (5 of 5).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (1 of 6).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (2 of 6).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (3 of 6).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (4 of 6).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (5 of 6).pdf · uploaded 16 Oct 2025Source
  • Occupational CertificateBUILDING NO 13 OC PLAN (6 of 6).pdf · uploaded 16 Oct 2025Source

Technical

  • DocumentNA Order (IOD).pdf · uploaded 29 Jul 2017Source
  • DocumentSanghvi Golden City Plan.pdf · uploaded 29 Jul 2017Source

Technical (Architect)

  • DocumentForm-1 Architect Certificate.pdf · uploaded 29 Jul 2017Source
  • DocumentForm-1.pdf · uploaded 4 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 8 May 2025Source

Technical (Engineer)

  • DocumentForm 2 Engineer Certificate ( New ).pdf · uploaded 5 Jun 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Atgaon, Shahapur taluka

Survey, CTS, gat or plot numbers

23/1A 23/1B 23/2 23/3 24

Boundaries

North
S no 21 2
South
S no 28
East
Nh3
West
Railway line

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahesh Jagtap & Associates—
EngineerE Struct Consultancy P Ltd—
OtherSanjay Chaturvedi Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology