RERA projects in Borsheti Bk
2 projects under 3 MahaRERA registrations, registered 2017–2019. None has an extended completion date on record.
Locality
2RERA projects
3Registrationssome projects hold several
1Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 1 |
Projects in Borsheti Bk
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Tulip N1 N2 N3 O1Royale Urbanspace | P51700019737 | 5 Mar 2019 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| TulipRoyale Urbanspace | P51700011791, P51700011815 | 31 Aug 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
Other localities in Shahapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Royale Urbanspace2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology