Skip to content
Residential / Group Housing · 1 building · 16 unitsRERA P51700024611

Abdullah Arcade

Deedo IDDP-THN-CN7G

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Bhiwandi (M Corp.), Thane 421302 · by Shahnawaz Farooque Ahmed Momin

Delivery4 yrs 11 mo past duePromised Dec 2021 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed

  • This projectRegistered 24 Feb 2020, completion promised 30 Dec 2021, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700024611
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002461124 Feb 202030 Dec 202130 Dec 2021Shahnawaz Farooque Ahmed MominProject page
Documents19

1 document held by Deedo, 18 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Shahnawaz_compressed.pdf · uploaded 10 Feb 2020Source
  • PAN CardPAN Danish.pdf · uploaded 13 Feb 2020Source

Legal

  • Declaration Form BForm B for RERA.pdf · uploaded 10 Feb 2020Source
  • Legal Title reportTitle Search_Multiplus.pdf · uploaded 19 Feb 2020Source

Migrated

  • 1 PAN CardPAN Shahnawaz_compressed.pdf · uploaded 10 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentPermission Letter.PDF · uploaded 10 Feb 2020Source
  • 1 Declaration in FORM BForm B for RERA.pdf · uploaded 10 Feb 2020Source
Show all 19 documentsShow fewer documents

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (Architect Certificate).pdf · uploaded 10 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 10 Feb 2020Source
  • 1 Proforma of Allotment letterAllotment Agreement.pdf · uploaded 10 Feb 2020Source
  • 2 PAN CardPAN Danish.pdf · uploaded 13 Feb 2020Source
  • 1 Details of encumbrancesDetails of encumbrance.pdf · uploaded 13 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentPermission Letter.PDF · uploaded 13 Feb 2020Source
  • 1 Copy of the legal title reportTitle Search_Multiplus.pdf · uploaded 19 Feb 2020Source
  • 1 Copy of Layout Approval (in case of layout)Approved Plan_compressed.pdf · uploaded 19 Feb 2020Source

Technical

  • DocumentPermission Letter.PDF · uploaded 10 Feb 2020Source
  • DocumentApproved Plan_compressed.pdf · uploaded 19 Feb 2020Source

Technical (Architect)

  • DocumentForm 1 (Architect Certificate).pdf · uploaded 10 Feb 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2294, 2295A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Office space, Shop16 units in all
Address
CTS NO. 2293, 2294, 2295A, 2296A, 9 meter road towards Mandai, Prabhu AlleyPIN 421302
Village
Bhiwandi (M Corp.), Bhiwandi taluka
Land area for this project
188 sq m (2,025 sq ft)
Permissible built-up area
563 sq m (6,055 sq ft)
Sanctioned built-up area
563 sq m (6,055 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

22942295A2296ACTS NO. 2293

Land as published on MahaRERA's project page

CTS NO. 2293, 2294, 2295A, 2296A

Boundaries

North
9 Meter Road
South
Cts No 2297
East
Municipal School
West
Cts No 2292

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

0 of 16 units booked (0%), as the promoter reported to MahaRERA

1BHK · 8 unitsOffice space · 5 unitsShop · 3 units
TypeCarpet areaUnitsBooked
1BHK35.66 sq m · 384 sq ft50
1BHK36.42 sq m · 392 sq ft30
Office space17.33 sq m · 187 sq ft20
Office space19.28 sq m · 208 sq ft10
Office space27.48 sq m · 296 sq ft20
Shop36.44 sq m · 392 sq ft10
Shop40.15 sq m · 432 sq ft10
Shop43.63 sq m · 470 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Bhiwandi (M Corp.)

All 153 projects in Bhiwandi (M Corp.) · Compare Abdullah Arcade with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology