Sai Orchid Phase 1

Certificate Signed

Dawadi, Thane 421201 |Promoter: gupta builders and developers

Residential / Group HousingRERAP51700004806
9 Aug 2017Registered with MahaRERA
30 Jun 2021Promised completion
30 Jun 2024Revised completionPushed back 3 years
8Buildings
239Units registered141 booked (59%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
8
Unit types
1 bhk, 1 RK, 1bhk, 1RK, 2bhk, 2 bhk239 units in all
Address
120/7A, Kalyan - Shil Phata Road, Dombivali EastPIN 421201
Designated bank account
89
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.19678, 73.11213
Sai Orchid Phase 1 is at latitude 19.19678, longitude 73.11213.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years

The latest completion date on record passed 2 years and 4 months ago.

Registered
9 Aug 2017
Promised
30 Jun 2021
Revised
30 Jun 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000048069 Aug 201730 Jun 202130 Jun 2024gupta builders and developersProject page

8 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A11030
A21129
B11230
B21231
C11028
C21035
D1928
D2928

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

141 of 239 units booked (59%), as the promoter reported to MahaRERA

1 bhk · 114 units1 RK · 3 units1bhk · 2 units1RK · 1 unit2bhk · 42 units2 bhk · 77 units
BuildingTypeCarpet areaUnitsBooked
A11 bhk24.88 sq m · 268 sq ft159
A11 bhk25.4 sq m · 273 sq ft11
A11 bhk25.46 sq m · 274 sq ft1313
A11 RK15.38 sq m · 166 sq ft10
A21 bhk24.88 sq m · 268 sq ft1514
A21 bhk25.46 sq m · 274 sq ft131
A21 RK15.38 sq m · 166 sq ft10
B11 bhk24.88 sq m · 268 sq ft158
Show all 22 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B11 bhk25.41 sq m · 274 sq ft1211
B11bhk25.14 sq m · 271 sq ft22
B11RK15.33 sq m · 165 sq ft10
B21 bhk24.88 sq m · 268 sq ft1611
B21 bhk25.41 sq m · 274 sq ft1414
B21 RK15.33 sq m · 165 sq ft10
C12bhk37.11 sq m · 399 sq ft1414
C12bhk42.11 sq m · 453 sq ft1410
C22 bhk42.11 sq m · 453 sq ft217
C22bhk37.11 sq m · 399 sq ft144
D12 bhk37.11 sq m · 399 sq ft143
D12 bhk42.11 sq m · 453 sq ft145
D22 bhk37.11 sq m · 399 sq ft146
D22 bhk42.11 sq m · 453 sq ft148

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardGupta_Builders_and_Developers_pan_card.pdf · uploaded 28 Jul 2017Source

Legal

  • Other712 extracts.pdf · uploaded 28 Jul 2017Source
  • Otheramentities.pdf · uploaded 28 Jul 2017Source
  • OtherNA order dt 2013.pdf · uploaded 28 Jul 2017Source
  • Legal Title reportTitle Certificate revised.pdf · uploaded 28 Jul 2017Source
  • Declaration Form BAffidavit cum declaration.pdf · uploaded 28 Jul 2017Source
Show all 90 documentsShow fewer documents

Legal

  • OtherStop work letter.pdf · uploaded 31 Mar 2018Source
  • Otherstatus report.pdf · uploaded 6 Jun 2022Source

Migrated

  • 1 PAN CardGupta_Builders_and_Developers_pan_card.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of the legal title reportTitle Certificate revised.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesEncumbrance certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)IMG_0834.pdf · uploaded 28 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)Proposed site layout.pdf · uploaded 28 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)declaration.pdf · uploaded 28 Jul 2017Source
  • 4 Copy of Layout Approval (in case of layout)Scan436.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)Scan1.pdf · uploaded 28 Jul 2017Source
  • 2 Building Plan Approval (IOD)Scan2.pdf · uploaded 28 Jul 2017Source
  • 3 Building Plan Approval (IOD)Scan3.pdf · uploaded 28 Jul 2017Source
  • 4 Building Plan Approval (IOD)Scan4.pdf · uploaded 28 Jul 2017Source
  • 5 Building Plan Approval (IOD)Scan5.pdf · uploaded 28 Jul 2017Source
  • 6 Building Plan Approval (IOD)Scan6 (1).pdf · uploaded 28 Jul 2017Source
  • 7 Building Plan Approval (IOD)Scan7.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentSai_Orchid_CC.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BAffidavit cum declaration.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)certificate (2).pdf · uploaded 28 Jul 2017Source
  • 2 Certificates of CA (Form 3)sheet.pdf · uploaded 28 Jul 2017Source
  • 3 Certificates of CA (Form 3)unsold_inventory.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterSai Orchid_28_07_2017.pdf · uploaded 28 Jul 2017Source
  • 2 Proforma of Allotment letterUndertaking.pdf · uploaded 28 Jul 2017Source
  • 1 Otheramentities.pdf · uploaded 28 Jul 2017Source
  • 2 OtherNA order dt 2013.pdf · uploaded 28 Jul 2017Source
  • 3 Other712 extracts.pdf · uploaded 28 Jul 2017Source
  • 2 Details of encumbrancesEncumberance.pdf · uploaded 7 Nov 2017Source
  • 3 Details of encumbrancesEncumberance Certificate dt 07_11_2017.pdf · uploaded 7 Nov 2017Source
  • 3 Proforma of Allotment letterDRAFT SALE AGREEMENT _Dt_07_11_2017.pdf · uploaded 7 Nov 2017Source
  • 4 Certificates of CA (Form 3)CA certificatee-1-3.pdf · uploaded 31 Mar 2018Source
  • 5 Certificates of CA (Form 3)CA certificatee-4-12 (1).pdf · uploaded 31 Mar 2018Source
  • 4 OtherStop work letter.pdf · uploaded 31 Mar 2018Source
  • 4 Details of encumbrancesEncumbrance certificate (1).pdf · uploaded 27 Aug 2018Source
  • 4 Proforma of Allotment letterRevised-RERA DRAFT AGREEMENT SAI ORCHID.pdf · uploaded 28 Aug 2018Source
  • 5 Details of encumbrancesEncumbrance05122018.pdf · uploaded 5 Dec 2018Source
  • 1 Certificates of CA (Form 5)Annual report march 2018 from CA Nair.pdf · uploaded 5 Dec 2018Source
  • 6 Details of encumbrancesEncumbrance30072019.pdf · uploaded 30 Jul 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer_Certificate_Dec_2019.pdf · uploaded 22 Jan 2020Source
  • 6 Certificates of CA (Form 3)Form_3_Dec_2019.pdf · uploaded 22 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Sai Orchid Form-2A 2020-Q3_Quality Assurance.pdf · uploaded 28 Apr 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sai Orchid Form-2A 2020-Q3_Quality Assurance.pdf · uploaded 28 Apr 2021Source
  • 7 Certificates of CA (Form 3)Sai Orchid CA Certificate Form-3 (1)-compressed.pdf · uploaded 28 Apr 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM_5 (2).pdf · uploaded 28 Apr 2021Source
  • 1 Disclosure of sold/ booked inventorySold_unSoldInventory.pdf · uploaded 25 May 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Audit clarification.pdf · uploaded 12 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form-5 FY 2018-19.pdf · uploaded 15 Jun 2021Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sai Orchid Form-1 21-22 Q1.pdf · uploaded 16 Aug 2021Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sai Orchid Form-2 Engineer Certificate 21-22 Q2.pdf · uploaded 16 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sai Orchid Form-2 Engineer Certificate 21-22 Q2.pdf · uploaded 16 Aug 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sai Orchid Phase-1 Form-2A 2021-22 Q1.pdf · uploaded 16 Aug 2021Source
  • 2 Disclosure of sold/ booked inventorySold_Unsold Inventory_QTR1 update on MAHARERA_compressed.pdf · uploaded 17 Aug 2021Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM_5 (4).pdf · uploaded 18 Aug 2021Source
  • 8 Certificates of CA (Form 3)Form-3 Sai Orchid.pdf · uploaded 25 Aug 2021Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certifiate_as per Maharera_compressed.pdf · uploaded 28 Dec 2021Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 4 D1.pdf · uploaded 28 Dec 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)sai orchid 2A.pdf · uploaded 28 Dec 2021Source
  • 3 Disclosure of sold/ booked inventorydisclosure.pdf · uploaded 28 Dec 2021Source
  • 9 Certificates of CA (Form 3)form 3 (1)_compressed.pdf · uploaded 6 Jan 2022Source
  • 4 Disclosure of sold/ booked inventorySold_unsold Inventory_Mar22_Maharera_compressed.pdf · uploaded 18 Apr 2022Source
  • 2 Certificates of CA (Form 5)Form 5_FY2021-22 (1).pdf · uploaded 26 May 2022Source
  • 5 Otherstatus report.pdf · uploaded 6 Jun 2022Source
  • 5 Disclosure of sold/ booked inventorySold unsold_compressed (1).pdf · uploaded 21 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_FY2021-22 (2).pdf · uploaded 28 Jan 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form1_RERA_FY 22-23_compressed.pdf · uploaded 1 Jun 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sai Orchid Form-2 Q3 2022-23.pdf · uploaded 1 Jun 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sai Orchid Form-2 Q1 2022-23.pdf · uploaded 1 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Sai Orchid Form-2A 22-23.pdf · uploaded 1 Jun 2024Source

Technical

  • DocumentProposed site layout.pdf · uploaded 28 Jul 2017Source
  • DocumentIMG_0834.pdf · uploaded 28 Jul 2017Source
  • DocumentScan7.pdf · uploaded 28 Jul 2017Source
  • DocumentScan5.pdf · uploaded 28 Jul 2017Source
  • DocumentScan6 (1).pdf · uploaded 28 Jul 2017Source
  • DocumentScan3.pdf · uploaded 28 Jul 2017Source
  • DocumentScan4.pdf · uploaded 28 Jul 2017Source
  • DocumentScan2.pdf · uploaded 28 Jul 2017Source
  • DocumentScan1.pdf · uploaded 28 Jul 2017Source
  • Documentdeclaration.pdf · uploaded 28 Jul 2017Source
  • DocumentScan436.pdf · uploaded 28 Jul 2017Source

Technical (Architect)

  • DocumentForm1_RERA_FY 22-23_compressed.pdf · uploaded 1 Jun 2024Source

Technical (Engineer)

  • DocumentSai Orchid Form-2 Q1 2022-23.pdf · uploaded 1 Jun 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dawadi, Kalyan taluka

Survey, CTS, gat or plot numbers

120/7A

Boundaries

North
Sai orchid Phase 2
South
6m Wide Village Road
East
120-7b
West
120-6

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDilip Deshmukh and Associates Architect and Environment Planner—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology