RERA projects in Dawadi
16 projects under 21 MahaRERA registrations, registered 2017–2026. 10% have a completion date extended beyond the one promised.
Locality
16RERA projects
21Registrationssome projects hold several
10Completion still due11 past their completion date
27 monthsMedian extension beyond promised date10% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 1 |
| 2019 | 3 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 4 |
| 2024 | 2 |
| 2025 | 1 |
| 2026 | 4 |
Projects in Dawadi
16 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sinhagad by Bhagwati Haware – Wing - BBhagwati Haware Properties Supertech | PR1331012600627 | 2 Jun 2026 | 31 Dec 2034 | — | Not yet due | 0 |
| Raigad by Bhagwati Haware – Wing - ABhagwati Haware Properties Supertech | PR1331012600607 | 1 Jun 2026 | 31 Dec 2034 | — | Not yet due | 0 |
| Pratapgad by Bhagwati Haware – Wing - CBhagwati Haware Properties Supertech | PR1331012600469 | 19 May 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| Rajgad by Bhagwati Haware – Wing - DBhagwati Haware Properties Supertech | PR1331012502333 | 11 Feb 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| Prakruti AanandamAvishkarskyline | PM1330002500837 | 18 Sep 2025 | 31 Jul 2030 | — | Not yet due | 0 |
| Regency Anantam Nxt Phase IRegency Nirman Ltd | P51700055848 | 23 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Vidhi ImpressionAshtavinayak Construction | P51700055396 | 22 Mar 2024 | 30 Dec 2028 | — | Not yet due | 0 |
| Regency SapphireRegency Nirman Ltd | P51700053596 | 10 Nov 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sohum HeightsM/S Sohum Enterprises | P51700051918 | 13 Jul 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Kapleshwara ResidencyKapleshwara Homes LLP | P51700049543 | 15 Feb 2023 | 31 Dec 2029 | — | Not yet due | 0 |
| Vidhi PremLotus Construction | P51700030057 | 29 Jul 2021 | 30 Dec 2023 | — | Promised date passed | 0 |
| Dream HomeUnity Builders And Developers | P51700019674 | 20 Feb 2019 | 31 Dec 2026 | — | Not yet due | 0 |
| Regency AnantamRegency Nirman Ltd | P51700017874, P51700020186, P51700020194 +3 | 24 Sep 2018 | 30 Mar 2024 | — | Promised date passed | 0 |
| Vidhi RatnaLotus Construction | P51700014528 | 8 Dec 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Pandurang smrutiLote Constructions | P51700013381 | 4 Oct 2017 | 5 Jul 2019 | 30 Dec 2020 | Extended 17 mo | 0 |
| Sai Orchid Phase 1gupta builders and developers | P51700004806 | 9 Aug 2017 | 30 Jun 2021 | 30 Jun 2024 | Extended 36 mo | 0 |
Other localities in Kalyan
- Dombivli405 projects
- Kalyandombivali (M Corp.)206 projects
- Kalyan137 projects
- Chikanghar107 projects
- Titwala89 projects
- Kalyan-Dombivali (M Corp.)85 projects
- Khoni71 projects
- Katemanevali55 projects
- Manda52 projects
- Tisgaon48 projects
- Gandhare43 projects
- Adharwadi24 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Bhagwati Haware Properties Supertech4 projects
- Regency Nirman Ltd3 projects
- Lotus Construction2 projects
- Ashtavinayak Construction1 project
- Avishkarskyline1 project
- gupta builders and developers1 project
- Kapleshwara Homes LLP1 project
- Lote Constructions1 project
- M/S Sohum Enterprises1 project
- Unity Builders And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology