RERA projects in Dawadi

16 projects under 21 MahaRERA registrations, registered 2017–2026. 10% have a completion date extended beyond the one promised.

Locality
16RERA projects
21Registrationssome projects hold several
10Completion still due11 past their completion date
27 monthsMedian extension beyond promised date10% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20193
20200
20211
20222
20234
20242
20251
20264

Projects in Dawadi

16 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sinhagad by Bhagwati Haware – Wing - BBhagwati Haware Properties SupertechPR13310126006272 Jun 202631 Dec 2034—Not yet due0
Raigad by Bhagwati Haware – Wing - ABhagwati Haware Properties SupertechPR13310126006071 Jun 202631 Dec 2034—Not yet due0
Pratapgad by Bhagwati Haware – Wing - CBhagwati Haware Properties SupertechPR133101260046919 May 202631 Dec 2032—Not yet due0
Rajgad by Bhagwati Haware – Wing - DBhagwati Haware Properties SupertechPR133101250233311 Feb 202631 Dec 2032—Not yet due0
Prakruti AanandamAvishkarskylinePM133000250083718 Sep 202531 Jul 2030—Not yet due0
Regency Anantam Nxt Phase IRegency Nirman LtdP5170005584823 Apr 202431 Dec 2028—Not yet due0
Vidhi ImpressionAshtavinayak ConstructionP5170005539622 Mar 202430 Dec 2028—Not yet due0
Regency SapphireRegency Nirman LtdP5170005359610 Nov 202330 Jun 2026—Promised date passed0
Sohum HeightsM/S Sohum EnterprisesP5170005191813 Jul 202331 Dec 2026—Not yet due0
Kapleshwara ResidencyKapleshwara Homes LLPP5170004954315 Feb 202331 Dec 2029—Not yet due0
Vidhi PremLotus ConstructionP5170003005729 Jul 202130 Dec 2023—Promised date passed0
Dream HomeUnity Builders And DevelopersP5170001967420 Feb 201931 Dec 2026—Not yet due0
Regency AnantamRegency Nirman LtdP51700017874, P51700020186, P51700020194 +324 Sep 201830 Mar 2024—Promised date passed0
Vidhi RatnaLotus ConstructionP517000145288 Dec 201730 Dec 2021—Promised date passed0
Pandurang smrutiLote ConstructionsP517000133814 Oct 20175 Jul 201930 Dec 2020Extended 17 mo0
Sai Orchid Phase 1gupta builders and developersP517000048069 Aug 201730 Jun 202130 Jun 2024Extended 36 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhagwati Haware Properties Supertech4 projects
  2. Regency Nirman Ltd3 projects
  3. Lotus Construction2 projects
  4. Ashtavinayak Construction1 project
  5. Avishkarskyline1 project
  6. gupta builders and developers1 project
  7. Kapleshwara Homes LLP1 project
  8. Lote Constructions1 project
  9. M/S Sohum Enterprises1 project
  10. Unity Builders And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology