8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects17
Registrations23some projects hold several
Completion still due1211 past their date
Median extension4 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

23 MahaRERA registrations in Dawadi

4 not yet due8 extended, not yet due11 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Dawadi

17 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Regency Anantam Neo Phase IRegency Nirman LtdDue Dec 2028——
Sinhagad by Bhagwati Haware – Wing - BBhagwati Haware Properties SupertechDue Apr 2035, extended 4 mo——
Raigad by Bhagwati Haware – Wing - ABhagwati Haware Properties SupertechDue Apr 2035, extended 4 mo——
Pratapgad by Bhagwati Haware – Wing - CBhagwati Haware Properties SupertechDue Apr 2033, extended 4 mo——
Rajgad by Bhagwati Haware – Wing - DBhagwati Haware Properties SupertechDue Apr 2033, extended 4 mo——
Prakruti AanandamAvishkarskylineDue Nov 2030, extended 4 mo——
Regency Anantam NxtRegency Nirman LtdDue Dec 2029——
Vidhi ImpressionAshtavinayak ConstructionDue Apr 2029, extended 4 mo——
Regency SapphireRegency Nirman LtdCompleted—15%
Sohum HeightsSohum EnterprisesDue Dec 2026—7%
Kapleshwara ResidencyKapleshwara Homes LLPDue Apr 2030, extended 4 mo—49%
Vidhi PremLotus ConstructionCompleted——
Dream HomeUnity Builders And DevelopersDue Dec 2026—41%
Regency AnantamRegency Nirman LtdCompleted—75%
Vidhi RatnaLotus ConstructionCompleted——
Pandurang smrutiLote ConstructionsCompleted, extended 1 yr 5 mo——
Sai Orchid Phase 1gupta builders and developers5 yrs 5 mo late—59%
Dawadi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Bhagwati Haware Properties Supertech4 projects
  2. Regency Nirman Ltd3 projects
  3. Lotus Construction2 projects
  4. Regency Nirman Ltd2 projects
  5. Ashtavinayak Construction1 project
  6. Avishkarskyline1 project
  7. Gupta Builders And Developers1 project
  8. Kapleshwara Homes Llp1 project
  9. Lote Constructions1 project
  10. Sohum Enterprises1 project

Dawadi, in questions

How many projects in Dawadi run late?

8 in 10 MahaRERA registrations (19 of 23): their completion date was extended or has passed, data through 6 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Dawadi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology