Delayed projects in Thane

1,161 MahaRERA projects in Thane are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 24.

ProjectLocalityPromisedRevisedDelivery
Hira Panna ResidencyHaro Om Sai Builders And DevelopersBadlapur (M Cl)Dec 2019Dec 20206 yrs 11 mo late
Imperial Heights S1 S2Kamran Livestock & Real Estate Pvt LtdThane (M Corp.)Dec 2019Jun 20226 yrs 11 mo late
Jaya Shantaram HeightsGurudeep ConstructionKalyandombivali (M Corp.)Dec 2019Dec 20216 yrs 11 mo late
Kavya ResidencyKavya Mira RealtyThaneDec 2019Dec 20216 yrs 11 mo late
Khatri GrandeAashiyana Builders AnddevelopersBadlapur (M Cl)Dec 2019Dec 20196 yrs 11 mo late
Lifestyle City Kalyan CypressNirmal Lifestyle (Kalyan) Private LimitedVadavali Kh.Dec 2019Sep 20236 yrs 11 mo late
Marathon Nagari Nx Vitoria DMarathon Realty Pvt LtdBadlapur (M Cl)Dec 2019Dec 20216 yrs 11 mo late
Navjeevan Co-Op. Housing Society LtdAvishkar GroupKulgaonDec 2019Dec 20216 yrs 11 mo late
Om Shiv Samarth ChsShree Saibaba Constructions Private LimitedThane (M Corp.)Dec 2019Aug 20226 yrs 11 mo late
Om Siddhivinayak ResidencyOm Siddhivinayak EnterprisesMandaDec 2019Dec 20216 yrs 11 mo late
Om Yashlaxmi ApartmentOm DevelopersKalyanDec 2019Dec 20196 yrs 11 mo late
Pentagon EnclaveDamji Hari Infrastructure Pvt LtdAsangaon (Ct)Dec 2019Dec 20256 yrs 11 mo late
Red Rose Co-Operative Housing SocietyImtiyaz Mohammed Saeed AnsariThane (M Corp.)Dec 2019Dec 20196 yrs 11 mo late
Royce Paradise Phase IIRoyce DevelopersGandhareDec 2019Dec 20256 yrs 11 mo late
Sanghvis Shri Parrsssva City 15-16Sanghvi Premises Private LimitedAtgaonDec 2019Jun 20266 yrs 11 mo late
Satkar TowerPragati ConstructionsKatemanevaliDec 2019Dec 20246 yrs 11 mo late
Savitri ApartmentSuresh MoreNavi Mumbai (M Corp.)Dec 2019Dec 20216 yrs 11 mo late
Shree Shashwat Building No 19Shashwat DevelopersMirabhayandar (M Corp.)Dec 2019Dec 20216 yrs 11 mo late
Shubh AanganShubh EnterprisesBadlapur (M Cl)Dec 2019Dec 20196 yrs 11 mo late
Shubh AshishShubh BuildersBadlapur (M Cl)Dec 2019Dec 20196 yrs 11 mo late
Silver EstateNanda Kapildev SharmaDhavaleDec 2019Jun 20226 yrs 11 mo late
Shantiniketan Wing B5Anmol AssociatesBhoparDec 2019Dec 20216 yrs 11 mo late
UrbanvilleSai Krupa BuildersKalyandombivali (M Corp.)Dec 2019Dec 20196 yrs 11 mo late
Vedant VatikaVedant VentureBadlapur (M Cl)Dec 2019Dec 20196 yrs 11 mo late
Wing C-5 GajmukhM K Patil DevelopersBadlapur (M Cl)Dec 2019Dec 20226 yrs 11 mo late
WoodshireShree Ji EnterprisesAmbivali Tarf ChonDec 2019Dec 20256 yrs 11 mo late
SundaramPurab AssociatesBadlapur (M Cl)Jan 2020Jan 20206 yrs 10 mo late
ShivamGagan Developers & EngineersChikangharMar 2020Sep 20206 yrs 8 mo late
Silver EnclaveSilverline Building & Constructions LLPThane (M Corp.)Mar 2020Mar 20236 yrs 8 mo late
Palm PrismP J ConstructionShahadJul 2020Dec 20226 yrs 4 mo late
Eknath TowerOmkar EnterprisesKalyan-Dombivali (M Corp.)Sep 2020Mar 20226 yrs 2 mo late
GautamSahara BuildconKhadakpadaSep 2020Sep 20206 yrs 2 mo late
Laabh Enclave- Phase 2Vaishnavi Housing Realty LLPThane (M Corp.)Sep 2020Mar 20236 yrs 2 mo late
Magnus MaryamShafi Abdul Kadar SyedThane (M Corp.)Sep 2020Mar 20226 yrs 2 mo late
Manas Height B WingJ D Realty Pvt.ltd.Savaroli Bk.Sep 2020Sep 20206 yrs 2 mo late
Sector VI/E-6Shantistar BuildersMirabhayandar (M Corp.)Sep 2020Dec 20246 yrs 2 mo late
iMPERIAL HEIGHTSSkheights Pvt LtdThaneSep 2020Mar 20226 yrs 2 mo late
Parshwa HillJrv Construction CoAmbarnath(M Cl)Oct 2020Oct 20206 yrs 1 mo late
Sai Vision ResidencyAvision RealtorsAsangaon (Ct)Oct 2020Dec 20246 yrs 1 mo late
Evergreen ApartmentsKaiyomerz Cowas PaliaDalkhanNov 2020Nov 20206 yrs late
Ryyan ViewHidayat KhanThane (M Corp.)Nov 2020Nov 20206 yrs late
Swami ResidencySatish Bapu GiriShahapurNov 2020Nov 20206 yrs late
Royal CastleShreenath DevelopersAmbarnath(M Cl)Nov 2020Mar 20246 yrs late
Vedant EnclaveSara EnterprisesBadlapur (M Cl)Nov 2020Nov 20206 yrs late
Advaita PrestigeAdvaita DevelopersNavaliDec 2020Aug 20255 yrs 11 mo late
Lambodara PalaceVighnaharta EnterprisesBadlapurDec 2020Dec 20205 yrs 11 mo late
Omkar HeightsGanga Estate DevelopersBhoparDec 2020Dec 20245 yrs 11 mo late
Poonam HillsAshapura DeveloperKharbav (Ct)Dec 2020Jun 20265 yrs 11 mo late
Ravindranath Tagore NiketanSai City DevelopersBadlapur (M Cl)Dec 2020Dec 20205 yrs 11 mo late
Ramkrishna NiketanYash Govinda Build Infra LLPNaupadaDec 2020Dec 20205 yrs 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology