Sundaram
Deedo IDDP-THN-JJS4Its promised completion date, Jan 2020, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.
Badlapur (M Cl), Thane 421503 · by Purab Associates
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jan 2020, has passed and MahaRERA does not show it completed
- This projectRegistered 10 May 2018, completion promised 31 Jan 2020, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700016386
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700016386 | 10 May 2018 | 31 Jan 2020 | 31 Jan 2020 | M/S. Purab Associates | Project page |
Documents35
1 document held by Deedo, 34 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD.pdf · uploaded 23 Apr 2018Source
Legal
Show all 35 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BAFFIDAVIT CUM DECLARATION.pdf · uploaded 23 Apr 2018Source
- 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 3 May 2018Source
- 1 Building Plan Approval (IOD)PLAN sundaram.pdf · uploaded 3 May 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate 1.pdf · uploaded 3 May 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg certificate.pdf · uploaded 3 May 2018Source
- 1 Certificates of CA (Form 3)ca certificate sign.pdf · uploaded 5 May 2018Source
- 1 OtherBLOCK PLAN SUNDARAM.pdf · uploaded 5 May 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5)Purab Associates.pdf · uploaded 30 Sep 2019Source
- 2 Annual Audit Report of Statutory CA (Form 5)Purab Associates.pdf · uploaded 30 Sep 2019Source
- 2 Commencement Certificates / NA Order for plotted development2652_compressed.pdf · uploaded 14 Apr 2021Source
- 3 Annual Audit Report of Statutory CA (Form 5)Form 5 FY 19-20.pdf · uploaded 29 Nov 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form5 Signed.pdf · uploaded 18 Jun 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 7 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 7 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 7 Apr 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 7 Apr 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 7 Apr 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 7 Apr 2023Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 7 Apr 2023Source
- 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 7 Apr 2023Source
- 4 Certificates of CA (Form 3)Form 3.pdf · uploaded 7 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 7 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 7 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 7 Apr 2023Source
Technical
- DocumentPLAN sundaram.pdf · uploaded 3 May 2018Source
Technical (Architect)
- Documentform 1.pdf · uploaded 7 Apr 2023Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 7 Apr 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PART PORTION OF S NO 45 H NO 2PT PLOT NO 1 2 3, PART PORTION OF S NO 45 H NO 2 PT PLOT NO 4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Address
- Part Portion Of S No 45 H No 2pt Plot No 1 2 3 And Part Portion Of S No 45 H No 2 Pt Plot No 4, Badlapur Ambernath MIDC Road, Opposite Hp Petrol PumpPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.17322, 73.22667
- Land area for this project
- 487 sq m (5,240 sq ft)
- Permissible built-up area
- 914 sq m (9,842 sq ft)
- Sanctioned built-up area
- 914 sq m (9,842 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PART PORTION OF S NO 45 H NO 2PT PLOT NO 1 2 3 AND PART PORTION OF S NO 45 H NO 2 PT PLOT NO 4
Boundaries
- North
- S No 46 And Existing Building Shivam
- South
- S No 41
- East
- S No 41
- West
- 30 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Satish Dattatray Oak | — |
| Engineer | S V Patel | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Badlapur (M Cl)
- Gokul HeightsRERA PR1330002601884
- Chandrama S ChslRERA PM1330002601355
- Mery Villa ChslRERA P51700081124
- Gurukrupa Builders And DevelopersRERA PM1330002600336
- Shrey SwapnaRERA PM1330002502637
- Swanand Niwas Co Op Housing Society LtdRERA PM1330002502083
- Saurabh ChslRERA PM1330002501948
- Ranimaa Devi ChsRERA PR1330002501812
All 432 projects in Badlapur (M Cl) · Compare Sundaram with another project