Skip to content
Residential / Group Housing · 2 buildings · 48 unitsRERA P51700016929

Ved Residency

Deedo IDDP-THN-4TPR

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 85% of its units are booked.

Titwala, Thane 421605 · by Om Corporatin

Delivery4 yrs 11 mo past duePromised Dec 2021 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales85% booked41 of 48 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed

  • This projectRegistered 22 Jun 2018, completion promised 30 Dec 2021, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700016929
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001692922 Jun 201830 Dec 202130 Dec 2021Om CorporatinProject page
Documents26

1 document held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardOM CORPORATION PAN CARD.pdf · uploaded 20 Jun 2018Source

Legal

  • Declaration Form BFROM B-compressed.pdf · uploaded 20 Jun 2018Source
  • Legal Title reportTITLE-compressed.pdf · uploaded 20 Jun 2018Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)Tiwala CC DWG PDF.pdf · uploaded 18 Jun 2018Source
  • 1 PAN CardOM CORPORATION PAN CARD.pdf · uploaded 20 Jun 2018Source
  • 1 Copy of the legal title reportTITLE-compressed.pdf · uploaded 20 Jun 2018Source
  • 1 Details of encumbrancesEncumbranes.pdf · uploaded 20 Jun 2018Source
Show all 26 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)IOD compressed.pdf · uploaded 20 Jun 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCCcompressed.pdf · uploaded 20 Jun 2018Source
  • 1 Declaration in FORM BFROM B-compressed.pdf · uploaded 20 Jun 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RCC FORM 2-compressed.pdf · uploaded 20 Jun 2018Source
  • 1 Certificates of CA (Form 3)CA FORM 3-compressed.pdf · uploaded 20 Jun 2018Source
  • 1 Proforma of Allotment letterOm corporation draft.pdf · uploaded 20 Jun 2018Source
  • 2 Copy of Layout Approval (in case of layout)OC NEW PLAN.pdf · uploaded 9 Aug 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentNEW CC.pdf · uploaded 9 Aug 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form5 O C 18-19.pdf · uploaded 13 Nov 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)VED2A.pdf · uploaded 31 Dec 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)OC A19-20.pdf · uploaded 31 Dec 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Ved Resi Soc certificate .pdf · uploaded 1 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FY 2021.pdf · uploaded 10 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FY 2122.pdf · uploaded 10 Mar 2023Source

Technical

  • DocumentTiwala CC DWG PDF.pdf · uploaded 18 Jun 2018Source
  • DocumentIOD compressed.pdf · uploaded 20 Jun 2018Source
  • DocumentOC NEW PLAN.pdf · uploaded 9 Aug 2018Source

Technical (Engineer)

  • DocumentRCC FORM 2-compressed.pdf · uploaded 20 Jun 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel NEW H. NO. 3/B/1, OLD H. NO. 3/2/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK 002, 1BHK 003, 1BHK 004, 1BHK 103.303.503.703, 1BHK 104.304.504.704, 1BHK 201.401.601, 1BHK 202.402.602, 1BHK 203.403.603, 1BHK 204.404.604, 1BHKT101.301.501.701, 1BHKT 102.302.702, 1RK 001, 1RK 502, 1BHKT 101.301.701, 1BHKT 501, 2BHK 002, 2BHK 202.402.602, 2BHKT102.302.502.70248 units in all
Address
S.no. 229, New H. No. 3/B/1, Old H. No. 3/2/1, 18 M Wide D P Road, Near Reshmai School, Narayan NagarPIN 421605
Village
Titwala, Kalyan taluka
Land area for this project
1,120 sq m (12,056 sq ft)
Permissible built-up area
2,012 sq m (21,662 sq ft)
Sanctioned built-up area
1,687 sq m (18,164 sq ft)
Designated bank account
213
Developed in phases
Yes

Survey, CTS, gat or plot numbers

NEW H. NO. 3/B/1OLD H. NO. 3/2/1S.NO. 229

Land as published on MahaRERA's project page

S.NO. 229, NEW H. NO. 3/B/1, OLD H. NO. 3/2/1

Boundaries

North
P No 34 35 H No 3 Pt S No 229
South
S No 191
East
S No 229 H No 7
West
18 M Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking48 units

41 of 48 units booked (85%), as the promoter reported to MahaRERA

1BHK 002 · 1 unit1BHK 003 · 1 unit1BHK 004 · 1 unit1BHK 103.303.503.703 · 4 units1BHK 104.304.504.704 · 4 units1BHK 201.401.601 · 6 units1BHK 202.402.602 · 3 units1BHK 203.403.603 · 3 units1BHK 204.404.604 · 3 units1BHKT101.301.501.701 · 4 units1BHKT 102.302.702 · 3 units1RK 001 · 2 units1RK 502 · 1 unit1BHKT 101.301.701 · 3 units1BHKT 501 · 1 unit2BHK 002 · 1 unit2BHK 202.402.602 · 3 units2BHKT102.302.502.702 · 4 units
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK 00235.28 sq m · 380 sq ft11
A Wing1BHK 00333.37 sq m · 359 sq ft11
A Wing1BHK 00431.44 sq m · 338 sq ft11
A Wing1BHK 103.303.503.70332.5 sq m · 350 sq ft44
A Wing1BHK 104.304.504.70432.28 sq m · 347 sq ft44
A Wing1BHK 201.401.60134.81 sq m · 375 sq ft33
A Wing1BHK 202.402.60235.19 sq m · 379 sq ft33
A Wing1BHK 203.403.60332.5 sq m · 350 sq ft33
Show all 20 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK 204.404.60432.28 sq m · 347 sq ft33
A Wing1BHKT101.301.501.70135.28 sq m · 380 sq ft43
A Wing1BHKT 102.302.70235.84 sq m · 386 sq ft33
A Wing1RK 00125.75 sq m · 277 sq ft10
A Wing1RK 50226.7 sq m · 287 sq ft11
B Wing1BHK 201.401.60137.81 sq m · 407 sq ft33
B Wing1BHKT 101.301.70138.47 sq m · 414 sq ft33
B Wing1BHKT 50136.47 sq m · 393 sq ft11
B Wing1RK 00122.13 sq m · 238 sq ft10
B Wing2BHK 00246.89 sq m · 505 sq ft11
B Wing2BHK 202.402.60250.92 sq m · 548 sq ft31
B Wing2BHKT102.302.502.70251.69 sq m · 556 sq ft42

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Shirish Gajana Nachane—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Titwala

All 94 projects in Titwala · Compare Ved Residency with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology