Mixed · 2 buildings · 131 unitsRERA PM1330002501327

Sai Vrindavan

Deedo IDDP-THN-T16Q

It is due for completion in Apr 2029, with no extension on record; no MahaRERA orders on record; 0% of its units are booked.

Titwala, Thane 421605 · by Sai Siddhi Enterprises

DeliveryDue Apr 2029No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 131 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Apr 2029, with no extension on record

  • This projectRegistered 24 Oct 2025, completion promised 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002501327
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133000250132724 Oct 202530 Apr 202930 Apr 2029M/S Sai Siddhi EnterprisesProject page
Documents35

2 documents held by Deedo, 33 filings listed on MahaRERA's project page

Registration certificate (2)

Finance

  • PAN Card1 PANCARD.pdf · uploaded 11 Sep 2025Source
  • Others6 Certificate of Encumbrances.pdf · uploaded 11 Sep 2025Source
  • Others8 Undertaking under CERSAI.pdf · uploaded 11 Sep 2025Source
  • Others5.reply -Finance Signed.pdf · uploaded 15 Oct 2025Source
  • Others1. Bank Declaration -Mr. Vilas Sadanand Dalal 361.pdf · uploaded 19 Oct 2025Source
  • Others2. Bank Declaration -Mr. Rajankumar Dalal 362 & 363.pdf · uploaded 19 Oct 2025Source
Show all 35 documentsShow fewer documents

Finance

  • Others3. Bank Declaration -Rajeshwari Mahajan 364 & 365.pdf · uploaded 19 Oct 2025Source

Legal

  • Declaration Form B11 Form B- Firm.pdf · uploaded 9 Sep 2025Source
  • Declaration Form B18 7 12 paper.pdf · uploaded 11 Sep 2025Source
  • Others1 7 12 paper.pdf · uploaded 7 Oct 2025Source
  • Declaration Form B2 Title Report upload.pdf · uploaded 7 Oct 2025Source
  • OthersPartners Disclosure.pdf · uploaded 8 Oct 2025Source
  • Others6 Reply legal Signed.pdf · uploaded 15 Oct 2025Source
  • Declaration Form B4 Legal Title report Vilas Dalal Sr No-361.pdf · uploaded 15 Oct 2025Source
  • Declaration Form B1 7 12 paper.pdf · uploaded 15 Oct 2025Source

Migrated

  • Withdrawal Update Form 1Form-1 Q3.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 2Form-2 Q3 signed.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 3Form-3 Q3.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 1Form-1 Q4 Signed.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2Form-2 Q4 Signed.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3Form-3 Q4 Signed.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1Form-1 Saisiddhi.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Signed.pdf · uploaded 29 Jul 2026Source
  • Form 2A (FY 2025-2026)Form-2A Sai Siddhi.pdf · uploaded 4 Sep 2026Source
  • Form 5 (FY 2025-2026)Form 5 Signed.pdf · uploaded 4 Sep 2026Source

Technical

  • DocumentPlan Copy.pdf · uploaded 25 Aug 2025Source
  • DocumentPlan Copy.pdf · uploaded 25 Aug 2025Source
  • Document20 Annexure A.pdf · uploaded 12 Sep 2025Source
  • Others5 Declaration certificate of CC.pdf · uploaded 12 Sep 2025Source
  • OthersKDMC Mail Receipt.pdf · uploaded 8 Oct 2025Source

Technical (Architect)

  • DocumentForm-1 Saisiddhi.pdf · uploaded 29 Jul 2026Source

Technical (Engineer)

  • DocumentForm-2.pdf · uploaded 29 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 100, 367

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—70 units in all
Address
S.no.361 To 365 And 367, (New), S.no.187, H.no. 1 To 10(P) S.no.190 H.no.1 To 10(P) (Old) Plot No. 94 To 98 & 100PIN 421605
Village
Titwala, Kalyan taluka
Land area for this project
1,984 sq m (21,350 sq ft)
Permissible built-up area
3,584 sq m (38,573 sq ft)
Sanctioned built-up area
3,584 sq m (38,573 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
59
Developed in phases
Yes

Survey, CTS, gat or plot numbers

100367H.NO. 1 TO 10(P) S.NO.190 H.NO.1 TO 10(P) (OLD) PLOT NO. 94 TO 98S.NO.187S.NO.361 TO 365

Land as published on MahaRERA's project page

S.NO.361 TO 365 AND 367 ,(NEW), S.NO.187, H.NO. 1 TO 10(P) S.NO.190 H.NO.1 TO 10(P) (OLD) PLOT NO. 94 TO 98 & 100

Boundaries

North
18 mtr Road
South
9 Mtr Road
East
plot 94
West
Plot 98

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking70 units

70 units registered

— · 70 units
BuildingTypeCarpet areaUnits
Building No.1——57
Building No.2——13

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAniruddha S Dastane—
Chartered accountantCA SAGAR Joshi—
EngineerMr Umesh Sharad Joshi—
EngineerVaibhav Dayaram Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology