8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due341653 past their date
Median extension4 months36% of registrations extended
Regulatory cases66on 66 projects

8 in 10 registrations run late here

1,173 MahaRERA registrations in Ratnagiri and the places within it

93 not yet due248 extended, not yet due653 past even the latest date179 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ratnagiri

1,149 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vakratunda ApartmentShinde Builder and DevelopersDue Apr 2031, extended 4 mo——
Akanksha ResidencyShailesh Sudhakar PawarDue Sep 2028, extended 4 mo——
Yasmin ResidencyAltaf Ahmed BebalDue Apr 2030, extended 4 mo——
Aaditya PalaceBalajiaadi DevelopersDue Apr 2029, extended 4 mo——
Mahakali ResidencySameer Bhawanji VichareDue Apr 2028, extended 4 mo——
Sati DarshanS P DevelopersDue Apr 2029, extended 4 mo——
Business Bay For DapoliGreencity RealtyDue Jul 2028, extended 4 mo——
Pokar ResidencyDipak Mohanlal PokarDue Apr 2029, extended 4 mo——
Shreeniwas Residency Phase IISachin Manohar ShindeDue Apr 2029, extended 4 mo——
Indira Dattatray SankulOm Radhey DevelopersDue Apr 2030, extended 4 mo——
Swami PrasadVakratund DevelopersDue Apr 2030, extended 4 mo——
Vastu GauravDhanashri DevelopersDue Apr 2029, extended 4 mo——
Arihant Lake City Ph IIArihant Vastu Nirman Pvt. LtdDue Apr 2029, extended 4 mo——
Shigwan PlazaSachin Chandrakant ThasaleDue Apr 2029, extended 4 mo——
VarsaPushpam City Spaces Dapoli LLPDue Apr 2028, extended 4 mo——
Gajanan SankulKedar Prakash BhideDue Mar 2030, extended 4 mo——
Anita HeightsGajanan Builders and DevelopersDue Apr 2030, extended 4 mo——
Desai AuroraPrakash Vasudev DesaiDue Apr 2029, extended 4 mo——
Brahmachaitanya SrushtiManisha Rajaram SarfareDue Apr 2029, extended 4 mo——
Shree Mahakal HeightsSunil Shivpoojan GuptaDue Apr 2028, extended 4 mo——
12 VillasKaumudi Builders and DevelopersDue Apr 2028, extended 4 mo——
Gulmohar HeightM Square Builders And DevelopersDue Apr 2029, extended 4 mo——
Khan ResidencyMmm BuildconDue Jan 2027, extended 4 mo——
Darussalam ResidencyFakiabdulla Fakiumar MullajiDue Apr 2030, extended 4 mo——
Shreeram ResidencyRupesh Shriram BamaneDue Apr 2028, extended 4 mo——
Ratnagiri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Samir Shrinivas Kale29 projects
  2. Samir Shrinivas Kale22 projects
  3. Arihant Vastu Nirman Pvt. Ltd10 projects
  4. Prasad Prabhakar Waghdhare10 projects
  5. Dinesh Mohanlal Jain8 projects
  6. Jain And Jain Construction Company8 projects
  7. Akar Infrastructure6 projects
  8. Gandhi Developers5 projects
  9. Phatak Developers5 projects
  10. Prakash Vasudev Desai5 projects

Ratnagiri, in questions

How many projects in Ratnagiri run late?

8 in 10 MahaRERA registrations (901 of 1,173): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ratnagiri by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology