10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects20
Registrations20
Completion still due713 past their date
Median extension4 months45% of registrations extended
Regulatory cases1on 1 project

10 in 10 registrations run late here

20 MahaRERA registrations in Savarde

1 not yet due6 extended, not yet due13 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Savarde

20 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Galaxy HeightsIra Developers And AssociatesDue Apr 2032, extended 4 mo——
Laxmi Narayan HeightsBhairi Bhavani DevlopersDue Apr 2029, extended 4 mo——
Pokar ResidencyDipak Mohanlal PokarDue Apr 2029, extended 4 mo——
Mauli ResidencyIra DevelopersCompleted—46%
Dasman DreamMujeeb Abdul Rahiman PataitDue Apr 2028, extended 4 mo—26%
All 20 projects →
Savarde market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Tamanna Builders & Developers4 projects
  2. Ira Developers2 projects
  3. Arun Hanumantrao Salvi1 project
  4. Bhairi Bhavani Devlopers1 project
  5. Dipak Mohanlal Pokar1 project
  6. D K Properties 11 project
  7. Ira Developers And Associates1 project
  8. Konark Enterprises1 project
  9. Krishika Universal Realtors Private Limited1 project
  10. Krishika Universal Realtors Private Limited1 project

Savarde, in questions

How many projects in Savarde run late?

10 in 10 MahaRERA registrations (19 of 20): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Savarde by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology