Deedo IDDL-RAT-SAVARDE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects20
Registrations20
Completion still due713 past their date
Median extension4 months45% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
20 MahaRERA registrations in Savarde
1 not yet due6 extended, not yet due13 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Savarde
20 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Galaxy HeightsIra Developers And Associates | Due Apr 2032, extended 4 mo | — | — |
| Laxmi Narayan HeightsBhairi Bhavani Devlopers | Due Apr 2029, extended 4 mo | — | — |
| Pokar ResidencyDipak Mohanlal Pokar | Due Apr 2029, extended 4 mo | — | — |
| Mauli ResidencyIra Developers | Completed | — | 46% |
| Dasman DreamMujeeb Abdul Rahiman Patait | Due Apr 2028, extended 4 mo | — | 26% |
Nearby: other localities in Chiplun
Most active promoters
- Tamanna Builders & Developers4 projects
- Ira Developers2 projects
- Arun Hanumantrao Salvi1 project
- Bhairi Bhavani Devlopers1 project
- Dipak Mohanlal Pokar1 project
- D K Properties 11 project
- Ira Developers And Associates1 project
- Konark Enterprises1 project
- Krishika Universal Realtors Private Limited1 project
- Krishika Universal Realtors Private Limited1 project
Savarde, in questions
How many projects in Savarde run late?
10 in 10 MahaRERA registrations (19 of 20): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Savarde by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology