8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due341653 past their date
Median extension4 months36% of registrations extended
Regulatory cases66on 66 projects

8 in 10 registrations run late here

1,173 MahaRERA registrations in Ratnagiri and the places within it

93 not yet due248 extended, not yet due653 past even the latest date179 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ratnagiri

1,149 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Kohinoor Sai SparshJain and Jain Construction CoDue Apr 2030, extended 4 mo——
MHVG BungalowSamir Shrinivas KaleCompleted——
Unique ResidencyRed Bricks DevelopersDue Apr 2028, extended 4 mo——
J J TowersJjhk Realty LLPDue Apr 2029, extended 4 mo——
Nakoda PrimeKohinoor RealtorsDue Apr 2029, extended 4 mo——
United TowerUnited DevelopersDue Apr 2028, extended 4 mo——
Bamne TowerArsh ConstructionDue Apr 2029, extended 4 mo——
Ekta HeightsEkta DevelopersDue Apr 2028, extended 4 mo——
Uma Shankar ResidencyVaishali Devendra KherDue Apr 2030, extended 4 mo——
Abdul Gafoor ResidencyFaraz Anwar RakhangeDue Apr 2028, extended 4 mo——
Kohinoor EliteKalpsutra Construction CoDue Apr 2027, extended 4 mo——
MilestoneChandrashekhar Sadashiv LawateDue Sep 2027, extended 4 mo——
Arihant Desai TowerArihant Vastunirman Private LimitedDue Apr 2030, extended 4 mo——
Shahid ComplexAftab Kadir MaldarDue Apr 2029, extended 4 mo——
Vasant ResidencyIdate Builders And DevelopersDue Apr 2027, extended 4 mo——
Baig ResidencyShahid Abdulla RakhangeDue Apr 2029, extended 4 mo——
Aniket HeightsSwakarm Builders And DevelopersDue Apr 2028, extended 4 mo——
Sun City Phase - INitin Talathi & CoDue Apr 2029, extended 4 mo——
Akar Vanaju EstateAkar InfrastructureDue Dec 2040——
Shree Vinayak ResidencyMahaveer Tele LinkDue Jul 2028, extended 4 mo——
Madhuban HeightsRajesh M VajeDue Jan 2030, extended 4 mo——
Sai MandirSai Tapaswi BuildersDue Apr 2030, extended 4 mo——
Elite ParkSamir Mahamad GhareDue Apr 2027, extended 4 mo——
Silver CityUnity InfrastructuresDue Apr 2031, extended 4 mo—1%
Shreeji SparshShree Krishna BuildconDue Dec 2031, extended 4 mo—23%
Ratnagiri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Samir Shrinivas Kale29 projects
  2. Samir Shrinivas Kale22 projects
  3. Arihant Vastu Nirman Pvt. Ltd10 projects
  4. Prasad Prabhakar Waghdhare10 projects
  5. Dinesh Mohanlal Jain8 projects
  6. Jain And Jain Construction Company8 projects
  7. Akar Infrastructure6 projects
  8. Gandhi Developers5 projects
  9. Phatak Developers5 projects
  10. Prakash Vasudev Desai5 projects

Ratnagiri, in questions

How many projects in Ratnagiri run late?

8 in 10 MahaRERA registrations (901 of 1,173): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ratnagiri by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology