Skip to content
Deedo home
Menu

RERA projects in Gimhavane

9 projects under 9 MahaRERA registrations, registered 2017–2025. 33% have a completion date extended beyond the one promised.

9RERA projects
9Registrations
2Completion still due7 past their completion date
24 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20182
20191
20201
20212
20220
20230
20240
20251

Projects in Gimhavane

9 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shreeniwas Residency Phase IISachin Manohar ShindeP5280008029819 May 202531 Dec 2028—Not yet due0
Shriniwas ResidencySachin Manohar ShindeP5280003073313 Sep 202131 Aug 2026—Promised date passed0
Shree Swami Samarth ComplexRaj ConstructionP5280002925810 May 202131 Dec 202431 Dec 2026Extended 24 mo0
Nikunj HeightsSahil Ravindra KshirsagarP5280002405416 Jan 202030 Jan 202430 Jun 2025Extended 17 mo0
Misty WoodsKGM AssociatesP5280002096227 May 201920 Dec 2022—Promised date passed0
Zeenat HeightsMajid Usman KhalfeP5280001875730 Nov 201825 Dec 2021—Promised date passed0
Prishita ParadiseVirendra Pandurang MoreP528000154761 Mar 201815 Aug 2022—Promised date passed0
Green ParkJayant Yeshwant KolhatkarP5280000847919 Aug 201730 Jun 201930 Jun 2023Extended 48 mo0
Hill ViewOmm Infrastructure Housing CorporationP5280000646814 Aug 201730 Jun 2018—Promised date passed0

Other localities in Dapoli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sachin Manohar Shinde2 projects
  2. Jayant Yeshwant Kolhatkar1 project
  3. KGM Associates1 project
  4. Majid Usman Khalfe1 project
  5. Omm Infrastructure Housing Corporation1 project
  6. Raj Construction1 project
  7. Sahil Ravindra Kshirsagar1 project
  8. Virendra Pandurang More1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology