Asud, Ratnagiri
Deedo IDDL-RAT-ASUD10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects2
Registrations2
Completion still due11 past their date
Median extension26 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
2 MahaRERA registrations in Asud
1 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 26 months.
Projects in Asud
2 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Club OceanClub Ocean Land Developers LLP | Due Dec 2030, extended 4 mo | — | — |
| Casa Asud - Phase ISkyline Developers | Completed, extended 4 yrs | — | 16% |
Nearby: other villages in Dapoli
Most active promoters
- Club Ocean Land Developers LLP1 project
- Skyline Developers1 project
Asud, in questions
How many projects in Asud run late?
10 in 10 MahaRERA registrations (2 of 2): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Asud by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology