9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects33
Registrations36some projects hold several
Completion still due729 past their date
Median extension9 months42% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

36 MahaRERA registrations in Jalgaon

3 not yet due4 extended, not yet due29 past even the latest date

Extended registrations moved their completion date by a median of 9 months.

Projects in Jalgaon

33 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
VrindavanUmket Corporation LLPDue Jul 2028, extended 4 mo——
Vasant ResidencyIdate Builders And DevelopersDue Apr 2027, extended 4 mo——
Shree Vinayak ResidencyMahaveer Tele LinkDue Jul 2028, extended 4 mo——
Shree Sadguru KrupaPramay EnterprisesDue Apr 2028, extended 4 mo——
Madhuryash Phase IIMansi Rakesh Vichare6 mo late——
All 33 projects →
Jalgaon market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Poona Realtors Pvt Ltd3 projects
  2. Idate Builders And Developers2 projects
  3. Nitin Vishnu Barve2 projects
  4. Phatak Developers2 projects
  5. Pramay Enterprises2 projects
  6. Akshay Shridhar Phatak1 project
  7. Avishkar Developers1 project
  8. Buildnova Constructions1 project
  9. Dosti Developers1 project
  10. Dream House Construction1 project

Jalgaon, in questions

How many projects in Jalgaon run late?

9 in 10 MahaRERA registrations (33 of 36): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Jalgaon by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology