Mauje Dapoli, Ratnagiri

Deedo IDDL-RAT-MAUJEDAPOLI

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due22 past their date
Median extension4 months25% of registrations extended
Regulatory cases1on 1 project

8 in 10 registrations run late here

4 MahaRERA registrations in Mauje Dapoli

1 not yet due1 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Mauje Dapoli

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Abdul Gafoor ResidencyFaraz Anwar RakhangeDue Apr 2028, extended 4 mo——
Abdul Gafoor ResidencyKayum Ali ParkarCompleted——
Fatima ResidencyKayum Ali Parkar11 mo late——
Vighnaharta DeveloperVighnaharta DeveloperCompleted—70%
Mauje Dapoli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Kayum Ali Parkar2 projects
  2. Faraz Anwar Rakhange1 project
  3. Vighnaharta Developer1 project

Mauje Dapoli, in questions

How many projects in Mauje Dapoli run late?

8 in 10 MahaRERA registrations (3 of 4): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mauje Dapoli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology