RERA projects in Gavhe
3 projects under 3 MahaRERA registrations, registered 2017–2018. 33% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
0Completion still due3 past their completion date
36 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 1 |
Projects in Gavhe
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aparant Green HomeImage Developers | P52800017354 | 7 Aug 2018 | 30 Dec 2022 | 30 Dec 2025 | Extended 36 mo | 0 |
| Symphony Palms Phase 1Konkan Vikas Development Company Ltd | P52800013334 | 22 Sep 2017 | 1 Dec 2019 | — | Promised date passed | 0 |
| VrundavanEmpire Realtors And Developers | P52800010311 | 24 Aug 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
Other localities in Dapoli
Most active promoters
By projects registered here, as named on MahaRERA.
- Empire Realtors And Developers1 project
- Image Developers1 project
- Konkan Vikas Development Company Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology