Bhoste, Ratnagiri
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects3
Registrations3
Completion still due03 past their date
Median extension18 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Bhoste
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mariyam ApartmentAl Haq Builders Developers & Contractor Bhagidari Sanstha | P52800023340 | 12 Dec 2019 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Royal HeightsMudassar Jabbar Shaikh | P52800016194 | 23 Apr 2018 | 21 Jun 2023 | 21 Jun 2023 | Promised date passed | 0 |
| Mullaji ComplexGilam Husain Mohamed Ali Mullaji | P52800014824 | 8 Jan 2018 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
Nearby: other localities in Khed
Most active promoters
- Al Haq Builders Developers & Contractor Bhagidari Sanstha1 project
- Gilam Husain Mohamed Ali Mullaji1 project
- Mudassar Jabbar Shaikh1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology