RERA projects in Khed Bhadgaon
1 project under 1 MahaRERA registration, registered 2022–2022. 100% have a completion date extended beyond the one promised.
1RERA projects
1Registrations
0Completion still due1 past their completion date
12 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 1 |
Projects in Khed Bhadgaon
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Galaxy Complex Phase 2Khalid Hussain Mullaji | P52800034855 | 28 Apr 2022 | 31 Mar 2025 | 31 Mar 2026 | Extended 12 mo | 0 |
Other localities in Khed
- Khed (M Cl)57 projects
- Bharane20 projects
- Bharana Naka13 projects
- Khedbhadgaon10 projects
- Dhamandivi8 projects
- Veral8 projects
- Bhoste3 projects
- Lote3 projects
- Boraj2 projects
- Ghanekhunt2 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Khalid Hussain Mullaji1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology