Lote, Ratnagiri
Deedo IDDL-RAT-LOTENo MahaRERA registration here has an extended completion date on record.
RERA projects3
Registrations3
Completion still due12 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
3 MahaRERA registrations in Lote
1 not yet due2 past even the latest date
Projects in Lote
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shree Samarth Krupa SankalpAshwini Sachin Kuchekar | Due Oct 2028 | — | — |
| Paras EnclaveParas Infrastructure | 4 mo late | — | — |
| Shamal ResidencyRavindra Gopal Kulkarni | 6 yrs 10 mo late | — | 50% |
Nearby: other localities in Khed
Most active promoters
- Ashwini Sachin Kuchekar1 project
- Paras Infrastructure1 project
- Ravindra Gopal Kulkarni1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology