Skip to content

RERA projects in Rahataghar

20 projects under 20 MahaRERA registrations, registered 2017–2025. 20% have a completion date extended beyond the one promised.

Locality
20RERA projects
20Registrations
5Completion still due15 past their completion date
6 monthsMedian extension beyond promised date20% of registrations extended
0Regulatory casesnone on MahaRERA's lists
25Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20179
20181
20191
20202
20212
20221
20233
20240
20251

Projects in Rahataghar

20 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sagar SparshAbhay Mahendra JainP528000808961 Aug 202531 Dec 203030 Apr 2031Extended 4 mo0
Rajlaxmi SankulDinesh Mohanlal JainP5280005404227 Dec 202331 Dec 202830 Apr 2029Extended 4 mo0
Shri Ganesh ResidencyVallabh Ravindra DamleP5280005334627 Oct 202331 Dec 202831 Dec 2028Not yet due0
Kohinoor TulipJain And Jain Construction CompanyP5280004897024 Jan 202331 Dec 202531 Dec 2025Promised date passed0
Omkar VishwaPrasad Prabhakar WaghdhareP528000330969 Feb 202231 Dec 202631 Dec 2026Not yet due0
Padmavatee VatikaAbhay Mahendra JainP5280003149725 Oct 202131 Dec 202431 Dec 2024Promised date passed0
Rakhumai VatsalyaNitin Anilkumar KanvindeP5280003099129 Sep 202131 Dec 202531 Dec 2025Promised date passed0
Amod ResidencyManoj Sham GhudeP5280002711719 Nov 202020 May 202320 May 2023Promised date passed0
Royal ParmeshwarRoyal InfraP5280002638016 Sep 20201 Aug 202331 Jul 2024Extended 11 mo0
Usha Bhaskar Chiplunkar SankulPrashant Manohar DingankarP5280002093923 May 20191 Nov 20201 Nov 2020Promised date passed0
Anantsudha ApartmentRajyog DevelopersP5280001644311 May 201830 Apr 202330 Apr 2023Promised date passed0
Shree Datta SankulShashikant Gangadhar PatwardhanP5280001064231 Aug 20171 Aug 20231 Aug 2023Promised date passed0
Mahalaxmi ArcadeSandeep Shashikant NerlekarP5280000999923 Aug 201731 Oct 201831 Oct 2018Promised date passed0
Shri GajananUtsahi Liladhar ChavandeP5280000984222 Aug 201731 Dec 202631 Dec 2026Not yet due0
Madhukrishna Chs LtdBuilt Tech Builders & Developers Pvt. Ltd.P5280000881419 Aug 201731 Dec 201931 Dec 2019Promised date passed0
Jugai GardensPrashant Manohar DingankarP5280000625814 Aug 20171 Jun 20181 Jun 2018Promised date passed0
Waghu ResidencyNeelkanth ProsperityP5280000553411 Aug 20177 Jun 201917 Feb 2020Extended 8 mo0
Suresh smrutiPrasad Prabhakar WaghdhareP528000040937 Aug 201721 Jan 201821 Jan 2018Promised date passed0
Kohinoor Crystal E wingJain And Jain Construction CompanyP528000033845 Aug 201730 Mar 202230 Mar 2022Promised date passed0
Aathley SankulArihant Vastu Nirman Pvt. LtdP528000000188 Jun 20171 Dec 20181 Dec 2018Promised date passed0

Other localities in Ratnagiri

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Abhay Mahendra Jain2 projects
  2. Jain And Jain Construction Company2 projects
  3. Prasad Prabhakar Waghdhare2 projects
  4. Prashant Manohar Dingankar2 projects
  5. Arihant Vastu Nirman Pvt. Ltd1 project
  6. Built Tech Builders & Developers Pvt. Ltd.1 project
  7. Dinesh Mohanlal Jain1 project
  8. Manoj Sham Ghude1 project
  9. Neelkanth Prosperity1 project
  10. Nitin Anilkumar Kanvinde1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology